US overhauls electric grid to make way for more renewables

By Valerie Volcovici
May 13, 20245:37 PM EDT

WASHINGTON, May 13 (Reuters) - The U.S. Federal Energy Regulatory Commission on Monday approved the first major electric transmission policy update in over a decade that aims to speed up new interregional lines to move more clean energy to meet growing demand amid the explosion of electric vehicles, data centers and artificial intelligence.
Approved in a 2-1 vote, the new rule is also the first time the FERC has ever squarely addressed the need for long-term transmission planning, playing a key role in helping meet the Biden administration's goal of decarbonizing the economy by 2050 and making the grid more resilient to more frequent climate-fueled extreme weather events.
"This rule cannot come fast enough," FERC Chairman Willie Phillips, who voted for the final rule. "There is an urgent need to act to ensure the reliability and the affordability of our grid."
"We are at a transformational moment for the electric grid with phenomenal load growth," he added, citing the surge in domestic manufacturing, proliferation of data centers, and the surge in extreme weather events that have pushed the country's ageing infrastructure to its limits.
FERC has been working for nearly two years on the rule to reform how new electric transmission gets approved and paid for, with new requirements for moving electricity across states and covering the costs of new projects.
FERC said that reforms to transmission planning received over 30,000 pages of comments, creating the largest public record ever considered by the commission.
The final rule requires transmission owners to conduct 20-year plans assessing regional electric transmission needs that would need to be revisited every five years.
It also requires transmission project participants to submit plans for how to split costs between states and companies; weigh seven specific benefits during the review process to determine whether transmission proposals will meet long-term needs cost effectively and gives operators the ability to re-evaluate projects that face cost-overruns or delays.
Before applicants submit plans, they would be required to hold a six-month engagement period with state agencies.
It also asks operators to identify opportunities to modify existing transmission facilities instead of replacing them when needed, a process known as “right-sizing” and to hold public meetings during the regional transmission planning cycle.
BEYOND FERC'S MANDATE?
President Joe Biden's administration has a goal of a carbon-free power sector by 2035, in order to fight climate change.
To meet that target, the country needs to more than double regional transmission capacity and expand interregional transmission capacity more than fivefold, a U.S. Department of Energy study said in November.
Boosted by tax incentives in Biden's 2022 Inflation Reduction Act (IRA), the queue of power generation projects awaiting a connection to the electric grid is currently around 2,600 gigawatts, twice the amount of generation of the current U.S. power plant fleet, as the grid struggles to integrate new wind, solar and battery power.
FERC Commissioner Mark Christie, who opposed the final transmission planning rule, said in his dissenting remarks that the commission rushed through the process and attempted to impose a major policy shift that favors renewables that went beyond FERC's mandate.
"This rule is a pretext to enact a sweeping policy agenda that Congress never passed," Christie said. "A policy that is intended to facilitate a massive transfer of wealth from consumers to for-profit, special interests, particularly generation developers - primarily wind and solar transmission developers and influential powerful corporations with preferences as to the types of power they want to purchase."
Republican Senator John Barrasso of Wyoming said it could make some states "foot the bill" to bring more renewable energy online and "force customers – often in rural states – to pay for new transmission lines even when those lines don’t provide any meaningful benefit to them."
All three commissioners also approved on Monday a separate but related order that would give FERC backstop siting authority to approve permits for interstate transmission projects that have been rejected or not acted upon by states.
That order also codified a code of conduct for project participants to engage with communities, conduct early outreach with Native American tribes and issue an environmental justice resource report.
"FERC’s backstop siting rule will help ensure that no one state can veto transmission lines that............................

https://www.reuters.com/business/energy/ferc-overhaul-us-electric-t...

************************************* 


Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.

 

Views: 49

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Willem Post on May 17, 2024 at 4:38pm

APPENDIX 1

World Offshore Wind Capacity Placed on Operation in 2021

During 2021, worldwide offshore wind capacity placed in operation was 17,398 MW, of which China 13,790 MW, and the rest of the world 3,608 MW, of which UK 1,855 MW; Vietnam 643 MW; Denmark 604 MW; Netherlands 402 MW; Taiwan 109 MW

Of the 17,398 MW, just 57.1 MW was floating, about 1/3%

At end of 2021, 50,623 MW was in operation, of which just 123.4 MW was floating, about 1/4%

https://www.energy.gov/eere/wind/articles/offshore-wind-market-repo...

 

Floating Offshore Wind Systems in the Impoverished State of Maine

https://www.windtaskforce.org/profiles/blogs/floating-offshore-wind...

Despite the meager floating offshore MW in the world, pro-wind politicians, bureaucrats, etc., aided and abetted by the lapdog Main Media and "academia/think tanks", in the impoverished State of Maine, continue to fantasize about building 3,000 MW of 850-ft-tall floating offshore wind turbines by 2040!!

 

Maine government bureaucrats, etc., in a world of their own climate-fighting fantasies, want to have about 3,000 MW of floating wind turbines by 2040; a most expensive, totally unrealistic goal, that would further impoverish the already-poor State of Maine for many decades.

 

Those bureaucrats, etc., would help fatten the lucrative, 20-y, tax-shelters of mostly out-of-state, multi-millionaire, wind-subsidy chasers, who likely have minimal regard for:

 

1) Impacts on the environment and the fishing and tourist industries of Maine, and

2) Already-overstressed, over-taxed, over-regulated Maine ratepayers and taxpayers, who are trying to make ends meet in a near-zero, real-growth economy.

 

Those fishery-destroying, 850-ft-tall floaters, with 24/7/365 strobe lights, visible 30 miles from any shore, would cost at least $7,500/ installed kW, or at least $22.5 billion, if built in 2023 (more after 2023)

 

Almost the entire supply of the Maine projects would be designed and made in Europe, then transported across the Atlantic Ocean, in European specialized ships, then unloaded at a new, $500-million Maine storage/pre-assembly/staging/barge-loading area, then barged to European specialized erection ships for erection of the floating turbines. The financing will be mostly by European pension funds paying pensions to retirees.

 

About 300 Maine people would have jobs during the erection phase

The other erection jobs would be by specialized European people, mostly on cranes and ships

About 100 Maine people would have long-term O&M jobs, using European spare parts, during the 20-y electricity production phase.

https://www.maine.gov/governor/mills/news/governor-mills-signs-bill...

 

The Maine woke bureaucrats are falling over each other to prove their “greenness”, offering $millions of this and that for free, but all their primping and preening efforts has resulted in no floating offshore bids from European companies

 

The Maine people have much greater burdens to look forward to for the next 20 years, courtesy of the Governor Mills incompetent, woke bureaucracy that has infested the state government 

 

The Maine people need to finally wake up, and put an end to the climate scare-mongering, which aims to subjugate and further impoverish them, by voting the entire Democrat woke cabal out and replace it with rational Republicans in 2024

The present course leads to financial disaster for the impoverished State of Maine and its people.

The purposely-kept-ignorant Maine people do not deserve such maltreatment

 

Electricity Cost: Assume a $750 million, 100 MW project consists of foundations, wind turbines, cabling to shore, and installation at $7,500/kW.

Production 100 MW x 8766 h/y x 0.40, CF = 350,640,000 kWh/y

Amortize bank loan for $525 million, 70% of project, at 6.5%/y for 20 years, 13.396 c/kWh.

Owner return on $225 million, 30% of project, at 10%/y for 20 years, 7.431 c/kWh

Offshore O&M, about 30 miles out to sea, 8 c/kWh.

Supply chain, special ships, and ocean transport, 3 c/kWh

All other items, 4 c/kWh 

Total cost 13.396 + 7.431 + 8 + 3 + 4 = 35.827 c/kWh

Less 50% subsidies (ITC, 5-y depreciation, interest deduction on borrowed funds) 17.913 c/kWh

Owner sells to utility at 17.913 c/kWh

 

NOTE: The above prices compare with the average New England wholesale price of about 5 c/kWh, during the 2009 - 2022 period, 13 years, courtesy of:

 

Gas-fueled CCGT plants, with low-cost, low-CO2, very-low particulate/kWh

Nuclear plants, with low-cost, near-zero CO2, zero particulate/kWh

Hydro plants, with low-cost, near-zero-CO2, zero particulate/kWh

Cabling to Shore Plus $Billions for Grid Expansion on Shore: A high voltage cable would be hanging from each unit, until it reaches bottom, say about 200 to 500 feet. 
The cables would need some type of flexible support system

There would be about 5 cables, each connected to sixty, 10 MW wind turbines, making landfall on the Maine shore, for connection to 5 substations (each having a 600 MW capacity, requiring several acres of equipment), then to connect to the New England HV grid, which will need $billions for expansion/reinforcement to transmit electricity to load centers, mostly in southern New England.

 

Floating Offshore a Major Financial Burden on Maine People: Rich Norwegian people can afford to dabble in such expensive demonstration follies (See Appendix 2), but the over-taxed, over-regulated, impoverished Maine people would buckle under such a heavy burden, while trying to make ends meet in the near-zero, real-growth Maine economy. Maine folks need lower energy bills, not higher energy bills.

 

APPENDIX 2

Floating Offshore Wind in Norway

Equinor, a Norwegian company, put in operation, 11 Hywind, floating offshore wind turbines, each 8 MW, for a total of 88 MW, in the North Sea. The wind turbines are supplied by Siemens, a German company

Production will be about 88 x 8766 x 0.5, claimed lifetime capacity factor = 385,704 MWh/y, which is about 35% of the electricity used by 2 nearby Norwegian oil rigs, which cost at least $1.0 billion each.

On an annual basis, the existing diesel and gas-turbine generators on the rigs, designed to provide 100% of the rigs electricity requirements, 24/7/365, will provide only 65%, i.e., the wind turbines have 100% back up.

The generators will counteract the up/down output of the wind turbines, on a less-than-minute-by-minute basis, 24/7/365

The generators will provide almost all the electricity during low-wind periods, and 100% during high-wind periods, when rotors are feathered and locked.

The capital cost of the entire project was about 8 billion Norwegian Kroner, or about $730 million, as of August 2023, when all 11 units were placed in operation, or $730 million/88 MW = $8,300/kW. See URL

That cost was much higher than the estimated 5 billion NOK in 2019, i.e., 60% higher

The project is located about 70 miles from Norway, which means minimal transport costs of the entire supply to the erection sites

The project produces electricity at about 42 c/kWh, no subsidies, at about 21 c/kWh, with 50% subsidies 

In Norway, all work associated with oil rigs is very expensive.

Three shifts of workers are on the rigs for 6 weeks, work 60 h/week, and get 6 weeks off with pay, and are paid well over $150,000/y, plus benefits.

If Norwegian units were used in Maine, the production costs would be even higher in Maine, because of the additional cost of transport of almost the entire supply, including specialized ships and cranes, across the Atlantic Ocean, plus

A high voltage cable would be hanging from each unit, until it reaches bottom, say about 200 to 500 feet. 

The cables would need some type of flexible support system
The cables would be combined into several cables to run horizontally to shore, for at least 25 to 30 miles, to several onshore substations, to the New England high voltage grid.

.

https://www.offshore-mag.com/regional-reports/north-sea-europe/arti...

https://en.wikipedia.org/wiki/Floating_wind_turbine

.

.

APPENDIX 3

Offshore Wind in US and UK

Most folks, seeing only part of the picture, write about wind energy issues that only partially cover the offshore wind situation, which caused major declines of the stock prices of Siemens, Oersted, etc., starting at the end of 2020; the smart money got out
All this well before the Ukraine events, which started in February 2022. See costs/kWh in below article

US/UK Governments Offshore Wind Goals

1) 30,000 MW of offshore by 2030, by the cabal of climate extremists in the US government 
2) 36,000 MW of offshore by 2030, and 40,000 MW by 2040, by the disfunctional UK government

 

Those US/UK goals are physically unachievable, even with abundant, low-cost financing, and low inflation, and low-cost energy, materials, labor, and a robust, smooth-running supply chain, to place in service about 9500 MW of offshore during each of the next 7 years, from start 2024 to end 2030, which has never been done before in such a short time. See URL
 
US/UK 66,000 MW OF OFFSHORE WIND BY 2030; AN EXPENSIVE FANTASY  
https://www.windtaskforce.org/profiles/blogs/biden-30-000-mw-of-off...

US Offshore Wind Electricity Production and Cost

Electricity production about 30,000 MW x 8766 h/y x 0.40, lifetime capacity factor = 105,192,000 MWh, or 105.2 TWh. The production would be about 100 x 105.2/4000 = 2.63% of the annual electricity loaded onto US grids.

Electricity Cost, c/kWh: Assume a $550 million, 100 MW project consists of foundations, wind turbines, cabling to shore, and installation, at $5,500/kW.

Production 100 MW x 8766 h/y x 0.40, CF = 350,640,000 kWh/y

Amortize bank loan for $385 million, 70% of project, at 6.5%/y for 20 y, 9.824 c/kWh.

Owner return on $165 million, 30% of project, at 10%/y for 20 y, 5.449 c/kWh

Offshore O&M, about 30 miles out to sea, 8 c/kWh.

Supply chain, special ships, ocean transport, 3 c/kWh

All other items, 4 c/kWh 

Total cost 9.824 + 5.449 + 8 + 3 + 4 = 30.273 c/kWh

Less 50% subsidies (ITC, 5-y depreciation, interest deduction on borrowed funds) 15.137 c/kWh

Owner sells to utility at 15.137 c/kWh; developers in NY state, etc., want much more. See Above.

 

Not included: At a future 30% wind/solar penetration on the grid:   

Cost of onshore grid expansion/reinforcement, about 2 c/kWh

Cost of a fleet of plants for counteracting/balancing, 24/7/365, about 2.0 c/kWh

In the UK, in 2020, it was 1.9 c/kWh at 28% wind/solar loaded onto the grid

Cost of curtailments, about 2.0 c/kWh

Cost of decommissioning, i.e., disassembly at sea, reprocessing and storing at hazardous waste sites

.

APPENDIX 4

Levelized Cost of Energy Deceptions, by US-EIA, et al.

Most people have no idea wind and solar systems need grid expansion/reinforcement and expensive support systems to even exist on the grid.

With increased annual W/S electricity percent on the grid, increased grid investments are needed, plus greater counteracting plant capacity, MW, especially when it is windy and sunny around noon-time.

Increased counteracting of the variable W/S output, places an increased burden on the grid’s other generators, causing them to operate in an inefficient manner (more Btu/kWh, more CO2/kWh), which adds more cost/kWh to the offshore wind electricity cost of about 16 c/kWh, after 50% subsidies

The various cost/kWh adders start with annual W/S electricity at about 8% on the grid.

The adders become exponentially greater, with increased annual W/S electricity percent on the grid

 

The US-EIA, Lazard, Bloomberg, etc., and their phony LCOE "analyses", are deliberately understating the cost of wind, solar and battery systems

Their LCOE “analyses” of W/S/B systems purposely exclude major LCOE items.

Their deceptions reinforced the popular delusion, W/S are competitive with fossil fuels, which is far from reality.

The excluded LCOE items are shifted to taxpayers, ratepayers, and added to government debts.

W/S would not exist without at least 50% subsidies

W/S output could not be physically fed into the grid, without items 2, 3, 4, 5, and 6. See list.

 

1) Subsidies equivalent to about 50% of project lifetime owning and operations cost,

2) Grid extension/reinforcement to connect remote W/S systems to load centers

3) A fleet of quick-reacting power plants to counteract the variable W/S output, on a less-than-minute-by-minute basis, 24/7/365 

4) A fleet of power plants to provide electricity during low-W/S periods, and 100% during high-W/S periods, when rotors are feathered and locked,

5) Output curtailments to prevent overloading the grid, i.e., paying owners for not producing what they could have produced

6) Hazardous waste disposal of wind turbines, solar panels and batteries. See image.

.

APPENDIX  5

BATTERY SYSTEM CAPITAL COSTS, OPERATING COSTS, ENERGY LOSSES, AND AGING
https://www.windtaskforce.org/profiles/blogs/battery-system-capital...

EXCERPT:

Annual Cost of Megapack Battery Systems; 2023 pricing
Assume a system rated 45.3 MW/181.9 MWh, and an all-in turnkey cost of $104.5 million, per Example 2
Amortize bank loan for 50% of $104.5 million at 6.5%/y for 15 years, $5.484 million/y
Pay Owner return of 50% of $104.5 million at 10%/y for 15 years, $6.765 million/y (10% due to high inflation)
Lifetime (Bank + Owner) payments 15 x (5.484 + 6.765) = $183.7 million
Assume battery daily usage for 15 years at 10%, and loss factor = 1/(0.9 *0.9)
Battery lifetime output = 15 y x 365 d/y x 181.9 MWh x 0.1, usage x 1000 kWh/MWh = 99,590,250 kWh to HV grid; 122,950,926 kWh from HV grid; 233,606,676 kWh loss
(Bank + Owner) payments, $183.7 million / 99,590,250 kWh = 184.5 c/kWh
Less 50% subsidies (ITC, depreciation in 5 years, deduction of interest on borrowed funds) is 92.3c/kWh
At 10% throughput, (Bank + Owner) cost, 92.3 c/kWh
At 40% throughput, (Bank + Owner) cost, 23.1 c/kWh
 
Excluded costs/kWh: 1) O&M; 2) system aging, 1.5%/y, 3) 20% HV grid-to-HV grid loss, 4) grid extension/reinforcement to connect battery systems, 5) downtime of parts of the system, 6) decommissioning in year 15, i.e., disassembly, reprocessing and storing at hazardous waste sites. Excluded costs would add at least 15 c/kWh
 

COMMENTS ON CALCULATION

Almost all existing battery systems operate at less than 10%, per EIA annual reports i.e., new systems would operate at about 92.4 + 15 = 107.4 c/kWh. They are used to stabilize the grid, i.e., frequency control and counteracting up/down W/S outputs. If 40% throughput, 23.1 + 15 = 38.1 c/kWh.

A 4-h battery system costs 38.1 c/kWh of throughput, if operated at a duty factor of 40%. That is on top of the cost/kWh of the electricity taken from the HV grid to feed the batteries

Up to 40% could occur by absorbing midday solar peaks and discharging during late-afternoon/early-evening, which occur every day in California and other sunny states. The more solar systems, the greater the peaks.

We are not even talking about longer-term storage, as during a multi-day W/S lull.

40% throughput is close to Tesla’s recommendation of 60% maximum throughput, i.e., not charging above 80% full and not discharging below 20% full, to achieve a 15-y life, with normal aging.

Tesla’s recommendation was not heeded by the Owners of the Hornsdale Power Reserve in Australia. They excessively charged/discharged the system. After a few years, they added Megapacks to offset rapid aging of the original system, and added more Megapacks to increase the rating of the expanded system.

http://www.windtaskforce.org/profiles/blogs/the-hornsdale-power-reserve-largest-battery-system-in-australia

Regarding any project, the bank and Owner have to be paid, no matter what. I amortized the bank loan and Owner’s investment

Divide total payments over 15 years by the throughput during 15 years, you get c/kWh, as shown.

There is about a 20% round-trip loss, from HV grid to 1) step-down transformer, 2) front-end power electronics, 3) into battery, 4) out of battery, 5) back-end power electronics, 6) step-up transformer, to HV grid, i.e., you draw about 50 units from the HV grid to deliver about 40 units to the HV grid, because of A-to-Z system losses. That gets worse with aging.

A lot of people do not like these c/kWh numbers, because they have been repeatedly told by self-serving folks, battery Nirvana is just around the corner.

Comment by Willem Post on May 15, 2024 at 2:13pm

Urban Heat Archipelagos

UHAs, such as on the US East Coast, from Portland, Maine, to Norfolk, Virginia, significantly contribute to local warming. That area used to be covered with forests.

Many large solar systems in the US Southwest add up to a heat archipelago, plus the very hot PV panels have very low efficiencies at high temperatures 

Adaptation, such as increasing the width and height of dikes, and capacities of culvert and storm sewer systems, etc., planting billions of trees each year, rebuilding the rain forests, etc., will be required.

Because, huge quantities of solar energy are collected in the Tropics to warm the planet each day, preservation of the world's rain forest belt is vital for the future well-being of the earth.
That should have priority over expensive, unfeasible, wind/solar/battery/EV/heat pump, etc., measures, implemented mostly in temperate zones.

.

.
Important Role of CO2 for Flora and Fauna Growth
Plants require require at least 1000 to 1200 ppm of CO2, as proven in greenhouses
Many plants have become extinct, along with the fauna they supported, due to a lack of CO2
As a result, many areas of the world became arid and deserts.
The current CO2 needs to at least double or triple
Earth temperature increased about 1.2 C since 1900, which is due to many causes, such as fossil CO2, flora CO2, and permafrost methane which converts to CO2.
.
CO2 emissions of fossil fuels are a blessing.
CO2 has increased from about 296 ppm end 1900 to 421.08 ppm end 2023, and
1) Increased world greening by at least 10 to 15%, as measured by satellites since 1979. Increased greening produces oxygen by photosynthesis. It forms a filter in the upper atmosphere that absorbs harmful UV radiation, with wavelengths below 240 nm.
2) Increased world fauna
3) Increased crop yields per acre.
4) Reduced world desert areas

.

Fossil fuel CO2 was 37.55 Gt, or 4.8 ppm in 2023, about 68% of total human CO2. See URL.

https://gml.noaa.gov/webdata/ccgg/trends/co2/co2_annmean_mlo.txt

CO2 (human + natural) was 418.53 in 2022; 421.08 ppm in 2023

The rest of CO2 (human + natural) was absorbed by oceans and other sinks; each CO2 ppm = 7.821 Gt

The Mauna Loa curve shows an annual variation of 8 - 9 ppm during a year, due to biomass growth and decay.

Photosynthesis 6CO2 + 6H2O → C6H12O6 (glucose) + 6O2

We need more biomass that uses CO2 to produce O2. See URL 

.
https://www.windtaskforce.org/profiles/blogs/new-study-2001-2020-gl...

https://www.windtaskforce.org/profiles/blogs/co2-is-not-pollution-i...

https://www.windtaskforce.org/profiles/blogs/summary-of-world-co2eq...

https://issuu.com/johna.shanahan/docs/co2_pitch_4-3-24_baeuerle_eng...

Oceans Absorb CO2

Sea water contains 3.5% salt, NaCl, by weight.

CO2 molecules continuously move from the air into sea water, per Henry’s Law

CO2 and NaCl form many compounds that contain C, O2, H2, Cl. They sustain flora and fauna in the oceans.

At the surface, seawater pH = 8.1, CO2 423 ppm, the % presence of [CO2], [HCO3−], and [CO3 2−] is 0.5, 89, and 10.5; “Free” CO2 molecules at the surface, is only 0.5%; CO2 out-migration is minimal, given the conditions.
As a result, the oceans are a major sink of CO2 (human + natural) in the TS.
At least 40% of new CO2 (human + natural) in the TS, is added to the oceans; about 50% stays in the TS 

https://tos.org/oceanography/assets/docs/14-4_feely.pdf

.

Comment by Willem Post on May 14, 2024 at 7:30am

The US spends $BILLIONS PER YEAR to expand and reinforce the ONSHORE electric grids to connect the VARIABLE, WEATHER-DEPENDENT outputs of wind and solar systems, that are spread out far and wide.

Remember, these grids were perfectly adequate before the $disturbing W/S systems

Traditional power plants are screwed, because they are forced to operate less efficiently than they could have, to counteract the up/down outputs of W/S systems, 24/7/365, as happened in Europe.

They do not get paid to perform that grid stabilizing $service.

The sooner the expensive, whale/porpoise and bird/bat and lobster/fisheries killing wind systems are abandoned, the better.

Almost all of the offshore supply of these systems is shipped in specialized ships, owned by European conglomerates, that are sucking on US subsidies

Those conglomerates also supply and install spare parts and perform much of the maintenance using specialized ships and tools.

All the US gets out of this is being screwed over with higher electricity prices, and a lower standard of living, as happened in Europe, California, etc.

However, it is great for Europe to knock the US even more out of world markets.

The Europeans already have about $10 TRILLION of direct investments in the US, which provides them with about a $1 TRILLION income per year, on top of their about $1 TRILLION per year trade surplus.

The Europeans have only $280 BILLION of direct investments in Russia, with a much smaller economy than the US.

The Europeans want to steal $300 BILLION of blocked Russian sovereign assets to pay Ukraine costs, but Russia would just expropriate their $280 BILLION of direct investments in Russia; tit for tat.

Politicians, in Democrat and RINO states, who don’t see the forest for the trees, are aiding and abetting these W/S scams that are mostly benefiting the elites.

They are lying through their teeth to justify these scams, using the scare-mongering hoax of global warming.

Comment by Dan McKay on May 14, 2024 at 6:59am

"Climate-fueled extreme weather events"?  This is a government, politically biased agency fueled by idiots who are fueling a narrative of fuelish interpretation of the weather and weather driven renewables. Build reliable gas-fired, coal-fired, hydro or nuclear plants close to the load centers, it is that simple. The majority of people on Earth understand cheap, reliable electricity fuels civilization.

Comment by Monique Aniel Thurston on May 13, 2024 at 6:10pm

Anybody who voted for Biden should have had a V8 .

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service