Friday, June 13, 2014 Hawaii wind player gets comeuppance in Maine |
||||||||
|
First Wind Rejection by Maine Making the National Industry Press
Could it be that when First Wind spoke with this reporter, they may not have brought up the Rhode Island PPA they pre-sold:
The denial of the Bowers project presents First Wind with a conundrum. On August 2, 2013, nine days after DEP announced that it would reject the Bowers project, First Wind signed a 15-year contract with National Grid, the utility that supplies electricity to customers in Rhode Island. Under terms of the contract, First Wind must build the Bowers Project and send its electricity to businesses and residents in Rhode Island. The company was so confident that the Bowers project would be approved on appeal that it put up approximately $1.5 million, money it will forfeit if it can’t deliver on the contract.
Additional information: http://www.ppdlw.org/
Maine Regulators Issue Third Strike Against First Wind Project
by NAW Staff Tuesday June 10 2014
|
http://www.nawindpower.com/naw/e107_plugins/content/content.php?con...
********************************************************************************************************
First Wind Fail
You can watch the entire BEP proceeding that took place 6/5/14 on YouTube. The Bowers item comes up at 11 minutes 11 seconds. Click this link to go straight to it.
*****************************************************************************************************
The citizen-run Board of Environmental Protection, which handled the appeal, voted 4-1 Thursday to uphold DEP Commissioner Patricia Aho’s rejection of the project.
Please continue reading at:
http://bangordailynews.com/2014/06/06/business/citizen-board-uphold...
*****************************************************************************
In its semi-annual tracking poll, Critical Insights of Portland asked Maine people three questions about wind energy. The company completed 601 telephone interviews (including cell phones) with randomly selected voters across the state between April 16th and April 24th, 2014. Poll results (at this link) indicate that support for building industrial wind turbines declines appreciably when respondents learn that:
Read more here.
*****************************************************************************************************
State of Maine Says NO to Giant Wind Power Project in God's Country
Breaking news from the Partnership for the Preservation of the Downeast Lakes Watershed (PPDLW):
Maine’s Board of Environmental Protection rejects First Wind appeal,
affirming DEP denial of Bowers Mountain Wind Project
Augusta, Maine — June 5, 2014 — Maine’s Board of Environmental Protection (BEP) today rejected two appeals and affirmed a 2013 decision by the Department of Environmental Protection (DEP) to deny a permit for the Bowers Mountain Wind project proposed for Carroll Plt. and Kossuth Twp. Appellants were Boston-based developer First Wind and landowner Douglas E. Humphrey.
“We are very pleased with this decision, but not surprised,” said Gary Campbell, president of local conservation group, the Partnership for the Preservation of the Downeast Lakes Watershed (PPDLW). “This project would have seriously damaged the scenic value of nine lakes that the State of Maine has designated as significant scenic resources, lakes that the legislature specifically shielded from wind projects.”
Campbell continued, “This constellation of more than 20 glacial lakes is very valuable to Maine. Sportsmen have been coming here for nearly 200 years and this was a crossroad of major water routes used by the native Abenaki people for many centuries before that. The lakes are largely undeveloped, the water is clean and they’re peppered with islands that have primitive campsites. You can spend weeks exploring by canoe, kayak or motorboat and camp on a different island every night.”
This was First Wind’s third attempt to put a project on the mountains overlooking the Downeast Lakes. The Land Use Regulation Commission (LURC) rejected the Bowers project in 2012, DEP rejected a modified Bowers project in 2013, and now BEP has reached the same conclusion in 2014.
In a last minute attempt to derail the BEP denial, First Wind attorney Juliet Browne filed a request that the Board either grant the appeal or remand the case back to DEP so First Wind could have the opportunity to modify the project. This request was unanimously voted down by the Board.
"To put forward a request to amend the project 72 hours before the final vote is ridiculous. First Wind could have amended the project any time over the past ten months but decided to file an appeal instead. We’re glad that the BEP saw through the tactic and rejected First Wind’s appeal.”
The Bowers project called for sixteen 459’ tall wind turbines to be erected on Bowers Mountain and neighboring hills in Carroll Plantation and Kossuth Township in Penobscot and Washington Counties. The project would have had a total nameplate capacity of 48MW with an actual output of approximately 14MW.
Although the turbines were to be sited in Maine’s Expedited Permitting Area (EPA), where scenic impact standards are reduced for grid-scale wind energy projects, it was within 1200’ of a large area that had been omitted from the EPA in order to protect the scenic value of the Downeast Lakes Region.
The denial of the Bowers project presents First Wind with a conundrum. On August 2, 2013, nine days after DEP announced that it would reject the Bowers project, First Wind signed a 15-year contract with National Grid, the utility that supplies electricity to customers in Rhode Island. Under terms of the contract, First Wind must build the Bowers Project and send its electricity to businesses and residents in Rhode Island. The company was so confident that the Bowers project would be approved on appeal that it put up approximately $1.5 million, money it will forfeit if it can’t deliver on the contract. First Wind’s only option now is to appeal the BEP’s decision to Maine’s Supreme Court.
“We’ve been fighting to protect this remarkable network of scenic lakes for four years now,” Campbell said. “First Wind claims to be doing what’s best for Maine but these endless hearings cost the taxpayers a lot of money. Three strikes and you’re supposed to be out. I hope this time the developer gets the message leaves this treasured area alone.”
* * * * *
Contact PPDLW: http://www.ppdlw.org/contactus.htm
Comment
This is truly a CITIZENS' victory over the most arrogant wind power developer in Maine. It is heartening to see that DEP, because it held a true HEARING, and not just a public comment meeting, could find the truth, apply it to the constraints embedded in the "Wind Law" (PL 661), and reach the proper decision that the magnificent lakes in this region are worthy of protecting from this scourge. Moreover, after the debacle of the Passsadumkeag reversal of the denial by the Board of Environmental Protection (BEP), it was a pleasant surprise to see the BEP be fair rather than being advocates for the wind industry.
Let First Wind appeal to the Law Court. I've sat through all the wind appeals and I expect the Law Court to be consistent and apply the same reasoning to uphold the denial as they have in upholding approvals; that is, the DEP and BEP followed the law and there is no role for the Law Court to overturn a law that was the intent (albeit misguided, hurried, and ignorant back in 2008) of the Legislature.
U.S. Sen Angus King
Maine as Third World Country:
CMP Transmission Rate Skyrockets 19.6% Due to Wind Power
Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.
Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT
******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********
(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/
Not yet a member?
Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?
We have the facts on our side. We have the truth on our side. All we need now is YOU.
“First they ignore you, then they laugh at you, then they fight you, then you win.”
-- Mahatma Gandhi
"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi
Task Force membership is free. Please sign up today!
Hannah Pingree - Director of Maine's Office of Innovation and the Future
"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."
https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/
© 2025 Created by Webmaster.
Powered by
You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!
Join Citizens' Task Force on Wind Power - Maine