Bill proposed to block Sears Island wind port

What about onshore wind?

Maine Public | By Peter McGuire
Published January 31, 2025 at 4:32 PM EST

State Rep. Reagan Paul, a Republican from Winterport, has proposed legislation that would prevent the state from building a planned facility on Sears Island to support a nascent offshore Gulf of Maine ocean wind power industry.

The measure was floated as President Donald Trump froze further ocean wind development in federal waters. It follows funding roadblocks to the ambitious port project led by the Maine Department of Transportation.

The bill would extend an existing conservation easement over the entire 941-acre, state-owned island in Searsport. The land was divided in 2007 between a preservation area and a smaller parcel set aside for development.

Paul opposes developing offshore wind power and argues it is too expensive and environmentally harmful. Protecting the entire island now would finally end decades of divisive debates over repeated plans to develop the island, Paul added.

"I just think it can be beneficial to stop having that conversation," she said. "It doesn’t have to happen, we can protect the island and look forward to generation sources that are better for the Maine environment, Maine ratepayers and the community."

Advocates insist building ocean wind power arrays are crucial to reaching state clean energy goals and reducing reliance on expensive fossil fuels for electricity generation.

Last year Gov. Janet Mills selected the Sears Island parcel to host a port capable of launching specialized floating wind turbines necessary for the deep waters in the Gulf of Maine.

But the Maine Department of Transportation failed to receive a $456 million package to build the facility and later a $16 million grant to design it, leaving the future of the project unclear.

One of President Trump's first actions was to stop leasing federal waters to offshore wind developments and review all permitting and funding for existing projects, further clouding the immediate future of Maine's wind industry ambitions.

In a statement, the Maine Department of Transportation said it was reviewing the bill ahead of a public hearing that has yet to be scheduled.

https://www.mainepublic.org/climate/2025-01-31/bill-proposed-to-blo...

************************************* 


Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.

 

Views: 39

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Willem Post on February 5, 2025 at 9:40am

The Dysfunctional State of Maine?
The over-taxed, over-regulated, already-impoverished Maine people are super-screwed, trying to make ends meet in a near-zero, real growth Maine economy
The Maine economy has lots of low-tech/low-pay/low-benefit, bs jobs
The Maine economy has lots of woke, leftist bureaucrats
Screwed-over Mainers also have to pay for poverty-stricken, aliens of different cultures from all over, who illegally enter the US, a federal felony
.
Those illegal aliens:
– are the dregs of Third World countries, sent to Maine by their US-hating, leftist, woke governments, in cahoots with Soros-financed NGOs
– are getting free housing, free food, a never-empty credit card, free healthcare, free education and whatever other goodies they want. They mainly suck from the government tit
– have no skills, no training, no education, no modern industrial experience.
– will take low-tech/low-pay/low-benefit jobs away from screwed-over Mainers.
– are often good at crime, murder, rape, drug and human trafficking and mayhem.
.
Many millions of illegal aliens have to be shipped back where they came from, before they ruin the US.
.
Down-trodden Mainers often have to put up with the visual ugliness and noise of hundreds of windmills, that are often idle, because of too little wind year-round, and many thousands of acres of solar panels, that are often covered with snow and ice in winter; there is no solar at night.
.
MAGA may lead to higher CO2 ppm to 1) increase growth of flora and fauna all over the world, and 2) increase crop yields to feed hungry people. What is not to like?

.

.

NEW ENGLAND ELECTRICITY 100% FROM WIND AND SOLAR by 2050?
In New England, we have Net Zero nut cases. They know nothing about energy systems, but spout lots of nonsense.

“Keep it in the ground”, they say. “All electricity from wind and solar”, they say.
When presented with numbers and facts their eyes glaze over

Here is a simple analysis, if no fossil fuels, no nuclear, and minimal other sources of electricity

 

ELECTRICITY STORAGE WITH TESLA POWER MODULES

https://www.windtaskforce.org/profiles/blogs/vermont-example-of-ele...

.

It is assumed, 1) all W/S output, based on historic weather data, is loaded into batteries, 2) all demand is drawn from batteries, based on historic load on the grid, as published by ISO-NE.

An annual storage balance was created, which needed to stay well above zero; the batteries are not allowed to "run dry" in bad W/S years. The balance was used to determine the wind and solar capacities needed to achieve it.

.

New England would need a battery storage system with a capacity of about 10 TWh of DELIVERABLE electricity from batteries to the HV grid.

Daily W/S output would be fed to the batteries, 140 TWh/y

Daily demand would be drawn from the batteries, 115 TWh/y in 2024

Battery system roundtrip loss, HV to HV, would be 25 TWh/y, more with aging

Transmission and Distribution to users incur additional losses of about 8%, or 0.08 x 115 = 9.2 TWh 

The battery system would cover any multi-day W/S lulls throughout the year
Batteries would supplement W/S output, as needed, 24/7/365
W/S would charge excess output into the batteries, 24/7/365 
Tesla recommends not charging to more than 80% full and not discharging to less than 20% full, to achieve normal life of 15 years and normal aging at 1.5%/y.
.
The INSTALLED battery capacity would need to be about 10 TWh / (0.6, Tesla factor x aging factor x 0.9, outage factor) = 18.5 TWh, delivered as AC at battery outlet.
.
The turnkey cost would be about $600/installed kWh, delivered as AC at battery outlet, 2024 pricing, or $600/kWh x 18.5 billion kWh = $11.1 trillion, about every 15 years.

 

If all money were borrowed from banks, the cost of amortizing $11.1 trillion at 6% over 15 years = 1132 billion/y, slightly less than the New England GDP
https://www.windtaskforce.org/profiles/blogs/battery-system-capital...

.

.

High Costs/kWh of Wind and Solar Foisted onto a Brainwashed Public

.

The three main US subsidies are:

Federal and state tax credits and cash grants,
5-y Accelerated Depreciation write off of the entire project
Deduction of interest of borrowed money

.

The effect of the three items is to reduce the owning and operating cost of a project by 50%, which means electricity can be sold at 50% less than it costs to produce.

Utilities pay 15 c/kWh, wholesale, after 50% subsidies, for electricity from fixedoffshore wind systems

Utilities pay 18 c/kWh, wholesale, after 50% subsidies, for electricity from floating offshore wind

Utilities pay 12 c/kWh, wholesale, after 50% subsidies, for electricity from larger solar systems

.

Excluded costs, at a future 30% W/S annual penetration on the grid, the current UK level: 

- Onshore grid expansion/reinforcement to connect distributed W/S systems, about 2 c/kWh

- Traditional power plants to quickly counteract W/S variable output, on a less than minute-by-minute basis, 24/7/365, about 2 c/kWh

- Traditional power plants providing electricity during 1) low-wind periods, 2) high-wind periods, when rotors are locked in place, and 3) low solar periods during mornings, evenings and at night, about 2 c/kWh

- W/S electricity that could have been produced, if not curtailed, about 1 c/kWh

- Importing electricity at high prices, when W/S output is low, 1 c/kWh

- Exporting electricity at low prices, when W/S output is high, 1 c/kWh

- Disassembly on land and at sea, reprocessing and storing at hazardous waste sites, about 2 c/kWh

Some of these values exponentially increase as more wind and solar systems are added to the grid
.
The economic/financial insanity and environmental damage of it all is off the charts.
No wonder Europe’s near-zero, real-growth economy is in such big do-do

 

UK and Norway

Norway gets 90% from hydro reservoir plants and 10% from west coast windmills.
.
Because of long distances, there is little connection between the north and south grid.
.
Any draw by the UK during W/S underproduction affects the south grid.
.
The grid is pumped by generators with 50-cycle electromagnetic waves which travel at near the speed of light.
Electrons do not travel. They just vibrate at 50 Hz
.
Any UK underproduction, resulting in voltage drops, is immediately sensed, and compensated for, by opening the water valves to hydro turbines in Norway.
.
A few years ago, Norway oversupplied Germany and the UK, which resulted in much higher wholesale prices in the south grid, low water levels in reservoirs, rationing, aka blackouts/brownouts, and lots of Norwegians with EVs and heat pumps being p..d off.
.

This time it happened again, and, just like that, the government fell.
INSTANT DEMOCRACY.

We should have it in the US, instead of endless lying, obfuscation, grandstanding, obstruction, etc., for up to 4 years, or, God forbid, 8 years

.

NOTE: I lived in Norway for 3 years. My brother-in-law worked at Norsk Hydro, which provides almost all hydro power in Norway. We talk shop. He thinks the nutcases in Oslo should be exiled to Nova Zembla.

 

Comment by Thinklike A. Mountain on February 2, 2025 at 9:32pm


Senators SCARED of 9/11 Truth!!!

The Washington, D.C., establishment is nervous – and for good reason!

Trump cabinet nominees have been confronted in their confirmation hearings about their refusal to condemn anyone who expresses even the slightest doubts about the truth of the 9/11 official story.

One is on track to be Secretary of Health and Human Services (Robert F. Kennedy Jr.), and the other is slated to become director of the FBI (Kash Patel)!

In this episode of 9/11 Free Fall, host Andy Steele is joined by Gene and Sandra Laratonda  of the weekly 9/11 War Room podcast and writer Craig McKee to discuss these recent exchanges as well as the revelation by former congressman Curt Weldon that the U.S. government hid..................

Weblink:

https://www.ae911truth.org/news/1044-trump-administration-nominees-...

Comment by Thinklike A. Mountain on February 2, 2025 at 7:12pm

Elon Deals the Most Devastating Blow Yet Against the Bureaucratic Deep State One Day After Gaining Access to the State Department’s Payment System, Discovers Hundreds of Billions in Fraud
https://www.infowars.com/posts/watch-live-elon-deals-the-most-devas...

Will John Brennan Be First Criminal Deep Stater Arrested?
https://www.thegatewaypundit.com/2025/02/calm-before-storm-will-joh...

DC U.S. Attorney Sends Letter to Chuck Schumer Related to Threats Against SCOTUS Justices
https://www.thegatewaypundit.com/2025/02/it-begins-dc-u-s-attorney-...

Comment by Dan McKay on February 2, 2025 at 2:16pm

Another nail in the coffin for immensely unpopular investments of land and waters for wind development, not to mention the costs to ratepayers. Ms. Paul has our backs, we must reciprocate.

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2025   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service