Massachusetts A Guilty Party In GE vs Vineyard Wind Case ?

Party 1: GE Vernova set to terminate its $1.3 billion contract, alleging that Vineyard Wind failed to pay over $300 million for work performed. GE is the manufacturer of the product.
.
Party 2: Vineyard Wind claims 800 million for "catastrophic injury" from defective blades manufactured by GE Renewables in Canada. Vineyard Wind is an offshore wind project off the coast of Massachusetts. 
.

Party 3: The State of Massachusetts failed to test any of the 150 GE blades manufactured in Canada.

On May 12, 2026, a Massachusetts Superior Civil Court judge will make a decision (2684 CV 01041).

There is a third-party question: the State of Massachusetts failure to test any of the 150 blades made in Canada. 
.
The Wind Technology Testing Center (WTTC) in Massachusetts, operated by the Massachusetts Clean Energy Center, was built to accelerate wind energy development by providing specialized testing, validation, and certification services for large wind turbine blades. MassCEC failed to perform a torsion test on the blade. 
.
The Wind Testing Facility only tested one GE Vernova prototype blade, manufactured in Cherbourg, France, for structural integrity, with 50 feet of the blade cut off due to size constraints. The blade was 351 feet, and the test center was too small. 
.
Massachusetts had set unrealistic renewable energy goals, cutting 50 feet off the test blade to get approval to manufacture 150 blades at the LM Wind Company, owned by GE in Gaspé, Canada. They extrapolated the figures to approve the blade. 
.
In the race to build the offshore wind project, none of the 150 blades made in Canada were tested by the MassCEC testing facility. Sources assert that "it would not have made a difference" if the Canadian-made blades had been tested at the wind testing site.  The Massachusetts Wind Technology Testing (WTTC) "copped out" of responsibility by allegedly certifying oversized blade designs through data extrapolation rather than full testing. 
.
During the initial Vineyard Wind construction project phase, 68 of the 72 GE Canadian-made blades were found defective, requiring removal. In January 2025, the US government ordered the removal of all blades made at the facility in Gaspé, Canada.
.
To build and coordinate the offshore wind project, there were three parties. GE Renewables, Vineyard Wind, and the State of Massachusetts
.
Massachusetts failed to provide specialized testing, validation, and certification of any of the 150 blades made in Canada.  Guilty? 
.

 

Views: 73

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."