By Willem Post

.

A recent announcement is for a statewide, 4-h battery system, installed capacity 5000 MW/20,000 MWh.

Tesla recommends not charging to more than 80% full and not discharging to less than 20% full, to achieve normal life of 15 years and normal aging at 1.5%/y.
The delivered capacity would be 20,000 MWh x 0.6, Tesla factor x aging factor x 0.9, outage factor = 10,800 MWh

The batteries would 1) absorb midday solar peaks and deliver the electricity during peak hours of late afternoon/early evening, and 2) stabilize the grid, due to varying W/S output, 24/7/365

The turnkey cost would be about $600/installed kWh, delivered as AC at battery outlet, 2024 pricing, or $600/kWh x 20 million kWh = $12.0 billion, about every 15 years.

There will be annually increasing insurance costs for risky W/S/B projects.

If 50% were borrowed from banks, the cost of amortizing $6 billion at 6% over 15 years = $608 million/y

If 50% were from Owners, the cost of amortizing $6 billion at 10% over 15 years = $774 million/y

The two items total $1,382 million/y; another hell-of-a-big subsidy for W/S systems

There are many more cost items

Less 50% subsidies (tax credits, 5-y depreciation, loan interest deduction, etc.)

Subsidies shift costs from project Owners to ratepayers, taxpayers, government debt

https://www.windtaskforce.org/profiles/blogs/battery-system-capital...

.

No banks will finance W/S/B projects at acceptable interest rates and no insurance companies will insure them at acceptable premiums, no matter what the leftist, woke bureaucrats are announcing.
The sooner the U-turn, the better for New England, the US and Europe

.

NOTE: Trump has declared a National Energy Emergency. A new gas line from Pennsylvania to New England and new gas/oil storage systems near each CCGT power plant are needed, because most of the “planned” W/S/B systems will never be built, especially after the application of tariffs.

Views: 49

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/