THE DYSFUNCTIONAL STATE OF MASSACHUSETTS WITH GIANT BATTERIES
https://www.windtaskforce.org/profiles/blogs/the-dysfunctional-stat...
By Willem Post
.
A recent announcement is to install a statewide, 4-h battery system, installed capacity 5000 MW/20,000 MWh.
Tesla recommends not charging to more than 80% full and not discharging to less than 20% full, to achieve normal life of 15 years and normal aging at 1.5%/y.
The delivered capacity would be 20,000 MWh x 0.6, Tesla factor x aging factor x 0.9, outage factor = 10,800 MWh
The batteries would 1) absorb midday solar peaks and deliver the electricity during peak hours of late afternoon/early evening, and 2) stabilize the grid, due to varying W/S output, 24/7/365
The turnkey cost would be about $600/installed kWh, delivered as AC at battery outlet, 2024 pricing, or $600/kWh x 20 million kWh = $12.0 billion, about every 15 years.
I did not mention annually increasing insurance costs of risky W/S projects.
If 50% were borrowed from banks, the cost of amortizing $6 billion at 6% over 15 years = $608 million/y
If 50% were from Owners, the cost of amortizing $6 billion at 10% over 15 years = $774 million/y
The two items total $1,382 million/y; another hell-of-a-big subsidy for W/S systems
There are many more cost items
Less 50% subsidies (tax credits, 5-y depreciation, loan interest deduction)
Subsidies shift costs from project Owners to ratepayers, taxpayers, government debt
https://www.windtaskforce.org/profiles/blogs/battery-system-capital...
.
No banks will finance W/S projects at acceptable interest rates and no insurance companies will insure them at acceptable premiums, no matter what the woke bureaucrats are announcing.
The sooner the U-turn, the better for the New England, the US and Europe
U.S. Sen Angus King
Maine as Third World Country:
CMP Transmission Rate Skyrockets 19.6% Due to Wind Power
Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.
Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT
******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********
(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/
Not yet a member?
Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?
We have the facts on our side. We have the truth on our side. All we need now is YOU.
“First they ignore you, then they laugh at you, then they fight you, then you win.”
-- Mahatma Gandhi
"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi
Task Force membership is free. Please sign up today!
Hannah Pingree - Director of Maine's Office of Innovation and the Future
"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."
https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/