Massachusetts Wind Turbine Fraud Using ARRA Stimulus Funds

Falmouth Wind Turbine II ARRA Grant/Loan Fraud: Health/Safety

Town created "a substantial and specific danger to public health or safety related to the implementation or use of covered funds" Nuisance

Falmouth, Massachusetts USA November 1, 2018 

Falmouth Select Board Members: Susan L. Moran, Chairman - Megan English Braga, Vice Chairman- Doug Jones. Samuel H. Patterson. Douglas C. Brown.

In 2005 the Town of Falmouth had a study done that included an acoustic decibel map showing a General Electric 1.5 megawatt wind turbine would break state noise regulations at up to 200 residential homes around the Wastewater Treatment Plant. The study stated that a Special Permit 240-166 was required. General Electric a domestic wind turbine company refused to place one single wind turbine.

Between 2010 and 2012 the Town of Falmouth went forward installing two Vestas V-82 commercial 1.65 wind turbines generating 110 decibels each almost twice as loud on the decibel scale as the General Electric wind turbine. The turbines were installed in disregard for public safety and health despite emails and a written warning from Vestas of America warning of the 110 decibels.

The Town of Falmouth in order to get ARRA, American Recovery, and Reinvestment Act, funds filed an EPA waiver to buy Falmouth Wind II a Vestas foreign made wind turbine. In that waiver, it said there were no domestic wind turbines available. The refusal by General Electric over residential setbacks and ice throw were omitted. The federal EPA waiver filed by the town referred to filing Special Permit 240-166 which the town never filed.

The town put the safety and health of its citizens at risk building the turbines using federal stimulus funds.

The Town of Falmouth after eight years of litigation witnessed on October 15, 2018, the production of a study to move Wind II to a new location because the courts have determined the turbines are a nuisance.

The study at a cost to taxpayers of $14,000.00 did not include an acoustic noise model done by experts and made no reference to Falmouth Wind II generating 110 decibels of noise. Safety & Health ignored in 2018.

In court testimony to shut down the wind turbines, expert acoustic testimony was given that a 108-decibel wind turbine needs noise setbacks at 2228 feet. The Falmouth wind turbines generate 110 decibels requiring even greater setbacks. There is no location safe at the Wastewater Treatment Plant.

The town hopes to move Falmouth Wind II and move the 5 million dollars loan/grant and project regulatory agreement with it to avoid paying the loan.

This brings us to what is ARRA Grant Fraud? Simply put, fraud is Lying, cheating, and stealing in the performance of a government grant, contract, or loan.
There is a fine line between Fraud and a Mistake… That line is Intent!

Ignoring the health and safety of up to 200 residential homeowners crossed the line creating a substantial and specific danger to public health or safety related to the implementation or use of covered funds.

The elements of fraud are: a false representation of fact, knowledge of the falsity by the party making the false representation, intent to deceive the party by making the false representation, reasonable reliance by the innocent party and actual loss suffered by the innocent party.

Where is the expert acoustical noise study to move Falmouth Wind II today?

The Town of Falmouth after years of omitting negative documents showing the wind turbines should never have been built are going forward again without any expert acoustic noise models with a wind turbine financed with ARRA funds that took the health and safety of residential homeowners

#1 ARRA --American Recovery and Reinvestment Act of 2009 Terms and Conditions May 2009 
The Town of Falmouth created "a substantial and specific danger to public health or safety related to the implementation or use of covered funds."

#2 PRA --Project Regulatory Agreement Falmouth Wind II - Brokered by Massachusetts Department of Environmental Protection - Financed by Massachusetts Clean Water Trust with SRF, State Revolving Funds

#3 Wind Turbine Noise -- Can cause heart disease, tinnitus, vertigo, panic attacks, migraines and sleep deprivation.

-------------------------------------------

Falmouth Select Board Wind Turbine Study To Move Falmouth Wind Turbine II

October 15,2018 Video 

Views: 218

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Frank Haggerty on November 1, 2018 at 10:49am

Danger: The Town of Falmouth  put the safety and health of its citizens at risk building the turbines using federal stimulus funds and continues to go forward endangering the public despite acoustic evidence of fraud.

The setbacks are well beyond 2228 thousand feet for new location of Falmouth Wind II

August 3, 2010 : WasteWater Superintendent, Town of Falmouth Public Works
59 Town Hall Square
Falmouth, MA 02540

RE: Falmouth WWTF Wind Energy Facility II "Wind II", Falmouth, MA
Contract No. #3297

"The Town has previously been provided with the Octave Band Data / Sound performance for the V82 turbine. This shows that the turbine normally operates at 103.2dB but the manufacturer has also stated that it may produce up to 110dB under certain circumstances. "

There are NO safe locations at the Wastewater Treatment Plant

http://www.windaction.org/posts/41357-vestas-raises-concerns-about-...

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."