UMPI turbine website reports new total

Wednesday, June 27, 2012 -The UMPI turbine website just posted a new production figure: 374,690 kWh since "mid-November".

That's 217 days, or an average of 1727 kWh per day.  The "installed capacity" is 14,400 kWh per day, so that's a Capacity Factor of  11.99%.  No other new information is posted - the "full turbine informaiton" software is still not working.

Harry Roper   Houlton/Danforth

Views: 192

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by alice mckay barnett on June 29, 2012 at 9:13pm

10-30% loss in transmission

10-20% loss in parasitic draw

75% loss wind does not blow

 

in the negative      i know

Comment by Willem Post on June 29, 2012 at 5:42pm

EXAMPLE: UNIVERSITY of MAINE WIND POWER A DISMAL FAILURE?

http://theenergycollective.com/willem-post/53258/examples-wind-powe...

The University of Maine, UM, decided to install a 600 kW wind turbine made by RRB Energy Ltd, an Indian company, at its Presque Isle Campus. Results from a 20-month wind resource assessment indicated the campus receives enough wind for a community wind project, not a commercial wind project. 

Community wind power is defined as locally-owned, consisting of one or more utility-scale or a cluster of small turbines, totaling less than 10 MW, that are interconnected on the customer or utility side of the meter. The power is consumed in the community and any surplus is sent to the utility which supplies power as needed.

The purpose was to generate power and to use the wind turbine as a teaching tool for the students. Because it is almost impossible to obtain operating data from the vendors, owners and financiers of wind facilities, UM, to its credit, decided to make available all of its wind turbine operating data. 

http://www.ppdlw.org/umpi.htm

http://www.umpi.edu/wind/timeline

http://www.windtaskforce.org/profiles/blog/show?id=4401701%3ABlogPo...

http://nwcommunityenergy.org/wind

Capital Cost and Power Production

Estimated capital cost $1.5 million

Actual capital cost $2 million; an overrun of 33%

The project was financed by UM cash reserves and a $50,000 cash subsidy from the Maine Public Utilities Commission.

Estimated useful service life about 20 years.

Predicted power production 1,000,000 kWh/yr

Predicted capacity factor = 1,000,000 kWh/yr)/(600 kW x 8,760 hr/yr) = 0.190

Actual power production after 1 year 609,250 kWh

Actual capacity factor for 1 year = 609,250 kWh/yr/(600 kW x 8,760 hr/yr) = 0.116; a shortfall of 39%

Value of power produced = 609,250 kWh/yr x $0.125/ kWh = $76,156/yr; if O&M and financing costs amortized over 20 years are subtracted, this value will likely be negative. 

Actual power production after 1.5 years 920,105 kWh

Actual capacity factor for 1.5 years = (920,105 kWh/1.5 yrs)/(600 kW x 8,760 hr/yr) = 0.117

Operation and Maintenance

According to the European Wind Energy Association: "Operation and maintenance costs constitute a sizable share of the total annual costs of a wind turbine. For a new turbine, O&M costs may easily make up 20-25 percent of the total levelized cost over the lifetime of the turbine." 

Power Used by the Turbine (Parasitic Power)

Parasitic power is the power used by the wind turbine itself. During spring, summer and fall it is a small percentage of the wind turbine output. During the winter it may be as much as 10-20 % of the wind turbine output. Much of this power is needed whether the wind turbine is operating or not. At low wind speeds, the turbine power output may be less than the power used by the turbine; the shortfall is drawn from the grid. 

Two little-wind days were selected; a summer day and a cooler winter day to show that in summer the parasitic power is less than in winter. In winter, the wind speed has to be well above 4.5 m/s, or 10.7 miles/hour, to offset the parasitic power and feed into the grid. Speeds less than that means drawing from the grid, speeds greater than that means feeding into the grid. 

This will significantly reduce the net power produced during a winter. On cold winter days, even at relatively high wind speeds of 10.7 miles/hour, or greater, power is drawn from the grid, meaning the nacelle (on big turbines the size of a greyhound bus) and other components require significant quantities of electric power; it is cold several hundred feet above windy mountain ridges.

14 May, 2010, wind speed 2.9 m/s (6.9 miles/hour), net power output  -0.3 kW.

20 Nov, 2010, wind speed 4.5 m/s (10.7 miles/hour), net power output -5.6 kW.

Below is a representative list of equipment and systems that require electric power; the list varies for each turbine manufacturer.

- rotor yaw mechanism to turn the rotor into the wind

- blade pitch mechanism to adjust the blade angle to the wind

- lights, controllers, communication, sensors, metering, data collection, etc.

- heating the blades during winter; this may require 10%-20% of the turbine's power

- heating and dehumidifying the nacelle; this load will be less if the nacelle is well-insulated.

- oil heater, pump, cooler and filtering system of the gearbox

- hydraulic brake to lock the blades when the wind is too strong

- thyristors which graduate the connection and disconnection between turbine generator and grid

- magnetizing the stator; the induction generators used to actively power the magnetic coils. This helps keep the rotor speed constant, and as the wind starts blowing it helps start the rotor turning (see next item)

- using the generator as a motor to help the blades start to turn when the wind speed is low or, as many suspect, to create the illusion the facility is producing electricity when it is not, particularly during important site tours. It also spins the rotor shaft and blades to prevent warping when there is no wind.

Conclusions

The huge difference between predicted and actual capital cost and capacity factor would be disastrous for a commercial installation. Because this is for “teaching purposes” such a detail is apparently not that important. The capital cost and any operating costs in excess of power sales revenues will likely be recovered by additions to tuition charges.

UM should find less expensive ways to educate students in all areas, not just wind power. Cost per university student in the US is already well over 2 times that of Europe, a competitive disadvantage.

Comment by alice mckay barnett on June 27, 2012 at 8:57pm

thank you Harrison and LI....keep on

Comment by Long Islander on June 27, 2012 at 5:29pm

This PDF at the link below examines the history of the University's industrial wind turbine. As the sole onshore wind experiment by the state, and not an insignicant expense of $2 million and counting, we believe it should give the state pause to question the overblown electricity production promises of the wind industry, on which were based much of the state's expedited wind law that is presently creating havoc with our citizens' health, citizens' rights, wildlife, quality of place, town social dynamics and electricity/transmission rates.

UMPI%20Turbine%20Backgrounder_8-3-11.pdf

Comment by Long Islander on June 27, 2012 at 5:19pm

"Although the turbine began spinning in mid-May, Zillman said officials “really view July 1, 2009, as the power bill comparison measure.”

- UMPI president Donald Zillman

May 18, 2010

http://bangordailynews.com/2010/05/18/news/umpi-windmill-lsquoa-gre...

So I guess that means the University will be telling us the three year production to date on July 1?

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service