Why am I not surprised that this article doesn't touch upon any of the negatives associated with batteries on the grid. Maybe start with what all these new batteries, including all of those in EV's, will do in terms of damaging the environment. Maybe tell me how much it costs and compare that to all the alternatives. Puff pieces are an important part of brainwashing. Me? I do NOT accept the inevitability of an all electric future and am very sick and tired of how one sided are the mainstream media.
By Murray Carpenter
Published July 19, 2022 at 7:17 AM ED
The white boxy structures across the river from the former Great Northern Paper mill in East Millinocket, Maine, don’t look like much from a distance. But a closer look offers a glimpse of Maine’s green energy future — one that's battery powered.
This story is part of our series "Climate Driven: A deep dive into Maine's response, one county at a time."
Half a mile down a dirt road through the woods, you come to a clearing above a dam on the West Branch of the Penobscot River. Nine gleaming white cubes, each the size of a short shipping container, are sitting on cement pads. They generate a faint hum.
The boxes are marked with a red logo: Tesla. They are high-tech lithium ion batteries known as Tesla Megapacks.
“The total of nine megapacks together is 10.3 megawatts. But they can do that for two hours, so the capacity is actually 20.6 megawatt hours,” says Jamey Cole, an electrical engineer with Brookfield Renewable, which owns this battery system. “Each one of these obviously is DC, and they have an inverter which will convert it to AC which is what our grid is. From there it will get stepped up on a transformer, and the battery will go out at AC at 34,500 volts.”
That’s a lot of numbers, but the takeaway is that the Megapacks hold a significant amount of juice, enough to power about 9,000 New England homes for two hours. That's the reason the batteries have been placed next to an existing substation that’s linked to Brookfield's East Millinocket dam.
And they don't just store renewable power when it's abundant and save it for times when it’s not. Cole says it’s a bit more complicated.
“Ideally we would keep them about 50% charged, that way if they needed, the grid needed power we can put it out, or if the grid needed us to take power, we could put it in," he says.
Cole says Brookfield can use the batteries to respond to the needs of ISO New England, which manages the regional electrical grid.
"It all depends on how we operate day to day. It may sit there and it may follow what ISO wants us to do; it might charge one minute and discharge the next. Or if the demand is there and we have the power, they may be asked to output power for the next two hours. It kind of goes day to day, depending on the grid needs,” he says.
In the best scenario, Brookfield could be paid to pull energy off the grid, when it is “negatively priced,” then sell it back when it has a higher value.
The corporation has another similar facility just up the road at the former mill in Millinocket. And it’s planning two more near its dams on the Androscoggin and Saco rivers.
Another company, NextEra, has a battery on Cousins Island in Yarmouth. These are some of the first sparks in a coming charge of battery power.
Chris Rauscher works from Maine for Sunrun, a national company specializing in solar and battery systems for residences. He is not involved in these large Maine battery projects, but he says, in general, batteries are sort of like bacon.
“Everything is a little better with bacon on it. And that’s true for the grid, everything is better with a battery attached. That’s whether we’re talking about homes or businesses that need backup power from a battery if the grid goes down, or renewable installations like solar and wind, the batteries can provide firming up, can provide energy at night when the sun isn’t shining on or when the wind isn’t blowing, or to provide all sorts of other services on the grid,” he says.
Battery storage is one part of a massive electrification project that will be increasingly critical as the nation weans itself from the fossil fuels that are the biggest drivers of climate change. The grid will be carrying more juice as more renewable power projects come online, and electricity replaces internal combustion engines in cars and other uses.
A bill signed by Maine Gov. Janet Mills in 2021 established a state goal of developing 300 megawatts of battery storage by 2025 and 400 megawatts by 2030.
State Rep. Mo Terry of Gorham sponsored a bill this year creating sales tax exemptions for battery storage developers, and directing the Governor’s Energy Office to explore other tax incentives for the industry.
Terry says a battery storage facility planned for her hometown is on an entirely different scale than those now operating in Maine.
“The storage facilities that we have right now are on the smaller size, 10-15 megawatts per facility, where the one that’s coming to Gorham is hopefully going to be up to about 150 megawatts of storage,” she says.
That proposed facility, Plus Power’s Cross Town Project, would be about 17 times the size of the Tesla system near East Millinocket. That's about enough to power 150,000 Maine homes for two hours.
Back at the Tesla battery plant near the East Millinocket dam, Cole says not only are batteries like these becoming more abundant, the technology is evolving quickly.
“The size of the batteries now, the technology seems to be a lot better. Probably 10-15 years ago, they would have been three times the size of what it is now. They're always developing the technology, and I would say there probably is coming something that will be a lot smaller in the future, that's for sure,” he says.
But for now, these batteries sitting on a bank above the river in the North Woods, quietly breathing energy in and out, are state of the art, offering a small glimpse of the electrified future.
https://www.mainepublic.org/environment-and-outdoors/2022-07-19/big...
*************************************
Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.
Comment
I see that the article is also in the Bangor Daily News.
https://www.bangordailynews.com/2022/07/19/news/penobscot/maine-ele...
Energy leaving a battery system is about 80% of what fed into it, from high voltage grid connection, via a step-down transformer, then via front-end power electronics, then into the battery, then out of the battery, then via back-end power electronics, then via a step-up transformer to the high voltage grid grid connection.
Night-time electricity is about 3 to 4 c/kWh, late-afternoon/early-evening electricity is about 7 to 8 c/kWh.
That small difference would not offset the owning and operating cost of the battery, which last at most 15 years and cost about $600/kW to install; turnkey
The owners should present spreadsheets to prove the economic viability of utility-scale battery systems
From the article: "In general, batteries are sort of like bacon. Everything is a little better with bacon on it. And that’s true for the grid, everything is better with a battery attached."
Bacon huh. File this statement under the heading of sounds good until you think about. Shallow, superficial sales speak. Now if the comparison to bacon was that these projects are so often pork, I would agree. Or if batteries often get fried like bacon, then I might agree to that also. If we talked about how both bacon and supposed green projects come from pigs, again I'd concur.
U.S. Sen Angus King
Maine as Third World Country:
CMP Transmission Rate Skyrockets 19.6% Due to Wind Power
Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.
Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT
******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********
(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/
Not yet a member?
Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?
We have the facts on our side. We have the truth on our side. All we need now is YOU.
“First they ignore you, then they laugh at you, then they fight you, then you win.”
-- Mahatma Gandhi
"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi
Task Force membership is free. Please sign up today!
Hannah Pingree - Director of Maine's Office of Innovation and the Future
"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."
https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/
© 2024 Created by Webmaster. Powered by
You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!
Join Citizens' Task Force on Wind Power - Maine