Aqua Ventus LLC Has No Business Plan. The People's Bank (Ratepayers) Rejects This Proposal

Pine Tree AKA Aqua Ventus LLC proposes an adjustable-rate power purchase agreement:

 
"The pricing structure proposed by Pine Tree will, pursuant to Chapter 327 Section 3(3)(D), recognize and accommodate “the commercial challenges in long-term cost estimation for large marine energy infrastructure”. It also will “permit power purchase agreement capacity, energy and renewable energy credit prices to be adjusted based on changing costs prior to the final investment decision by New England Aqua Ventus, LLC."
 
The Maine PUC Response:
 
The Act directs the parties to “determine the lowest reasonable cost to ratepayers, that is sufficient to enable the financing, construction and operation of the research array” by NEAV “in a manner that is consistent with the lease issued by the federal Department of the Interior, Bureau of Ocean Energy Management and any final agreement” between NEAV and the State.” In furtherance of this statutory directive, the Hearing Examiners hereby ORDER NEAV to provide the following information relating to their Petition: 
 
1. A fully resourced construction schedule that sets out the timing, labor resources and construction equipment used to construct the project. The project schedule should be provided in MS-Project .mpp format. 
 
2. A description of the project management structure, including identification of equipment suppliers and contractors. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
3. Any subsurface investigation information for the locations where the floating foundation will be moored. This information should be provided in Adobe .pdf or MS-Word .docx format
 
4. Price quotations, or other supporting documentation, for all project components not being fabricated by NEAV or its affiliates. This information should be provided in MS-Excel .xlsx format. 
 
5. An itemized cost estimate detailing the quantity of materials, labor hours, types and costs of equipment used for the fabrication, that NEAV or its affiliates will use to fabricate project components. This information should be provided in MS-Excel .xlsx format. 
 
6. A description of the process NEAV or its affiliates will use to fabricate the floating foundation. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
7. A description of the construction sequencing for installing the foundation, mooring system, wind turbines, cable to the onshore interconnection, etc., for the offshore components of the project. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
8. A description of the interconnection for the project and all onshore project components, including leases, licences or fee simple ownership of property required for the onshore interconnection. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
9. Copies of any studies performed evaluating interconnection options including the costs of interconnecting to the ISO-NE transmission grid. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
10. An itemized build-up of the Development Expenses indicated in Figure 6.2 of the Petition. This information should be provided in Adobe .pdf or MSWord .docx format. 
 
11. An itemization of Financing Costs in Figure 6.2 and discussion of the anticipated financing approach. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
12. Any correspondence or documents shared with and provided by potential project lenders or investors. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
13. An itemization of any project soft costs not included in Development Expenses or Financing Costs, above. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
14. An itemized buildup of project operating expenses, explaining the basis for these estimates. This information should be provided in Adobe .pdf or MSWord .docx format or in MS-Excel .xlsx format. 
 
15. A description of the Community Benefits noted in Figure 6.2, including the status of any discussions and/or undertakings with local communities. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
16. A wind resource assessment that supports the project’s proposed net capacity factor. This information should be provided in Adobe .pdf or MSWord .docx format. 
 
17. A description of the rights that NEAV or affiliates have to the VolturnUS technology, including copies of any agreements pertaining to these rights. This information should be provided in Adobe .pdf or MS-Word .docx format. 
 
18. The Core Proposal states “Pine Tree team, assisted by a separate team of SMEs, commenced design of a fabrication assembly line” (page 7-3). a. What role will NEAV and partners have with respect to funding and ownership of fabrication assembly line? b. What residual rights will there be to NEAV and partners to assembly line? 
 
19. A copy of the working financial pro forma model that was used to develop the required project pricing showing all project assumptions. 
 
This information should be provided in MS-Excel .xlsx format. The information requested shall be filed in the docket, pursuant to the terms set forth in the Temporary Protective Order issued on April 15, 2022, on or before July 15, 2022.
 
 As potential negotiating parties, the Office of the Public Advocate, the Governor’s Energy Office, and Maine’s investor-owned transmission and distribution utilities, Central Maine Power, and Versant Power, may file their own requests for information relating to the NEAV petition in the docket if they choose to do so.

Views: 149

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Willem Post on July 14, 2022 at 10:04pm

DEEP-WATER FLOATING OFFSHORE WIND TURBINES IN MAINE

http://www.windtaskforce.org/profiles/blogs/deep-water-floating-off...

 

The Norwegians have about 60 years of experience building and servicing oil/gas rigs and laying undersea electric cables, gas lines and oil lines all over the world.

 

They have invested billions of dollars in specialized deep-water, Norwegian harbors and facilities for assembly of oil/gas rigs and invested in specialized sea-going heavy lifters, and specialized sea-going tugboats to tow the oil/gas rigs from Norwegian building sites to oil/gas production sites. The heavy lifters and other ships perform services all over the world.

 

Norway companies want to expand their business by building and servicing and providing spare parts for floating wind turbines for deep-water conditions all over the world

 

NOTE: Norwegians advocating expensive floating wind turbines that depend on the randomness of wind and produce high-cost, variable, intermittent electricity for other people, such as Jane and Joe Worker/Ratepayer, is highly hypocritical, because the Norwegians get 98% of their electricity from their own hydro plants, which produce low-cost, steady electricity (not variable, not intermittent). The Danes advocating wind turbines and boasting about their high percent of wind on their grid is similarly hypocritical, because the Danes have been increasingly using the storage reservoirs of Norway’s hydro plants for decades.

 

First Experimental Floating Wind Turbine in Norway

 

Equinor (formerly Statoil, a Norwegian government controlled company) launched the world's first operational deep-water, floating large-capacity wind turbine in 2009. The turbine trade name is “Hywind”.

 

The wind turbine consists of a 120 m (390 ft) tall tower, above the sea water level, and a 60 m (195 ft) submerged extension below the sea water level, with a heavy weight at the bottom to keep the wind turbine steady and upright, even with very high waves and strong wind conditions. The design was tested and perfected under storm and wind conditions simulated in a laboratory.

 

The 2.3 MW wind turbine is mounted on top of the tower. It was fully assembled in a deep-water harbor near Stavanger, Norway.

 

It was towed to a site 10 km (6.2 mi) offshore into the Amoy Fjord in 220 m (720 ft) deep water, near Stavanger, Norway, on 9 June 2009, for a two-year test run, which turned out to be successful.

 

First Commercial Floating Wind Turbine Plant in Scotland

 

Hywind Scotland project is the world's first commercial wind turbine plant using floating wind turbines.

 

It is located 29 km (EIGHTEEN MILES) off PeterheadScotland to minimize visual impacts from shore.

It has five Hywind floating turbines with a total capacity of 30 MW.

It is operated by Hywind (Scotland) Limited, a joint venture of Equinor, Norway (75%) and Masdar, Kuwait (25%).

 

In 2015, Equinor received permission to install 5 Hywind turbines in Scotland.  

 

Manufacturing started in 2016 in Spain (wind turbine, rotor), Norway (tower, underwater base, assembly), and Scotland (various parts)

The turnkey capital cost was $263 million for five 6 MW turbines, or $8,767/kW.

They were designed to float on the surface, with about 180 m (600 ft) above the sea water level and 80 m (265 ft) submerged below the seawater level.

Total steel weight is about 2300 metric ton, total ballasted weight is about 20,000 metric ton.

Heavy weights in the bottom of the submerged parts serve to keep them steady and upright.

 

The turbines were assembled at Stord in Norway in the summer of 2017, using the specialized Saipem 7000 floating crane, and then towed to the north of Scotland by sea-going tugboats.

Make sure to see the videos showing the crane assembling the entire wind turbine.

Nothing like that exists in Maine, or in the rest of New England.

That means offshore wind turbine assembly and servicing would largely be performed by foreign companies, which already have built the infrastructures and other facilities during the past 25 years.

 

https://www.youtube.com/watch?v=PUlfvXaISvc

https://www.youtube.com/watch?v=PmkA6hbJ_j8

https://www.youtube.com/watch?v=bQVU7UaMuck

 

The huge, sea-going, specialized, crane (14,000-metric ton lifting capacity) is required for partial assembly on land and final assembly in an area close to shore with a very deep harbor, before towing, fully assembled, to the site.

 

The finished turbines were towed to Peterhead, Scotland.  

Three  cup anchors hold each turbine in place.

About 2400 meter of chain is required, weighing 400 metric ton, for each turbine.

The Hywind Scotland project was commissioned in October 2017.

 

Hywind Wind Turbines for Demonstration Purposes in Maine

 

Hannah Pingree and other Maine's wind bureaucrats in state government are engaging in mindless prattle, eager to do the bidding of various multi-millionaires and foreign companies that may be providing some wining/dining boondoggle trips to “view the Hywind turbines” in Norway and Scotland.

 

The turnkey cost of those two Hywind turbines would be about $10,000 per kW, versus NE ridgeline wind at $2,000/kW, and regular offshore, south of Martha’s Vineyard, at $4,000/kW.

http://www.windtaskforce.org/profiles/blogs/iso-ne-study-of-1600-mw...

 

That would be at about $120 million for a two 6 MW Hywind wind turbines, plus whatever facilities would need to be built in Maine to support the project.

 

The turnkey capital cost of the wind turbine plant in Maine would be much higher, because Maine does not have the experience of the Norwegians and the specialized equipment and specialized ships, and other facilities. It would be very costly to build those facilities and ships in Maine, or elsewhere.

 

600-ft Tall Hywind Turbines Highly Visible From Mohegan Island, Plus Infrasound

 

The 600-ft tall Hywind wind turbines would be highly visible from Mohegan Island, if they were located TWO MILES east of the island.

 

At that distance, the problem would not be just cyclical, audible noises keeping people awake, but also low frequency infrasound, which can travel many miles, and passes through walls of houses, and can be felt but not heard, and has been shown to have adverse health impacts on people and animals.

http://www.windtaskforce.org/profiles/blogs/wind-turbine-noise-adve...

 

The FAA-required aviation beacons would be clearly visible during nighttime. BTW, they would need to be located about 15 - 20 miles away from Mohegan Island to be unobtrusive to the Islanders.

 

Here is a research report of daytime and nighttime visibility of wind turbines that are about 3 to 4 MW and about 500 ft tall. See URL with photos.

http://visualimpact.anl.gov/offshorevitd/docs/OffshoreVITD.pdf

 

“Study objectives included identifying the maximum distances the facilities could be seen in both daytime and nighttime views and assessing the effect of distance on visual contrasts associated with the facilities. Results showed that small to moderately sized facilities were visible to the unaided eye at distances greater than 42 km [26 miles (mi)], with turbine blade movement visible up to 39 km (24 mi). At night, aerial hazard navigation lighting was visible at distances greater than 39 km (24 mi). The observed wind facilities were judged to be a major focus of visual attention at distances up to 16 km (10 mi), were noticeable to casual observers at distances of almost 29 km (18 mi), and were visible with extended or concentrated viewing at distances beyond 40 km (25 mi).”

 

One has to feel sorry for all the residents of Mohegan Island, but the bureaucrats in Augusta, Maine, do not care about that, because there are not enough votes to stop them. Those bureaucrats are hell-bent to use federal and state grants, subsidies, taxpayer and ratepayer money of already-struggling Joe and Jane Worker to save the world, and to enrich a host of multi-millionaires seeking tax shelters. See Appendix.

 

Some Questions

 

Who are these Aqua Ventus multi-millionaire owners pushing for this expensive project?

How much would be the subsidies?

What would be the energy cost/kWh?

How long would the project last before it would have to be repaired?

How would it be repaired?

Would any special ships, facilities be required?

Does Maine have the required, at least 100-meter, deep-water port?

Is anyone looking at the entire picture on an A to Z basis, or are Maine bureaucrats just dreaming/prattling about castles in Spain?

Does anyone think the Norwegians would not want to make money to maintain/service and provide spare parts for their Hywind wind turbines?

 

Extremely Adverse Impact on CMP Electric Rates

 

LePage’s energy director, Steven McGrath, has focused exclusively on the cost of electricity from the demonstration project.

 

The rate is at least FOUR TIMES above wholesale market value, reflecting the custom design and experimental nature of the platforms.

 

It would start at 23 cents per kilowatt-hour in the first year, escalating at 2.5% per year to 35 cents after 20 years.

 

The PUC estimates it would add up to $208 million over the term, or about $10.5 million a year from Central Maine Power ratepayers. Maine Aqua Ventus had calculated the extra cost would add 73 cents a month to the average household electric bill, in the first year of operation, more thereafter.

  

That is a total rip-off, because Massachusetts pays only an average of 8 - 9 c/kWh over the life of the project.

Main bureaucrats need to learn from Governor Baker.

 

NOTE: The above prices should be compared with NE wholesale prices, which have been about 5 c/kWh since 2008, courtesy of abundant, domestic, low-cost, low-CO2 electricity from gas at about 5 c/kWh, and low-cost, near CO2-free electricity from nuclear at about 4.5 - 5.0 c/kWh.

 

This project is insanity on STEROIDS.

 

One has to feel sorry for the already-struggling Joe and Jane Workers in Maine who will ultimately pay for all this.

https://www.pressherald.com/2018/04/01/effort-to-build-offshore-win...

 

NOTE:

Dear Mr. Greg Kesich, Editor Portland Press Herald

 

(Mr. Greg suggested I write an op-ed regarding the referenced PPH article, so here it is.)

 

This op-ed is in reference to an article on floating wind turbines off the coast of Maine in the Portland Press Herald, dated 20 May 2019.

https://www.pressherald.com/2019/05/20/our-view-blown-off-course-ma...

 

The article states, Statoil had proposed a $120 million demonstration project for two 6 MW Hywind turbines ($10,000/kW) off Boothbay Harbor, but that Governor Page had rejected it. As you recall, his main reason was the higher electricity prices Joe and Jane Worker/Ratepayer would have to pay for 20 years.

 

The article states, Statoil instead took its project to Scotland, where it has invested more than $200 million for five 6 MW Hywind turbines. After some checking, the actual turnkey cost turned out to be $263 million.

 

Scotland got the turbines at $8,767/kW in 2017, but Maine would have gotten the same turbines at $10,000/kW.

 

The article states, “.....and given that country (Scotland) a head start on establishing itself as developer, manufacturer and exporter of offshore technology. Such potential was recognized by the wind energy task force, which was created in 2008 by Gov. John Baldacci and released its findings in December 2009.”

 

That statement is highly naïve and unrealistic. Norway has invested billions of dollars in infrastructures to develop specialized facilities and seagoing ships for shallow-water and deep-water wind turbines during the past 10 - 15 years. Norway has absolutely no intention of establishing Scotland and Maine as competitors.

 

The Scotland/UK actual contributions to the project were:

 

1) Scotland making some parts that were shipped to Norway for assembly

2) Scotland providing the site 18 miles from shore to minimize visual impacts from shore.

3) The UK providing a subsidy of 18.5 c/kWh, plus Statoil selling electricity at about 6.5 c/kWh on the wholesale market, for a total wholesale cost of 25 c/kWh for 20 years. This compares with New England wholesale prices averaging about 5 c/kWh since 2008.

4) The Scotland people paying higher prices/kWh for low-value, variable/intermittent electricity for 20 years that requires the services of other generators for peaking, filling in and balancing year-round. Statoil had to provide a 1.0 MWh li-ion battery system, at a capital cost of about $700,000, to help smooth the flow of the variable electricity from Hywind to minimize disturbances of the Scotland grid.

 

NOTE: If Maine government would have insisted Statoil would build significant infrastructure in Portland, ME, or elsewhere in Maine, Statoil, if willing to do so, would merely have increased the cost of the electricity, c/kWh, to cover its additional costs.

 

NOTE: Massachusetts has signed contracts for 800 MW of offshore wind turbines south of Martha’s Vineyard. If the state government would have insisted the consortium of European companies would build significant infrastructure in New Bedford, MA, or elsewhere in Massachusetts, the consortium, if willing to do so, would merely have increased the cost of the electricity, c/kWh, to cover its additional costs. However, Governor Baker insisted on lowest electricity cost, as that would benefit all of Massachusetts, not just New Bedford, etc. Counting votes is important. See URL.

http://www.windtaskforce.org/profiles/blogs/iso-ne-study-of-1600-mw...

 

NOTE:

School Students Playing with Floating Wind Turbines

 

The main objective with floating wind turbines is to isolate the wind turbine from any wave action, including 30 - 40 ft waves. That can only be done with a long, submerged extension of the wind turbine mast, with a heavy weight inside the bottom of the extension (ballast) to keep the wind turbine steady and upright.

 

Dr. Habib Dagher, Executive Director of the Advanced Structures & Composites Center, should have watched the youtube video, and then given proper instructions to teachers all over Maine, so those teachers could have educated these students regarding the physical requirements, to ensure these students would not waste their valuable time and money building inappropriate models. See URLs and watch both videos.

 

https://www.youtube.com/watch?v=PmkA6hbJ_j8

https://www.wabi.tv/content/news/Students-compete-to-build-most-sta...

 

CO2 Reduction due to Wind Turbines Much Less Than Claimed

 

The Irish Grid

Studies of operating conditions of the Irish grid performed a few years ago showed, at 17% wind on the grid, about 55% of the CO2 was reduced due to wind, instead of the claimed 100%. At higher wind percentages, the percent CO2 reduction would be even less.

 

NOTE: The mantra often promulgated by pro-wind folks is one MWh of wind displaces one MWh of other generation, and as wind uses no fuel there is no CO2, but other generation does use fuel, so that CO2 is avoided. That turned out to be of advantage to pro-wind folks, but is, in fact, highly simplistic.

 

In Ireland, there were years of denial and ignoring of various studies by independent energy systems analysts. Dr. Fred Udo was one of the early analysts of the Irish grid to point out the discrepancy. He was ignored at that time. Another study showed the gas turbines operated near 40% efficiency at 17% wind, whereas, at zero wind, they operated at near 50% efficiency. At that time, the Irish grid had only a minor connection to the UK grid. 

 

The undeniable tip-off was Irish gas imports, which had been predicted to decrease as wind would increase, but had, in fact, not decreased as much as predicted. After much back and forth, the government finally launched an inquiry, which revealed the inefficient operation of the gas turbines at part load (more Btu/kWh, more CO2/kWh), due to the variable, intermittent output of the wind turbines, and their more frequent start/stop operations (high Btu/kWh, high CO2/kWh).

 

Since that time, the Irish grid acquired large capacity connections to the UK and French grids to spread the “discrepancy” over a much larger grid area, which makes it nearly invisible. A Brussels PR problem solved. See URL.

http://www.windtaskforce.org/profiles/blogs/fuel-and-co2-reductions...

 

The New England Grid

Future wind on the NE grid is planned to be about 20% by 2025, i.e., higher than the 17% in Ireland a few years ago, and the NE grid has only minor connections to nearby grids, the same as Ireland a few years ago.

 

At the higher wind percentages, the NE percent CO2 reduction would be even less than 55%, i.e., expensive or inexpensive, variable/intermittent wind is no panacea regarding reducing CO2 and ameliorate global warming.

http://www.windtaskforce.org/profiles/blogs/high-demand-and-low-win...

 

DUCK Curves: DUCK curves due to daytime solar, a minor problem in not-so-sunny Ireland, would impart an additional worsening of grid stability problems after solar would become a significant percentage on the NE grid at noontime in the future.

 

Dealing with the down ramping in the morning as solar is increasing, and the up ramping in the afternoon/early evening as solar is decreasing would impart additional cost/kWh on owners of traditional generators. They likely would be compensated by means of capacity payments by ISO-NE. Those payments should be charged to the disturbers, the solar system owners. However the payments likely would be socialized, i.e., charged to ratepayers/taxpayers.

 

NOTE: If solar system owners were required to install batteries, then the down/up ramping would be avoided, but that would place a cost burden on solar system owners and there would be no end to their complaints.

 

 

Multi-Day Wind/Solar Lulls: Also, during simultaneous wind/solar lulls, which occur at random throughout the year, and may last up to 7 days, a full complement of traditional generation plants and energy storage sources must be available, 24/7/365, to serve NE demand, including future EVs and heat pumps. That storage must be replenished in a timely manner to serve a second lull, which may occur a few days after the first lull. See URLs.

 

The mantra often promulgated by pro-wind folks is “the wind always blows somewhere”. However, weather systems tend to be 500 to 1000 miles long and wide. Any surplus wind electricity would have to come from at least 1000 miles away, which would require high voltage DC lines, as the transmission losses of high voltage AC lines would be too large, plus it would require very robust connections between the NE and nearby grids. Dealing with the wind/solar lull problems would impart additional cost/kWh that likely would not be charged to wind turbine owners but to ratepayers/taxpayers.

 

http://www.windtaskforce.org/profiles/blogs/wind-and-solar-energy-l...

http://www.windtaskforce.org/profiles/blogs/high-demand-and-low-win...

http://www.windtaskforce.org/profiles/blogs/analysis-of-a-6-day-lul...

http://www.windtaskforce.org/profiles/blogs/large-scale-solar-plant...

Comment by Kenneth Capron on July 11, 2022 at 2:26pm

"provide electricity for about 20 years"?

Forget about 20 years. How about just in between major storms and the time to restore service when the turbine platforms sink?

Daring Mother Nature is a tricky proposition. Do so at your own risk!

Comment by Willem Post on July 11, 2022 at 8:17am

What is the turnkey capital cost of this floating boondoggle that will provide electricity for about 20 years.

And what will be the cost of electricity, c/kWh during each one of these years?

This is not rocket science

Show us the year to year spreadsheets with many line items

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."