Massachusetts Offshore Wind Companies Pick Cheapest Route

Correct Method Using All Submarine Cables To Power Usage Locations ( Avoids rebuilding old grid from Falmouth, Cape Cod to Boston at ratepayers expense ) 
 
Offshore wind companies want to bring their cables into Falmouth on Cape Cod to get the power to Boston by land the cheapest route for them.
 
Ocean submarine cables are very expensive and in order to get the power to Boston, the wind companies want to come on land in Cape Cod and make the electric ratepayers upgrade the electric infrastructure of the state from Cape Cod To Boston by land. Plans in 2020 showed the best method was a submarine cable from the offshore wind site directly to Boston at the expense of the ocean wind companies. 
 
Falmouth Massachusetts residents voiced overwhelming opposition to plans by an offshore wind company to run electric cables from its offshore wind site through the community at a public hearing held by the select board on Wednesday, June 8, 2022
 
Citizens said that the power plant project would cause excessive noise, or that people would not be able to mortgage their homes because of the massive electric substation. The majority of residents said the town overall objects to wind turbines, referring to two land-based court-designated nuisance wind turbines, Wind 1 and Wind 2, which are now slated to be dismantled. 
 
Residents worried about the EMF, electric-magnetic field from the 345,000 volts AC, Alternating Current buried cables next to their homes. The wind company talked of changing the cable current to DC, Direct Current but very few studies have been done in the United States regarding the exposure to HVDV, High Voltage Direct Current cables on nearby residential homeowners. 
 
An East Falmouth resident said that the project should be moved to Fall River or Boston by submarine cable and that he is disappointed in the town government.
“It’s got to end right here and now,” the resident said. “You’ve been intentionally torturing my friends and the citizens of Falmouth with the two town-owned wind turbines. It’s time to find a new place for your  power supply.”
In 2020 a consulting group with offices in Boston, Brussels, Chicago, London, Madrid, New York City, Rome, San Francisco, Sydney, Toronto, and Washington, DC. did a study showing an ocean wind turbine submarine cable grid that avoided Falmouth, Massachusetts. ( See Photograph ) 
 
The plan shows only three ocean wind submarine cables needed from the offshore wind lease areas directly to the power usage destinations in Boston, Fall River, and Connecticut.
 
The first submarine cable from the offshore wind sites provides power directly to (Boston) the Mystic power station in Everett, Massachusetts. The sea link saves electric ratepayers from rebuilding the overland electric grid from Cape Cod to Boston. This cable also avoids the need for an onshore wind cable through the residential locations in Falmouth, Massachusetts.
 
Recently on June 8, at a public meeting, Falmouth residents overwhelming spoke out against the onshore cable route and power plant the size of the Falmouth Mall.
 
The second undersea cable provides power directly near (Fall River) to the old Brayton Point Power Station in Somerset, Massachusetts.
 
The third sub cable goes directly to the grid in Connecticut.
 
The safest route is all submarine cables depicted in the picture in this article.  

Views: 233

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Willem Post on June 20, 2022 at 9:41pm

THE MORE WIND AND SOLAR, THE HIGHER THE ELECTRIC RATES

 

1) Wind and Solar Subsidies Provide a Bonanza for Wall Street

 

This URL shows wind and solar prices per kWh would be at least 50% higher without direct and indirect subsidies. They would be even higher, if the costs of other items were properly allocated to the owners of wind and solar projects, instead of shifted elsewhere. See below section High Levels of Wind and Solar Require Energy Storage.

 

http://www.windtaskforce.org/profiles/blogs/economics-of-tesla-powe...

http://www.windtaskforce.org/profiles/blogs/large-scale-solar-plant...

http://www.usu.edu/ipe/wp-content/uploads/2016/04/UnseenWindFull.pdf

 

This URL shows about 2/3 of the financial value of a wind project is due to direct and indirect subsidies, and the other 1/3 is due to electricity sales.

http://johnrsweet.com/Personal/Wind/PDF/Schleede-BigMoney-20050414.pdf

 

- Indirect subsidies are due to federal and state tax rebates due to loan interest deductions from taxable income, and federal and state MARCS depreciation deductions from taxable income.

 

- Direct subsidies are up-front federal and state cash grants, the partial waiving of state sales taxes, the partial waiving of local property, municipal and school taxes. See URLs.

 

http://www.windtaskforce.org/profiles/blogs/excessive-subsidies-for...

https://www.eia.gov/analysis/requests/subsidy/pdf/subsidy.pdf

 

Any owner, foreign or domestic, of a wind and/or solar project, looking to shelter taxable income from their other US businesses, is allowed to depreciate in 6 years almost the entire cost of a wind and solar project under the IRS scheme called Modified Accelerated Cost Recovery System, MARCS. The normal period for other forms of utility depreciation is about 20 years.

 

Then, with help of Wall Street financial wizardry from financial tax shelter advisers, such as BNEF*, JPMorgan, Lazard, etc., the owner sells the project to a new owner who is allowed to depreciate, according to MARCS, almost his entire cost all over again. Over the past 20 years, there now are many thousands of owners of RE projects who are cashing in on that bonanza.

 

Loss of Federal and State Tax Revenues: The IRS estimated the loss of tax revenues to the federal government for the 5y period of 2017 - 2021. See “Energy” heading in URL

The next report would be for the 2018 - 2022 period

https://www.jct.gov/publications.html?func=select&id=5

 

The indirect largesse, mostly for wind and solar plants^ that produce expensive, variable/intermittent electricity, does not show up in electric rates. It likely is offset by taxes and added to the federal debt.

 

Most of the direct federal subsidies to all energy projects of about $25 billion/y also do not show up in electric rates. They likely were also added to the federal debt.

 

Most of the direct state subsidies to RE projects likely were added to state debts.

 

The additional costs of state-mandated RPS requirements likely were added to the utility rate base for electric rates.

 

* BNEF is Bloomberg New Energy Finance, owned by the pro-RE former Mayor Bloomberg of New York, which provides financial services to the wealthy of the world, including providing them with tax avoidance schemes.

 

^ In New England, wind is near zero for about 30% of the hours of the year, and solar is minimal or zero for about 70% of the hours of the year.

 

https://www.nrel.gov/docs/fy17osti/68227.pdf

https://www.greentechmedia.com/articles/read/tax-equity-investors-b...

 

Warren Buffett Quote: "I will do anything that is basically covered by the law to reduce Berkshire's tax rate," Buffet told an audience in Omaha, Nebraska recently. "For example, on wind energy, we get a tax credit if we build a lot of wind farms. That's the only reason to build them. They don't make sense without the tax credit." 

https://www.usnews.com/opinion/blogs/nancy-pfotenhauer/2014/05/12/e...

 

Comment by Willem Post on June 20, 2022 at 9:39pm

COST SHIFTING IS THE NAME OF THE GAME REGARDING WIND AND SOLAR

http://www.windtaskforce.org/profiles/blogs/cost-shifting-is-the-na...

 

Regarding wind and solar, cost shifting is rarely mentioned, identified or quantified. Those costs, as c/kWh, could be quantified, but it is politically expedient, using various, often far-fetched reasons, to charge them to:

 

- Directly to ratepayers, via electric rate schedules, and/or added taxes, fees and surcharges on electric bills

- Directly to taxpayers, such as carbon taxes, user fees and surcharges.

- Directly to federal and state budgets and debts

 

Per Economics 101, no cost ever disappears.

 

Eventually, the various shifted wind and solar costs, plus direct and indirect wind and solar subsidies, would increase the prices of energy and of other goods and services.

 

Efficiency and productivity improvements elsewhere in the energy sector, and other sectors of the economy, may partially, or completely, offset such increases.

 

However, wind and solar subsidies would divert capital from other sectors of the economy, which likely would result in fewer improvements in efficiency and productivity in these sectors.

http://www.windtaskforce.org/profiles/blogs/high-demand-and-low-win...

 

LIFECYCLE COST ANALYSIS OF EXISTING AND NE ELECTRICITY SOURCES

 

This report uses publicly available data to estimate the average levelized cost of electricity from existing generation resources (LCOE-Existing), as compared to the levelized cost of electricity from new generation resources (LCOE-New) that might replace them.

 

The additional information provided by LCOE-Existing presents a more complete picture of the generation choices available to the electric utility industry, policymakers, regulators and consumers.

https://www.instituteforenergyresearch.org/wp-content/uploads/2019/...

 

Existing coal-fired power plants can generate electricity at an average LCOE of $41 per megawatt-hour, whereas the LCOE of a new coal plant, operating at a similar duty cycle, would be $71 per MWh.

 

Similarly, existing combined-cycle gas power plants (CCGTs) can generate electricity at an average LCOE of $36 per MWh, whereas the LCOE of a new CCGT gas plant would be $50 per MWh.

 

Non-dispatchable wind and solar impose a cost on the dispatchable generators which are required to remain in service for peaking, filling in and balancing, 24/7/365, to ensure reliable electricity service.

 

Non-dispatchable means the output of wind and solar depends on factors beyond our control (the wind blowing and the sun shining) and cannot be relied upon for peaking, filling in and balancing.

 

Wind and solar increase the LCOE of dispatchable resources by reducing their utilization rates without reducing their fixed costs, resulting in a levelized fixed cost increase, i.e., higher c/kWh.

 

This report estimates the “imposed cost” of wind generation at about $24 per MWh, or 2.4 c/kWh, if CCGT gas generation performs the peaking, filling in and balancing.

 

The CCGT plants compensate for the erratic outputs of wind and solar by inefficiently ramping up and down their outputs at part load, and inefficiently making more frequent starts and stops.

 

All that decreases annual production of CCGT plants, adversely affects their economic viability, increases Btu/kWh and CO2/kWh, and increases wear and tear, all at no cost to the wind and solar multi-millionaires.

 

This report estimates the “imposed cost” of wind generation at about $24 per MWh, or 2.4 c/kWh, if CCGT gas generation performs the peaking, filling in and balancing.

 

This report estimates the “imposed cost” of solar generation at about $21 per MWh, or 2.1 c/kWh, if CCGT gas generation performs the peaking, filling in and balancing.

 

As a result, existing coal ($41), CCGT gas ($36), nuclear ($33) and hydro ($38) are less than half the cost of new wind ($90) or new PV solar ($88.7), if imposed costs were included.

 

NOTE: The imposed cost on ratepayers and taxpayers of various direct and indirect wind and solar subsidies are an entirely separate issue.

 

COST SHIFTING ONTO RATEPAYERS, TAXPAYERS AND DEBT 

 

Clever multi-millionaires have known about wind and solar being much more expensive compared with existing generation (coal, oil, gas, nuclear, hydro, etc.) for at least 25 years.

https://www.instituteforenergyresearch.org/wp-content/uploads/2019/...

 

By beating the drums of climate change and global warming, and using clever lobbyists in the halls of Congress and State legislatures, they were able to get all sorts of goodies, such as upfront cash grants, upfront tax credits, low-cost loans, generous, above-market, feed-in tariffs, production tax credits, and loan interest and asset depreciation write-offs to avoid paying income taxes.

 

All that enables them, and others to claim wind and solar is equivalent and competitive with other workers. What more could these millionaires ask for?

 

Cost Shifting: Here is a partial list of the costs that were shifted, i.e., not charged to wind and solar plant owners, to make wind and solar appear less costly than in reality to the lay public and legislators.

 

1) The various forms of grid-stabilizing inertia (presently provided by synchronous gas, coal, oil, nuclear, bio and hydro plants).

 

2) The filling-in, peaking and balancing by traditional generators (mostly gas turbines in New England), due to wind and solar variability and intermittency, 24/7/365. Their random outputs require the other generators to inefficiently ramp up and down their outputs at part load, and to inefficiently make more frequent starts and stops, which also causes more wear and tear, all at no cost to wind and solar owners.

 

The more wind and solar on the grid, the larger the required up and down ramping of the gas turbines, which imparts added costs to owners for which they likely would not be paid: And the wind and solar erratic output is coddled by government programs and subsidies!!

 

Owners of traditional generators:  

 

- Have less annual production to cover power plant costs, which jeopardizes the economic viability of their plants.

 

- Are left with inefficient remaining production (more fuel/kWh, more CO2/kWh), due to up and down ramping at part load, and due to more frequent starts and stops, which leads to less fuel and CO2 reduction than claimed, and increased costs for owners. See URL

http://www.windtaskforce.org/profiles/blogs/fuel-and-co2-reductions...

 

- Have more wear and tear of their gas turbine plants, which further adds to owner costs

 

NOTE: All of this is quite similar to a car efficiently operating at a steady 55 mph, versus a car inefficiently operating at continuously varying speeds between 45 mph to 65 mph, and accelerating for frequent starts and decelerating for frequent stops.

 

3) Any battery systems to stabilize distribution grid with many solar systems. They would quickly offset downward spikes due to variable cloud cover. See URL.

http://www.windtaskforce.org/profiles/blogs/large-scale-solar-plant...

 

4) Any measures to deal with DUCK curves, such as a) daily gas turbine plant down and up ramping, b) utility-scale storage and c) demand management.

 

NOTE: GMP in Vermont, has determined 70 of its 150 substations will eventually need upgrades to avoid “transmission ground fault overvoltage,” (TGFOV), if more solar is added per requirements of the VT Comprehensive Energy Plan. This is nothing new, as utilities in southern Germany have been dealing with these issues for over ten years, which has contributed to German households having the highest electric rates (about 30 eurocent/kWh) in Europe.

 

5) Grid-related costs, such as grid extensions and augmentations to connect the remotely distributed wind and solar, and to deal with variable and intermittent wind and solar on the grid. Those grid items usually are utilized at the low capacity factors of wind and solar, i.e., a lot of hardware doing little work.

 

6) Utility-scale electricity storage (presently provided by the world’s traditional fuel supply system).

https://www.neon-energie.de/Hirth-2013-Market-Value-Renewables-Sola...

 

The above 6 items are entirely separate from the high levels of direct and indirectsubsidies. They serve to make wind and solar appear to be much less costly than in reality. See sections 1 and 2 and Appendix.

  

All that enables wind and solar proponents to endlessly proclaim: “Wind and solar are competitive with fossil and nuclear”.

 

Example of Cost Shifting: For example, to bring wind electricity from the Panhandle in west Texas to population centers in east Texas, about 1000 miles of transmission was built at a capital cost of $7 billion. The entire cost was “socialized”, i.e., it appeared as a surcharge on residential electric bills. Wind in Texas would have been much more expensive, if the owning and operating cost, c/kWh, of those transmission lines were added to the cost of wind.

 

Example of Cost Shifting: Often the expensive grid connection of offshore wind plants, say from 20 miles south of Martha's Vineyard, across the island, then about 7 additional miles under water, and then to the reinforced mainland grid, is not separately stated in the capital cost estimates, i.e., all or part of it is provided by the utilities that buy the electricity under PPAs to make PPA-pricing appear smaller than in reality. That cost would be “socialized”, i.e., it appears as a surcharge on residential electric bills, or is added to the rate base.

 

Wind and Solar Wholesale Prices in NE: Here are some wholesale prices of wind electricity RE folks in New England, especially in Maine, do not want to talk about. They would rather dream RE fantasies, obfuscate/fudge the numbers, and aim to convert others to their dream scenarios, somewhat like religious missionaries.

 

EXHORBITANT REAL COST OF WIND AND SOLAR ELECTRICITY

 

“All-in” Electricity Cost of Wind and Solar in New England

 

https://www.windtaskforce.org/profiles/blogs/high-costs-of-wind-sol...

http://www.windtaskforce.org/profiles/blogs/cost-shifting-is-the-na...

 

Pro RE folks point to the “price paid to owner” as the cost of wind and solar, purposely ignoring the other cost categories. The all-in cost of wind and solar, c/kWh, includes:

 

1) Above-market-price paid to Owners 

2) Subsidies paid to Owners

3) Owner return on invested capital at about 9%/y

4) Grid extension/augmentation

5) Grid support services

6) Future battery systems

 

Comments on table 1

   

- Vermont legacy Standard Offer solar systems had greater subsidies paid to owner, than newer systems

 

- Wind prices paid to owner did not have the drastic reductions as solar prices.

 

- Vermont utilities are paid about 3.5 c/kWh for various costs they incur regarding net-metered solar systems

 

- "Added to rate base" is the cost wind and solar are added to the utility rate base, used to set electric rates.

 

- “Total cost”, including subsidies to owner and grid support, is the cost at which wind/solar are added to the utility rate base

 

- “NE utility cost” is the annual average cost of purchased electricity, about 6 c/kWh, plus NE grid operator charges, about 1.6 c/kWh

for a total of 7.6 c/kWh.

 

- “Grid support costs” would increase with increased use of battery systems to counteract the variability and intermittency of increased build-outs of wind and solar systems. See URL

https://www.windtaskforce.org/profiles/blogs/fuel-and-co2-reduction...

 

NOTES:

1) NE wholesale grid price averaged about 5 c/kWh, starting in 2009, due to low-cost CCGT and nuclear plants providing at least 65% of all electricity loaded onto the NE grid, in 2019.

 

https://www.iso-ne.com/about/key-stats/resource-mix/

https://nepool.com/uploads/NPC_20200305_Composite4.pdf


2) There are Owning costs, and Operating and Maintenance costs, of the NE grid

ISO-NE charges these costs to utilities at about 1.6 c/kWh. The ISO-NE charges include: 

 
Regional network services, RNS, based on the utility peak demand occurring during a month

Forward capacity market, FCM, based on the utility peak demand occurring during a year.

 

Table 1/VT & NE sources

Paid to

Subsidy

Grid

GMP

 Added

ISO-NE

Total

NE

Times

 

 

paid to

support

 

to rate

RNS+

 

utility

 

owner

towner

cost

adder

base

FCM

cost

cost

c/kWh

c/kWh

c/kWh

c/kWh

c/kWh

c/kWh

c/kWh

c/kWh

Solar, rooftop, net-metered, new

17.4

5.2

2.1

3.5

20.9

1.6

29.8

7.6

3.92

Solar, rooftop, net-metered, legacy

18.2

5.4

2.1

3.5

21.7

1.6

30.8

7.6

4.05

Solar, standard offer, combo

11.0

6.74

2.1

11.0

1.6

21.44

7.6

2.82

Solar, standard offer, legacy

21.7

10.5

2.1

21.7

1.6

35.9

7.6

4.72

Wind, ridge line, new

8.5

3.9

2.4

8.5

1.6

16.4

7.6

2.15

Wind, offshore, new

9.0

4.1

2.4

9.0

1.6

17.1

7.6

2.25

 

Sample calculations:

 

NE utility cost = 6, Purchased + 1.6, (RNS + FCM) = 7.6 c/kWh

Added to utility rate base = 17.4, net-metered, new + 3.5 = 20.9 c/kWh

Total cost = 17.4 + 5.2 + 2.1 + 3.5 + 1.6 = 29.8 c/kWh

 

Excludes costs for very expensive battery systems

Excludes costs for very expensive floating, offshore wind systems

Excludes cost for dealing with shortfalls during multi-day wind/solar lulls. See URL

https://www.windtaskforce.org/profiles/blogs/wind-and-solar-provide...

 

“Added to rate base” is for recent 20-y electricity supply contracts awarded by competitive bidding in NE.

“Added to rate base” would be much higher without subsidies and cost shifting.

Areas with better wind and solar conditions, and lower construction costs/MW have lower c/MWh, than NE

New England has average winds, has highest on-shore turnkey costs ($2,400/kW in 2020), has highest PPA c/kWh

See page 39 of URL

https://www.energy.gov/sites/default/files/2021-08/Land-Based%20Win...

Comment by Willem Post on June 20, 2022 at 9:37pm

BIDEN 30,000 MW OFFSHORE WIND SYSTEMS BY 2030; AN EXPENSIVE FANTASY  

https://www.windtaskforce.org/profiles/blogs/biden-30-000-mw-of-off...

 

The Biden administration announced on October 13, 2021, it will subsidize the development of up to seven offshore wind systems (never call them farms) on the US East and West coasts, and in the Gulf of Mexico; a total of about 30,000 MW of offshore wind by 2030.

 

Biden's offshore wind systems would have an adverse, long-term impact on US electricity wholesale prices, and the prices of all other goods and services, because their expensive electricity would permeate into all economic activities.

 

The wind turbines would be at least 800-ft-tall, which would need to be located at least 30 miles from shores, to ensure minimal disturbance from night-time strobe lights.

 

Any commercial fishing areas would be significantly impacted by below-water infrastructures and cables. The low-frequency noise (less than 20 cycles per second, aka infrasound) of the wind turbines would adversely affect marine life, and productivity of fishing areas.

 

Production: Annual production would be about 30,000 x 8766 h/y x 0.45, capacity factor = 118,341,000 MWh, or 118.3 TWh of variable, intermittent, wind/weather/season-dependent electricity.

 

The additional wind production would be about 100 x 118.3/4000 = 2.96% of the annual electricity loaded onto US grids.

That US load would increase, due to tens of millions of future electric vehicles and heat pumps.

 

This would require a large capacity of combined-cycle, gas-turbine plants, CCGTs, to cost-effectively:

 

1) Counteract the wind output variations, MW, aka grid balancing

2) Fill-in wind production shortfalls, MWh, during any wind lulls

 

Such lulls occur at random throughout the year, and may last 5 to 7 days in the New England area.

 

These URLs provide examples of similar wind/solar lull conditions in Germany and New England

 

https://www.windtaskforce.org/profiles/blogs/analysis-of-a-6-day-lu...

http://www.windtaskforce.org/profiles/blogs/wind-plus-solar-plus-st...

https://www.windtaskforce.org/profiles/blogs/wind-and-solar-energy-...

https://www.windtaskforce.org/profiles/blogs/playing-russian-roulet...

 

High Costs of Balancing the Grid with Increased Wind and Solar

 

The ANNUAL grid balancing costs are entirely due to the variations and intermittencies of wind and solar, because the OTHER power plants have to operate far from their efficient modes of operation, 24/7/365. They experience:

 

1) More up/down production at lower efficiencies, which have more Btu/kWh, more CO2/kWh

2) More equipment wear-and-tear cost/kWh, due to up/down production

3) More-frequent plant starts/stops, which have high Btu/kWh, high CO2/kWh

 

Increased wind and solar also requires:

 

- Increased hot, synchronous (3,600 rpm), standby plant capacity, MW, to immediately provide power, if wind/solar generation suddenly decreases, or any other power system outage occurs.

- Increased cold, standby plant capacity, MW, to provide power after a plant’s start-up period.  

 

When wind and solar were only a very small percent of the electricity loaded onto the NE grid, those balancing costs were minimal, sort of “lost in the data fog”

 

When wind and solar became a large percent, those balancing costs in the UK became 1.3 BILLION U.K. pounds in 2020, likely even more in 2021, 2022, etc.

https://www.windtaskforce.org/profiles/blogs/grid-balancing-costs-s...

 

Those balancing costs should have been charged to the Owners of wind and solar systems, but, in reality, they were politically shifted to taxpayers, ratepayers, and government debts.

 

Those balancing costs are in addition to the various government subsidies, which are also politically shifted to taxpayers, ratepayers, and government debts.

 

Now you all are finally beginning to see just how wonderful wind and solar have been, and will be, for your pocketbook.

 

Energy systems analysts, with decades of experience, saw this mess coming about 20 years ago, but all-knowing legislators and bureaucrats ignored them, because they were pressured into aiding and abetting the harvesting of federal and state subsidies for RE businesses.

 

Turnkey Capital Cost: The turnkey capital cost for wind systems, plus offshore/onshore grid extension/augmentation would be about 30,000 MW x $5,000,000/MW = $150 BILLION, excluding financing costs. Biden’s excessive inflation rates, about 7% at present, surely would increase that cost.

 

Area Requirements: The 8-MW wind turbines would be arranged on a grid, spaced at least one mile apart (8 rotor diameters), about 1 sq mile per wind turbine. The minimum sea area requirement for 30,000/8 = 3,750 wind turbines would be 3,750 sq miles, or 2,400,000 acres

 

Electricity Cost/kWh: Based on the real-world European, mostly UK and German, operating experience in the North Sea and Baltic, such highly subsidized wind turbine systems:

 

1) Last about 20 years

2) Have high maintenance and operating costs, due to the adverse marine environment

3) Produce electricity at an “al-in” cost of about 2.25 times NE wholesale prices. See Appendix

 

The “all-in” wholesale prices of the offshore electricity of new systems are calculated at about 17 c/kWh, without cost shifting and subsidies, and about 9 c/kWh, with cost shifting and subsidies. The shifted costs and subsidies would result in:

 

1) Increased tax burdens on taxpayers

2) Increased household electric rates on ratepayers

3) Additions to federal and state government debts.

4) Additional burdens on the owners of traditional generators, because their power plants have to counteract the wind output variations, 24/7/365; the more wind (and solar), the greater the electricity quantities involved in the counteracting, plus their plants have to spend more time on standby, and are required to have more-frequent start/stops. See URLs and Appendix

 

https://www.windtaskforce.org/profiles/blogs/grid-balancing-costs-s...

http://www.windtaskforce.org/profiles/blogs/cost-shifting-is-the-na...

 

NOTE: These rates compare with the average New England wholesale price of 5 c/kWh, during the 2009 - 2022 period, 13 years, courtesy of:

 

1) Abundant, domestic, natural gas-fueled CCGT plants, that have: 1) low-cost/kWh, low-CO2/kWh, extremely-low particulate/kWh

2) Domestic, uranium-fueled nuclear plants, that have low-cost/kWh, near-zero CO2/kWh, zero particulate/kWh

3) Long-lasting hydro plants, that have low-cost/kWh, near-zero-CO2/kWh, zero particulate/kWh

 

NOTE: Cost shifting and subsidies have not yet affected NE wholesale prices, because the percent of new RE (mostly wind and solar) on the NE grid is very small, after 20 years of subsidies.

The image shows the negligeable “contribution” of wind + solar to the NE grid load, during 2021, after 20 years of subsidies!!

 

Wind and solar became significant in Germany and Denmark after more than 20 years of subsidies, resulting in:

 

- Politicians excessively allocating RE costs to households, thereby greatly increasing household electric rates.

- Politicians keeping industrial rates artificially low for international competitiveness reasons (a hidden trade subsidy). See URL

https://www.windtaskforce.org/profiles/blogs/german-household-elect...

Comment by Willem Post on June 20, 2022 at 9:36pm

DEEP-WATER FLOATING OFFSHORE WIND TURBINES IN MAINE

http://www.windtaskforce.org/profiles/blogs/deep-water-floating-off...

 

The Norwegians have about 60 years of experience building and servicing oil/gas rigs and laying undersea electric cables, gas lines and oil lines all over the world.

 

They have invested billions of dollars in specialized deep-water, Norwegian harbors and facilities for assembly of oil/gas rigs and invested in specialized sea-going heavy lifters, and specialized sea-going tugboats to tow the oil/gas rigs from Norwegian building sites to oil/gas production sites. The heavy lifters and other ships perform services all over the world.

 

Norway companies want to expand their business by building and servicing and providing spare parts for floating wind turbines for deep-water conditions all over the world

 

NOTE: Norwegians advocating expensive floating wind turbines that depend on the randomness of wind and produce high-cost, variable, intermittent electricity for other people, such as Jane and Joe Worker/Ratepayer, is highly hypocritical, because the Norwegians get 98% of their electricity from their own hydro plants, which produce low-cost, steady electricity (not variable, not intermittent). The Danes advocating wind turbines and boasting about their high percent of wind on their grid is similarly hypocritical, because the Danes have been increasingly using the storage reservoirs of Norway’s hydro plants for decades.

 

First Experimental Floating Wind Turbine in Norway

 

Equinor (formerly Statoil, a Norwegian government controlled company) launched the world's first operational deep-water, floating large-capacity wind turbine in 2009. The turbine trade name is “Hywind”.

 

The wind turbine consists of a 120 m (390 ft) tall tower, above the sea water level, and a 60 m (195 ft) submerged extension below the sea water level, with a heavy weight at the bottom to keep the wind turbine steady and upright, even with very high waves and strong wind conditions. The design was tested and perfected under storm and wind conditions simulated in a laboratory.

 

The 2.3 MW wind turbine is mounted on top of the tower. It was fully assembled in a deep-water harbor near Stavanger, Norway.

 

It was towed to a site 10 km (6.2 mi) offshore into the Amoy Fjord in 220 m (720 ft) deep water, near Stavanger, Norway, on 9 June 2009, for a two-year test run, which turned out to be successful.

 

First Commercial Floating Wind Turbine Plant in Scotland

 

Hywind Scotland project is the world's first commercial wind turbine plant using floating wind turbines.

 

It is located 29 km (EIGHTEEN MILES) off PeterheadScotland to minimize visual impacts from shore.

It has five Hywind floating turbines with a total capacity of 30 MW.

It is operated by Hywind (Scotland) Limited, a joint venture of Equinor, Norway (75%) and Masdar, Kuwait (25%).

 

In 2015, Equinor received permission to install 5 Hywind turbines in Scotland.  

 

Manufacturing started in 2016 in Spain (wind turbine, rotor), Norway (tower, underwater base, assembly), and Scotland (various parts)

The turnkey capital cost was $263 million for five 6 MW turbines, or $8,767/kW.

They were designed to float on the surface, with about 180 m (600 ft) above the sea water level and 80 m (265 ft) submerged below the seawater level.

Total steel weight is about 2300 metric ton, total ballasted weight is about 20,000 metric ton.

Heavy weights in the bottom of the submerged parts serve to keep them steady and upright.

 

The turbines were assembled at Stord in Norway in the summer of 2017, using the specialized Saipem 7000 floating crane, and then towed to the north of Scotland by sea-going tugboats.

Make sure to see the videos showing the crane assembling the entire wind turbine.

Nothing like that exists in Maine, or in the rest of New England.

That means offshore wind turbine assembly and servicing would largely be performed by foreign companies, which already have built the infrastructures and other facilities during the past 25 years.

 

https://www.youtube.com/watch?v=PUlfvXaISvc

https://www.youtube.com/watch?v=PmkA6hbJ_j8

https://www.youtube.com/watch?v=bQVU7UaMuck

 

The huge, sea-going, specialized, crane (14,000-metric ton lifting capacity) is required for partial assembly on land and final assembly in an area close to shore with a very deep harbor, before towing, fully assembled, to the site.

 

The finished turbines were towed to Peterhead, Scotland.  

Three  cup anchors hold each turbine in place.

About 2400 meter of chain is required, weighing 400 metric ton, for each turbine.

The Hywind Scotland project was commissioned in October 2017.

 

Hywind Wind Turbines for Demonstration Purposes in Maine

 

Hannah Pingree and other Maine's wind bureaucrats in state government are engaging in mindless prattle, eager to do the bidding of various multi-millionaires and foreign companies that may be providing some wining/dining boondoggle trips to “view the Hywind turbines” in Norway and Scotland.

 

The turnkey cost of those two Hywind turbines would be about $10,000 per kW, versus NE ridgeline wind at $2,000/kW, and regular offshore, south of Martha’s Vineyard, at $4,000/kW.

http://www.windtaskforce.org/profiles/blogs/iso-ne-study-of-1600-mw...

 

That would be at about $120 million for a two 6 MW Hywind wind turbines, plus whatever facilities would need to be built in Maine to support the project.

 

The turnkey capital cost of the wind turbine plant in Maine would be much higher, because Maine does not have the experience of the Norwegians and the specialized equipment and specialized ships, and other facilities. It would be very costly to build those facilities and ships in Maine, or elsewhere.

 

600-ft Tall Hywind Turbines Highly Visible From Mohegan Island, Plus Infrasound

 

The 600-ft tall Hywind wind turbines would be highly visible from Mohegan Island, if they were located TWO MILES east of the island.

 

At that distance, the problem would not be just cyclical, audible noises keeping people awake, but also low frequency infrasound, which can travel many miles, and passes through walls of houses, and can be felt but not heard, and has been shown to have adverse health impacts on people and animals.

http://www.windtaskforce.org/profiles/blogs/wind-turbine-noise-adve...

 

The FAA-required aviation beacons would be clearly visible during nighttime. BTW, they would need to be located about 15 - 20 miles away from Mohegan Island to be unobtrusive to the Islanders.

 

Here is a research report of daytime and nighttime visibility of wind turbines that are about 3 to 4 MW and about 500 ft tall. See URL with photos.

http://visualimpact.anl.gov/offshorevitd/docs/OffshoreVITD.pdf

 

“Study objectives included identifying the maximum distances the facilities could be seen in both daytime and nighttime views and assessing the effect of distance on visual contrasts associated with the facilities. Results showed that small to moderately sized facilities were visible to the unaided eye at distances greater than 42 km [26 miles (mi)], with turbine blade movement visible up to 39 km (24 mi). At night, aerial hazard navigation lighting was visible at distances greater than 39 km (24 mi). The observed wind facilities were judged to be a major focus of visual attention at distances up to 16 km (10 mi), were noticeable to casual observers at distances of almost 29 km (18 mi), and were visible with extended or concentrated viewing at distances beyond 40 km (25 mi).”

 

One has to feel sorry for all the residents of Mohegan Island, but the bureaucrats in Augusta, Maine, do not care about that, because there are not enough votes to stop them. Those bureaucrats are hell-bent to use federal and state grants, subsidies, taxpayer and ratepayer money of already-struggling Joe and Jane Worker to save the world, and to enrich a host of multi-millionaires seeking tax shelters. See Appendix.

 

Some Questions

 

Who are these Aqua Ventus multi-millionaire owners pushing for this expensive project?

How much would be the subsidies?

What would be the energy cost/kWh?

How long would the project last before it would have to be repaired?

How would it be repaired?

Would any special ships, facilities be required?

Does Maine have the required, at least 100-meter, deep-water port?

Is anyone looking at the entire picture on an A to Z basis, or are Maine bureaucrats just dreaming/prattling about castles in Spain?

Does anyone think the Norwegians would not want to make money to maintain/service and provide spare parts for their Hywind wind turbines?

 

Extremely Adverse Impact on CMP Electric Rates

 

LePage’s energy director, Steven McGrath, has focused exclusively on the cost of electricity from the demonstration project.

 

The rate is at least FOUR TIMES above wholesale market value, reflecting the custom design and experimental nature of the platforms.

 

It would start at 23 cents per kilowatt-hour in the first year, escalating at 2.5% per year to 35 cents after 20 years.

 

The PUC estimates it would add up to $208 million over the term, or about $10.5 million a year from Central Maine Power ratepayers. Maine Aqua Ventus had calculated the extra cost would add 73 cents a month to the average household electric bill, in the first year of operation, more thereafter.

  

That is a total rip-off, because Massachusetts pays only an average of 8 - 9 c/kWh over the life of the project.

Main bureaucrats need to learn from Governor Baker.

 

NOTE: The above prices should be compared with NE wholesale prices, which have been about 5 c/kWh since 2008, courtesy of abundant, domestic, low-cost, low-CO2 electricity from gas at about 5 c/kWh, and low-cost, near CO2-free electricity from nuclear at about 4.5 - 5.0 c/kWh.

 

This project is insanity on STEROIDS.

 

One has to feel sorry for the already-struggling Joe and Jane Workers in Maine who will ultimately pay for all this.

https://www.pressherald.com/2018/04/01/effort-to-build-offshore-win...

 

NOTE:

Dear Mr. Greg Kesich, Editor Portland Press Herald

 

(Mr. Greg suggested I write an op-ed regarding the referenced PPH article, so here it is.)

 

This op-ed is in reference to an article on floating wind turbines off the coast of Maine in the Portland Press Herald, dated 20 May 2019.

https://www.pressherald.com/2019/05/20/our-view-blown-off-course-ma...

 

The article states, Statoil had proposed a $120 million demonstration project for two 6 MW Hywind turbines ($10,000/kW) off Boothbay Harbor, but that Governor Page had rejected it. As you recall, his main reason was the higher electricity prices Joe and Jane Worker/Ratepayer would have to pay for 20 years.

 

The article states, Statoil instead took its project to Scotland, where it has invested more than $200 million for five 6 MW Hywind turbines. After some checking, the actual turnkey cost turned out to be $263 million.

 

Scotland got the turbines at $8,767/kW in 2017, but Maine would have gotten the same turbines at $10,000/kW.

 

The article states, “.....and given that country (Scotland) a head start on establishing itself as developer, manufacturer and exporter of offshore technology. Such potential was recognized by the wind energy task force, which was created in 2008 by Gov. John Baldacci and released its findings in December 2009.”

 

That statement is highly naïve and unrealistic. Norway has invested billions of dollars in infrastructures to develop specialized facilities and seagoing ships for shallow-water and deep-water wind turbines during the past 10 - 15 years. Norway has absolutely no intention of establishing Scotland and Maine as competitors.

 

The Scotland/UK actual contributions to the project were:

 

1) Scotland making some parts that were shipped to Norway for assembly

2) Scotland providing the site 18 miles from shore to minimize visual impacts from shore.

3) The UK providing a subsidy of 18.5 c/kWh, plus Statoil selling electricity at about 6.5 c/kWh on the wholesale market, for a total wholesale cost of 25 c/kWh for 20 years. This compares with New England wholesale prices averaging about 5 c/kWh since 2008.

4) The Scotland people paying higher prices/kWh for low-value, variable/intermittent electricity for 20 years that requires the services of other generators for peaking, filling in and balancing year-round. Statoil had to provide a 1.0 MWh li-ion battery system, at a capital cost of about $700,000, to help smooth the flow of the variable electricity from Hywind to minimize disturbances of the Scotland grid.

 

NOTE: If Maine government would have insisted Statoil would build significant infrastructure in Portland, ME, or elsewhere in Maine, Statoil, if willing to do so, would merely have increased the cost of the electricity, c/kWh, to cover its additional costs.

 

NOTE: Massachusetts has signed contracts for 800 MW of offshore wind turbines south of Martha’s Vineyard. If the state government would have insisted the consortium of European companies would build significant infrastructure in New Bedford, MA, or elsewhere in Massachusetts, the consortium, if willing to do so, would merely have increased the cost of the electricity, c/kWh, to cover its additional costs. However, Governor Baker insisted on lowest electricity cost, as that would benefit all of Massachusetts, not just New Bedford, etc. Counting votes is important. See URL.

http://www.windtaskforce.org/profiles/blogs/iso-ne-study-of-1600-mw...

 

NOTE:

School Students Playing with Floating Wind Turbines

 

The main objective with floating wind turbines is to isolate the wind turbine from any wave action, including 30 - 40 ft waves. That can only be done with a long, submerged extension of the wind turbine mast, with a heavy weight inside the bottom of the extension (ballast) to keep the wind turbine steady and upright.

 

Dr. Habib Dagher, Executive Director of the Advanced Structures & Composites Center, should have watched the youtube video, and then given proper instructions to teachers all over Maine, so those teachers could have educated these students regarding the physical requirements, to ensure these students would not waste their valuable time and money building inappropriate models. See URLs and watch both videos.

 

https://www.youtube.com/watch?v=PmkA6hbJ_j8

https://www.wabi.tv/content/news/Students-compete-to-build-most-sta...

 

CO2 Reduction due to Wind Turbines Much Less Than Claimed

 

The Irish Grid

Studies of operating conditions of the Irish grid performed a few years ago showed, at 17% wind on the grid, about 55% of the CO2 was reduced due to wind, instead of the claimed 100%. At higher wind percentages, the percent CO2 reduction would be even less.

 

NOTE: The mantra often promulgated by pro-wind folks is one MWh of wind displaces one MWh of other generation, and as wind uses no fuel there is no CO2, but other generation does use fuel, so that CO2 is avoided. That turned out to be of advantage to pro-wind folks, but is, in fact, highly simplistic.

 

In Ireland, there were years of denial and ignoring of various studies by independent energy systems analysts. Dr. Fred Udo was one of the early analysts of the Irish grid to point out the discrepancy. He was ignored at that time. Another study showed the gas turbines operated near 40% efficiency at 17% wind, whereas, at zero wind, they operated at near 50% efficiency. At that time, the Irish grid had only a minor connection to the UK grid. 

 

The undeniable tip-off was Irish gas imports, which had been predicted to decrease as wind would increase, but had, in fact, not decreased as much as predicted. After much back and forth, the government finally launched an inquiry, which revealed the inefficient operation of the gas turbines at part load (more Btu/kWh, more CO2/kWh), due to the variable, intermittent output of the wind turbines, and their more frequent start/stop operations (high Btu/kWh, high CO2/kWh).

 

Since that time, the Irish grid acquired large capacity connections to the UK and French grids to spread the “discrepancy” over a much larger grid area, which makes it nearly invisible. A Brussels PR problem solved. See URL.

http://www.windtaskforce.org/profiles/blogs/fuel-and-co2-reductions...

 

The New England Grid

Future wind on the NE grid is planned to be about 20% by 2025, i.e., higher than the 17% in Ireland a few years ago, and the NE grid has only minor connections to nearby grids, the same as Ireland a few years ago.

 

At the higher wind percentages, the NE percent CO2 reduction would be even less than 55%, i.e., expensive or inexpensive, variable/intermittent wind is no panacea regarding reducing CO2 and ameliorate global warming.

http://www.windtaskforce.org/profiles/blogs/high-demand-and-low-win...

 

DUCK Curves: DUCK curves due to daytime solar, a minor problem in not-so-sunny Ireland, would impart an additional worsening of grid stability problems after solar would become a significant percentage on the NE grid at noontime in the future.

 

Dealing with the down ramping in the morning as solar is increasing, and the up ramping in the afternoon/early evening as solar is decreasing would impart additional cost/kWh on owners of traditional generators. They likely would be compensated by means of capacity payments by ISO-NE. Those payments should be charged to the disturbers, the solar system owners. However the payments likely would be socialized, i.e., charged to ratepayers/taxpayers.

 

NOTE: If solar system owners were required to install batteries, then the down/up ramping would be avoided, but that would place a cost burden on solar system owners and there would be no end to their complaints.

 

 

Multi-Day Wind/Solar Lulls: Also, during simultaneous wind/solar lulls, which occur at random throughout the year, and may last up to 7 days, a full complement of traditional generation plants and energy storage sources must be available, 24/7/365, to serve NE demand, including future EVs and heat pumps. That storage must be replenished in a timely manner to serve a second lull, which may occur a few days after the first lull. See URLs.

 

The mantra often promulgated by pro-wind folks is “the wind always blows somewhere”. However, weather systems tend to be 500 to 1000 miles long and wide. Any surplus wind electricity would have to come from at least 1000 miles away, which would require high voltage DC lines, as the transmission losses of high voltage AC lines would be too large, plus it would require very robust connections between the NE and nearby grids. Dealing with the wind/solar lull problems would impart additional cost/kWh that likely would not be charged to wind turbine owners but to ratepayers/taxpayers.

 

http://www.windtaskforce.org/profiles/blogs/wind-and-solar-energy-l...

http://www.windtaskforce.org/profiles/blogs/high-demand-and-low-win...

http://www.windtaskforce.org/profiles/blogs/analysis-of-a-6-day-lul...

http://www.windtaskforce.org/profiles/blogs/large-scale-solar-plant...

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service