Construction proceeds on NECEC power corridor through western Maine

About 41% of foundations for the setting of poles on the NECEC corridor have been completed, 31% of poles have been set and 34% of circuit wires are done, the developer said.


July 3, 2024

Stephen Singer
Press Herald

EXCERPTS

The developer of a controversial 145-mile electricity transmission line through western Maine has told state regulators it’s making progress after resuming work last October, but projects such as setting foundations for poles and running wires are only about one-third completed.
In a report Monday on the New England Clean Energy Connect, Avangrid, the parent company of Central Maine Power, told the Public Utilities Commission that access to the route is about 81% complete. However, 294 foundations for the setting of poles have been completed, or about 41% of the total; 217 poles have been set, 31% complete; and 36 circuit miles of wire work are done, or 34% of what’s required, Avangrid said.

The corridor, which is to bring hydropower from Canada to the New England electrical grid, has grown to $1.5 billion from an original price tag of $1 billion due to delays and cost inflation.

The report provided no information about when the project may be completed but indicated another report would be filed in January. Avangrid also did not say how much the delay may have cost developers, and said it would not comment on the report.

https://www.pressherald.com/2024/07/03/construction-proceeds-on-con...

************************************* 


Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.

 

Views: 19

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by arthur qwenk on July 7, 2024 at 7:36am

 NECEC won't help Maine.Maine energy costs are  exorbitant due to green washed braindead Augusta energy policies  and passive citizens controlled by socialists. trifecta Boston North socialists.

Comment by Dan McKay on July 5, 2024 at 8:39am

Expect an AI data center popping up in Lewiston

Comment by Willem Post on July 5, 2024 at 7:54am

If there is another ice storm, no power will come from Canada.

The hydro power will be used to counteract the variable, intermittent, up/down output of wind and solar systems, 24/7/365, instead of unaffordable battery systems that last about 15 years

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service