CMP Project Taking Shape Fast Despite Legal, Political Risks

Maine Public | By Fred Bever
Published May 14, 2021

Central Maine Power first proposed building a transmission line to Canada in 2017, and four years of controversy later, there are still hurdles ahead: legal challenges at the state and federal levels, a statewide ballot item set for November, unexpected technical issues to address.

But on Thursday, a federal court lifted an injunction that barred tree-clearing in one disputed segment.

And elsewhere on the corridor, trees are being cut and cleared, and poles are rising from the brush. Some observers say the $950 million project's gathering momentum could make it unstoppable.

Up in Bald Mountain Township, miles into the timberlands east of Bingham, hard-hatted contractors maneuver what look like giant Tonka toys across a 200-foot wide swathe of cleared land.

Skidders and grappling hooks pluck and load downed trees that were recently cut for the new CMP corridor.

A dusty haze hangs in the air.

"I'm glad to have the sun and the dry conditions, I like seeing dust 'cause when there's dust there's no mud," says Adam Desrosiers a project manager for CMP's "New England Clean Energy Connect."

The power line would take electricity from Canada's Hydro-Quebec dam system into the regional grid, thanks to a contract with Massachusetts utilities.

Desrosiers and more than 400 others — CMP staff and contractors — have been working since before mud-season to clear trees, raise poles and string wire for the 141-mile long, high-voltage line.

"This corridor was originally 125 feet wide, and we've added 75 feet of clearing on the western side. The forwarders and the excavators are bringing out the wood that's been cut. As they come out they bring timber mats back in with them. They're building mat roads down there, you can see them, to cross the wetlands, and protect the ground," he says, gesturing at their progress.

Poles in this segment, as with roughly two-thirds of the route, are going up alongside existing, smaller utility lines. Workers this year have already widened some 55 miles of that existing corridor.

Until Thursday, a key section where more than 50 miles of entirely new corridor would be cut from Jackman to The Forks, was off limits. Just before CMP was set to start cutting trees there, opponents won an injunction that put a U.S. Army Corps of Engineers permit for the work on hold.

"I mean it was a change that we didn't expect at first, but we had this area that was ready to work, and we quickly pivoted and moved the crews into this area and got working. The last thing we wanted to do was lay off all these Maine workers that we had hired, and send them back home," Desrosiers says.

But a federal appeals court lifted that injunction on Thursday.

CMP could soon start ramping up its hires and start clearing trees in that disputed section.

Jobs for Mainers are a big part of the pitch CMP and allies like the state Chamber of Commerce and the electrical workers union are making in their efforts to make sure the project survives the various challenges it still faces.

Opponents say even if CMP makes good on promises that most of the construction jobs will go to state residents, that work will be gone once the project is done. Meanwhile, the expanded corridor and the new cut to Jackman will bisect a unique woodland habitat, scarring it for decades and more, risking the health of many species, including rare native trout, pine martens and even mayflies.

"It's horrific. It's horrific. It shows an utter disregard for Maine," says Elizabeth Caruso, a first selectman in Caratunk, a town on the corridor route, where many residents make their living in and around the Kennebec River.

CMP charges that opposition is being drummed up by fossil-fuel energy companies that could lose profits if the project goes through. And companies such as Calpine and NextEra have financed petition drives and lawsuits.

But it's grassroots activists like Caruso and her husband — both certified Maine guides — providing the passion.

"They're taking down our trees. They just don't care," Caruso says.

And Caruso is quick to note that project profits will go to foreign entities — Canada's Hydro Quebec, and Spain-based Iberdrola, whose investors own the biggest stake in CMP's parent company, Avangrid.

She has put in many hours in permit proceedings and lawsuits related to the project. And even with construction underway, she's hopeful that any one of the challenges still out there — including a statewide referendum set for November — will spell its demise.

But as CMP cuts more trees, as it plants more poles in the ground, the company's risk of failure could be growing smaller.

"The risk is becoming increasingly small, looking at the whole perspective," says David Littell, a former state regulator and lawyer who now advises governments and private clients on utility issues.

He says that in addition to the physical work being done, CMP and Hydro-Quebec are also providing millions of dollars in benefits — such as investments in electric vehicle infrastructure or broadband service — on an expedited schedule.

Littell says a case is building that could make the project a legal fait accompli.

"You know, sometimes facts make a difference. CMP is clearly working hard to change the facts on the ground by building corridor and making payments," he says.

Littell says it's far from a slam dunk though. And one legal expert, Portland lawyer Jamie Kilbreth, is counting on the state's courts.

"There are a lot of issues here that all inter-relate. And they all suggest that CMP's rush to build this thing may be a mistake," he says.

Kilbreth says there is precedent from the Maine Law Court that could overcome any "vested rights" that CMP may develop on the ground.

And he is a lead lawyer in a suit brought by a bipartisan group of lawmakers, conservationists and others contending that the state leased lands for the project to CMP without seeking a two-thirds vote of the Legislature that's required by the state Constitution.

"Regardless of what happens with the referendum, if they can't get two-thirds legislative approval to cross the public lands then they are going to have to find a new route and start the permit process all over anyway," he says.

If Kilbreth's clients win the case, that is.

CMP has already made an appeal in that case to the Maine Law Court that could slow it down, and some observers think that's a stalling tactic by CMP so it can pile more poles into the ground before any court takes decisive action.

Thorn Dickinson, CMP's top executive on the project, steadfastly avoids the question of whether its aggressive construction schedule is keyed to any legal risks.

"We're going to continue to be nimble; we're going to focus on the work that we can get done, and we'll deal with the challenges as they come up. We're not ready to move our commercial operation date at this point," he said.

Earlier deadlines have been missed, though, and CMP has pushed its planned in-service date to May of 2023.

And in a proceeding at the Federal Energy Regulatory Commission, CMP is seeking a quick decision in a contentious dispute with NextEra over transmission system upgrades at the Seabrook nuclear power plant.

System regulators say the upgrade is needed for grid safety before CMP energizes the new powerline. CMP says NextEra, which owns the nuclear plant, is dragging its feet on planning and scheduling that upgrade, forcing delays that could stall the powerline's in-service date past 2023.

In a sworn affidavit, Dickinson of CMP alleges that NextEra offered a quid-pro-quo: agree to buy electricity from Seabrook at an above-market rate, and NextEra would expedite the upgrade process.

Starting two weeks from now, tree-cutting on CMP's corridor project will be barred through the end of July. That's required to protect summer habitat for the northern long-eared bat, a threatened species.

https://www.mainepublic.org/business-and-economy/2021-05-14/too-big...

************************************* 


Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.

Views: 97

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Kenneth Capron on May 18, 2021 at 2:23am

Isn't there an advantage to be claimed in court if the project is substantially in progress? Can't wait to see the transmission line being proposed for Northern Maine?

Comment by Thinklike A. Mountain on May 18, 2021 at 1:09am

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."