BDN - Aroostook wind megaproject is 1st in Maine to need legislative approval

by Lori Valigra

September 25, 2023

EXCERPTS

Doug Mulvey and his company, LS Power, wanted to minimize the risk of their multi-billion-dollar bid for a 160-mile transmission line that would bring wind power through Aroostook County and onto the New England grid.

So they asked the Maine Legislature in March to approve the project, and by June they received it. The approval was required under provisions of the citizen initiative passed by voters in 2021 that also had aimed, unsuccessfully, to derail another large project — a Central Maine Power Co. affiliate’s hydropower line through western Maine.

The Aroostook wind project is the first high-impact transmission line covered by the new Maine law.

Not everyone was pleased by the project being approved so quickly. Some Republican lawmakers questioned in a legislative work session whether more information, including the final route for the project, should be submitted first.

Mulvey said it is an unusual step for a state to require, and it took more than four months to get the nod from Maine lawmakers, but it was necessary to protect his company’s investment.

“I’m not aware of any other state where legislative approval is required for a project like this,” said Mulvey, vice president of project development for LS Power. “I’ve never gone through that.”

The 33 year old private company, which develops, invests in and operates electricity infrastructure, has installed more than 680 miles of transmission lines across the United States.

The law created after the citizen initiative does not specify how and when to apply for approval, but getting early confirmation of a project from the Legislature rather than waiting until it is already in progress adds certainty for developers like LS Power, Maine Public Advocate William Harwood said. His office has not taken a position on the project.

“If they think the Legislature still has a veto right, that’s way too much risk,” Harwood said. “So you’ve got to consent to the building of this line.”

LS Power agreed that the first step for any project it proposes is whether the state is willing to allow it. Mulvey said his company was aware of efforts to retroactively require legislative approval for the CMP affiliate’s hydropower project. Critics of the Maine referendum had worried that if the hydropower corridor was stopped it could send a signal to other prospective developers that their multi-million-dollar plans might be reversed by the state.

“There would have been a concern of investing a ton of money in the state and then having a lot of uncertainty later in the process,” Mulvey said.

The law spawned by the referendum requires that any high-impact electricity project longer than 50 miles and substantially altering the land must be approved by the Legislature, as would any project that uses public lands. The Aroostook project exceeds the mileage limit.

The companies behind the Aroostook Renewable Gateway project are LS Power of New York, which intends to build the 345 kilovolt transmission line, and Longroad Energy’s King Pine Wind of Massachusetts, which is responsible for the 170 wind turbine array that would be able to generate 1,000 kilowatts of energy to run through the transmission line. The project is being billed as the largest of its kind on the east coast.

Founded in 2016, Longroad Energy owns 1.5 gigawatts of wind and solar projects across the United States. It is owned by two New Zealand companies, NZ Super Fund and Infratil Limited; MEAG of Germany; and Longroad Energy Partners LLC. Both companies have extensive operations across the United States.

The LS Power transmission line would run from Glenwood Plantation to Dixmont or Detroit, with substations in the two terminus locations and a third near Coopers Mills Road in Windsor.

The Maine Public Utilities Commission chose the companies last October in two separate bids because they had the lowest combined amount for the project and had the experience to build it, PUC Chairman Philip Bartlett said.

The entire project is projected to cost ratepayers $1.7 billion over 30 years. The cost of the power line is expected to be $2.8 billion, but it would be offset by lower electricity prices driven by the wind turbines over 20 years. These are estimates, however, as the final costs to consumers won’t be known until energy contracts with utilities are completed.

Central Maine Power and Versant Power ratepayers would pay for 60 percent of the project, or about $1 billion, with three Massachusetts utilities paying for the remaining 40 percent.

The PUC, LS Power, Longroad, CMP and Versant are currently negotiating contract rates for the power with the Maine and Massachusetts utilities. Bartlett said he hopes those negotiations will conclude soon so that the project can move ahead. Mulvey said one unusual aspect of the project is that it aims to get a fixed rate for the utilities for 20 years, which will provide more stable prices for consumers.

Both companies still must get various local, state and municipal permits, including from the Maine Department of Environmental Protection, the U.S. Army Corps of Engineers, and the Land Use Planning Commission, which oversees the unorganized territory.

LS Power must also get a certificate of public convenience and necessity from the PUC for the power line. That certificate would give LS Power the right to acquire land for its project by eminent domain. LS Power is still determining the route for the project, which it expects to go into service by the end of 2028 or early 2029.

The project could develop significant amounts of renewable generation in northern Maine at a competitive cost and boost the regional economy, including with thousands of jobs. Longroad’s King Pine Wind farm is expected to produce about 3 billion kilowatt-hours of electricity annually, which the company said is enough to power roughly 270,000 homes per year in Maine and 180,000 homes in Massachusetts.

Longroad also said the wind farm will help avoid about 1.3 billion tons of carbon dioxide emissions annually, equivalent to removing 260,000 vehicles from the road. The proposal will help Maine reach its climate goals of 80 percent renewable energy by 2030 and 100 percent by 2050, supporters have said.

“Such projects would provide substantial economic development benefits, property taxes, construction jobs and many other benefits to a part of our state that could surely benefit from these investments,” PUC Commissioner Patrick Scully said when the bid winners were announced.

The Legislature has been looking at tapping the ample wind available in Aroostook County for at least a couple decades, which is one of the reasons why the current project was approved, sources familiar with the project said.

It was quick to set new laws in motion. Two main bills propelled the Aroostook wind project.

Testimony on the first bill, LD 1710, to spur development of renewable energy in northern Maine, began on June 16, 2021. It was enacted into law soon after, on June 29. The PUC issued a request for proposals for the Aroostook project on Nov. 29, 2021, and chose winning bidders, LS Power and Longroad, on Oct. 26, 2022.

The bids and names of other bidders are confidential, according to the PUC.

Then the Legislature approved a second bill, LD 924, to greenlight the project for the bidders the PUC had selected. Gov. Janet Mills signed that bill into law on June 22, 2023. Both bills were sponsored by Senate President Troy Jackson, D-Allagash.

The project is unusual in that there were two separate requests for proposals, one for the power generation and another for the transmission line. Adding another level of detail, the transmission line can handle 1,200 megawatts of power, but Longroad is only supplying 1,000 megawatts. A potential third company could be chosen to supply the remaining 200 megawatts under LD 1943 governing future energy procurement.

The next big milestone for Longroad’s part of the project is getting power purchase contracts with CMP, Versant and the Massachusetts utilities, Chad Allen, director of development at Longroad, said. The company also is studying the land for its turbine array, which it has under option. In 2017 Longroad purchased the assets of First Wind, which had an option on the land signed in 2011.

“We need to ensure that the land is appropriate and suitable to construct the project,” Allen said.

LS Power, which owns the Kibby Wind Power Project in Franklin County, is also focused on the contracts. It plans to hold additional meetings with local communities. It already has held six public meetings attended by more than 700 people and is using that feedback to help finalize its transmission route, Mulvey said. The company has heard people’s concerns about the route crossing agricultural fields and property with planned new homes.

“We’ll have another series of open houses later this year,” he said.

Lori Valigra is an environment reporter for the Bangor Daily News.

https://www.bangordailynews.com/2023/09/25/mainefocus/aroostook-win...

************************************* 


Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.

Views: 96

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Dan McKay on September 25, 2023 at 5:17pm

Jackson is slaveowner over the democrats in the house as well as the senate. They fear him and not the people. Even some republicans fear him. This is defined as tyranny. 

The only way to give this boondoggle the heave-ho is for people to attend the PUC and DEP hearings and deny approval of this project. Let town hall know how bad this project is to landowners, ratepayers and the reliability of the ISO-NE grid. 

Comment by Willem Post on September 25, 2023 at 8:29am

Maine northern areas are being treated as a colony by Massachusetts, etc., to be exploited for wind turbines and power lines to transmit power to Massachusetts under long term 20-y contracts.

Any “approvals” are strictly pro for a

Nobody gives a damn about the turnkey capital cost/MW, which has increased 50% since 2021, to save the world while going bankrupt

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service