Vermont has a Comprehensive Energy Plan, CEP. The capital cost for implementing the CEP would be in excess of $1.0 billion/y for at least 33 years, per Energy Action Network annual report. See URLs.
http://eanvt.org/wp-content/uploads/2016/04/EAN-2015-Annual-Report-...
https://outside.vermont.gov/sov/webservices/Shared%20Documents/2016...
ENERGY ACTION NETWORK
“Meeting Paris”: Energy Action Network, EAN, claims about: 1) $1.115 billion less would be sent out of state to buy fossil fuels, and 2) $323 million in savings from additional, in-state investment (primarily weatherization), would yield net savings to consumers of 1115 – 323 = $792 million during 2020 – 2025, if its measures to reduce CO2 by 2.281 million metric ton to “meet Paris” were implemented by 2025. See Note, and page 4 and 5 of EAN URL
https://www.eanvt.org/wp-content/uploads/2020/03/EAN-report-2020-fi...
Capital Cost to “Meet Paris”: The measures are a multi-billion-dollar wish list of EAN members with a cost exceeding $15.536 billion during 2020 – 2025, about $3.107 billion/y. EAN members want these heavily subsidized measures, because it is good for RE businesses.
Amortizing the cost of the mostly short-life assets (EVs, ASHPs, battery storage systems, etc.), at 3.5% over 15 years, would require annual payments of $1.333 billion, more than offsetting the 800/5 = $160 million/y of energy cost savings.
https://www.myamortizationchart.com
It took about 20 years (2000 – 2020) to achieve the existing conditions by spending about $210 million/y, including Efficiency Vermont. The annual spending to “meet Paris” during 2020 - 2025 would be at least 10 times greater.
These measures would be major burdens on the stagnant Vermont economy, its businesses, ratepayers, taxpayers, etc., while in the middle of a major recession, with decreasing tax collections by state government (room & meals, sales, income, gasoline, etc.), due to the coronavirus.
EAN Savings and Capital Cost Estimate: The EAN report promises undefined energy cost savings, and lacks a capital cost estimate to “meet Paris”. Why does EAN not provide the spreadsheet that calculated these energy cost savings, as part of its glossy report? Why the reluctance to make a capital cost estimate by private entities and government entities?
EAN CO2 Reduction: EAN makes CO2 reduction estimates, based on primary energy, and on the artificial/political value of 34 g CO2/kWh for electricity, based on “paper” PPAs, as concocted by VT-DPS, to obtain very optimistic CO2 reductions per EV and per ASHP. See table 1
EAN Members Eager to “Meet Paris”: EAN eagerly urged the Vermont legislature to “meet Paris” a few years ago, because that would be good for their businesses, and would display proper virtue signaling. However, no entity, including EAN, made a capital cost estimate of what would be required to “meet Paris” at that time, or since.
EAN Members Eager for GWSA and “Fortress Vermont”: EAN is eagerly urging the Vermont Legislature to pass the Global Warming Solutions (Spending) Act. That act would turn aspirational goals of the CEP into mandated goals. The capital cost of GWSA would dwarf “meet Paris”. That would be sweet music for EAN members; heavily subsidized business and job security for decades at everyone else’s expense, despite the scam not yielding one iota of difference regarding climate.
NOTE: Ten senior state employees of VT-DPS are members of EAN, including Tierney, head of VT-DPS, and Perchlik, who is on loan to the legislature to help write the GWSA and $1.2 billion “Fortress Vermont” bills to ensure they contain all the bennies for EAN members. Perchlik manages the Clean Energy Development Fund that donates taxpayer money to renewable energy programs. No wonder VT-DPS resorts to artificial/political CO2 calculations regarding Vermont’s electrical sector, and EV and ASHP programs.
https://www.eanvt.org/about/people/network-members/
Table 1/Meet Paris |
Existing |
Addition |
Total |
CO2 reduction |
CO2 Reduction |
Year |
2019 |
2025 |
2025 |
2025 |
|
million Mt |
% |
||||
EVs/plug-in hybrids |
3,541 |
90,000 |
93,541 |
0.405 |
|
Fleet mileage increase |
0.187 |
||||
Solo driving increase |
0.172 |
||||
Total |
0.764 |
33.5 |
|||
ASHPs, space heat |
17,717 |
90,000 |
107,717 |
0.370 |
|
Adv. wood. heat |
21,421 |
25,000 |
46,421 |
0.258 |
|
Building retrofits |
27,186 |
90,000 |
117,186 |
0.160 |
|
ASHPs, DHW |
11,687 |
90,000 |
101,687 |
0.106 |
|
Total |
0.894 |
39.2 |
|||
Electricity; in-state |
MWh |
MWh |
MWh |
||
Wind |
161,198 |
250,000 |
411,198 |
||
Solar |
502,949 |
700,000 |
1,202,949 |
||
Hydro |
513,183 |
50,000 |
563,183 |
||
Total |
1,177,330 |
1,000,000 |
2,177,330 |
0.373 |
16.4 |
Miscellaneous |
0.250 |
11.0 |
|||
Total |
2.281 |
100.0 |
Table 2 shows the EAN measures to “meet Paris”, based on source energy, and real-world values for CO2/kWh, per ISO-NE, instead of the artificial/political values concocted by VT-DPS, and lifetime basis, in case of EVs. As a result, many more EVs and ASHPs would be required to achieve the EAN estimated CO2 reductions.
Table 2/ Costs |
EVs |
ASHPs |
Adv. Wood Heat |
Wind/Solar/Storage |
Hydro |
Total |
||
$billion |
$billion |
$billion |
$billion |
$billion |
$billion |
|||
EVs |
8.483 |
Deep retrofits |
2.700 |
Wind |
0.095 |
|||
Chargers |
0.318 |
ASHPs, space |
0.900 |
Solar |
0.570 |
|||
ASHP, DHW |
0.360 |
Grid |
0.100 |
|||||
Storage |
0.900 |
|||||||
8.801 |
3.960 |
0.250 |
1.665 |
0.860 |
15.536 |
|||
Annual |
3.107 |
NOTE:
Source energy, SE, is from mines, wells and forests, etc.
Primary energy, PE, is finished fuel/energy fed to power plants
Upstream = SE – PE
SE basis includes Upstream
PE basis excludes Upstream
Wall meter basis and wall socket basis = WM basis
Vehicle meter basis = VM basis
Metric ton = Mt = 2204.62 lb
Wall socket basis or wall meter basis = WM basis
Air source heat pump = ASHP
Electric vehicle = EV
New England = NE
Power purchase agreements = PPAs
New England grid operator = ISO-NE
ELECTRIC VEHICLES
The complete analysis of EVs is described in this article.
http://www.windtaskforce.org/profiles/blogs/vermont-co2-reduction-o...
Capital Cost
Cost for EVs; about 210,938 x $40000/small EV = $8.483 billion
Cost for private and public chargers; about 210,938 x $1500 = $0.318 billion
Total = 8.483 + 0.316 = $8.801 billion
AIR SOURCE HEAT PUMPS FOR SPACE HEAT
The complete analysis of ASHPs is described in this article
http://www.windtaskforce.org/profiles/blogs/vermont-co2-reduction-o...
Capital Cost:
"Deep" retrofits: 90,000 x $30,000/housing unit = $2.7 billion
ASHPs for space heat: 90,000 x $10,000/housing unit = $0.9 billion
ASHPs for DHW: 90,000 x $4000/system = $360 million
Total = 2.70 + 0.9 + 0.36 = $3.96 billion
WIND, SOLAR AND STORAGE
Moving to ASHPs and EVs would require increased generation
EAN does not mention any costs and subsidies for: 1) Expanding/augmenting the grid, 2) Increased wind and solar systems, which would require:
- Wind turbines costing about 250000/(8766 x 0.30) x $2.5 million/MW = $95 million
- Solar systems costing about 700000/(8766 x 0.14) x $3.5 million/MW = $570 million
- Expanding/augmenting of the grid costing about $100 million
- Storage costing about $900 million
Storage would mitigate/counteract:
- Daily disturbances of distribution grids, due to: 1) Solar outputs impacted by variable cloudiness, 2) Midday solar DUCK curves
- Daily disturbances of high voltage grids monitored by ISO-NE, due to larger solar systems
- Year-round, random disturbances of high voltage grids monitored by ISO-NE, due to wind systems
The storage systems would store unused solar during low-demand, mid-day hours, and discharge solar during high-demand, late-afternoon/early-evening hours
NOTE: Battery storage loss is about 20% (100 in, 80 out), high-voltage-to-high-voltage basis.
http://www.windtaskforce.org/profiles/blogs/vermont-is-going-to-hel...
Capital cost = 0.095 + 0.570 + 0.100 + 0.900 = $1.665 billion
IN-STATE HYDRO GENERATION
EAN recommends about 50,000 MWh/y of additional in-state, hydro generation, likely under a Standard Offer at 13 c/kWh; i.e., additional cost shifting to rate payers.
The NE wholesale rate has averaged about 5 c/kWh starting in 2009
Capital cost = 50000/(8766 x 0.40) x $6 million/MW = $86 million
APPENDIX 1
NE Electric Grid CO2
ISO-NE uses fuel/energy fed to power plants, PE, to calculate CO2/kWh.
ISO-NE does not include CO2 of upstream energy
Upstream is about 10.2% of PE CO2
https://www.iso-ne.com/static-assets/documents/2020/01/draft_2018_e...
Fed to grid becomes 299 x 1.102 = 329 g CO2/kWh, SE basis.
Fed to wall meter becomes 323 x 1.102 = 356 g CO2/kWh, SE basis.
For analysis purposes, 356 g/kWh should be used for electricity via any wall meter in NE.
Table A shows:
Source energy required for a quantity of electricity at wall sockets.
Values for Tesla Model 3 (0.3080 and 0.2449 kWh/mile) and Model S (0.4339 and 0.3329 kWh/mile), based on real-world conditions in California and upstate NY, for a year. Both are more efficient EVs compared to other EVs.
Value for a mix of LDVs was assumed at 0.350 kWh/mile.
Table A/NE grid for 2018 |
LDV mix |
Tesla |
Tesla |
Grid CO2 |
Grid CO2 |
Model S |
Model 3 |
PE |
SE |
||
kWh/mile |
kWh/mile |
kWh/mile |
g/kWh |
g/kWh |
|
Source energy |
1.2291 |
1.1713 |
0.8315 |
||
Upstream for extract, process, transport, 10.2% |
0.1138 |
0.1084 |
0.0770 |
||
Primary energy = Fed to power plants |
1.1153 |
1.0629 |
0.7545 |
||
Conversion loss, 55.5% |
0.6078 |
0.5793 |
0.4112 |
||
Gross generation |
0.5075 |
0.4836 |
0.3433 |
||
Plant self-use loss, 3.0% |
0.0152 |
0.0145 |
0.0103 |
||
Net generation = Fed to grid |
0.4922 |
0.4691 |
0.3330 |
299 |
329 |
T&D loss, 7.5% |
0.0369 |
0.0352 |
0.0250 |
||
Fed to wall meters = Fed to grid x 0.925 |
0.4553 |
0.4339 |
0.3080 |
323 |
356 |
Charging loss, 15% of WM |
0.0683 |
0.0651 |
0.0462 |
||
Loss due to self-use, NE road/climate |
0.0370 |
0.0359 |
0.0169 |
||
In batteries for a mix of LDVs, as DC |
0.3500 |
0.3329 |
0.2449 |
420 |
463 |
APPENDIX 2
Vermont Electricity Sector CO2
Based on Physics, per ISO-NE: Electricity, via any wall socket, would have the NE mix of electricity; CO2 of 323 g/kWh, WM basis, PE basis, in 2018. See table A
Electricity loaded by generators into the Vermont grid is about 6 billion kWh/y, aka “grid load“
User consumption is about 6 x (1 – 0.075) = 5.55 billion kWh/y
CO2 would be 5.55 billion kWh x 323 g/kWh x 1 lb/454 g x 1 Mt/2204.62 lb = 1,791,043 Mt/y, WM basis, PE basis, in 2018
Based on PPAs, per VT-DPS: CO2 of the “Vermont electricity mix”, based on PPAs, yields an artificial/political value of 190,000 Mt/y in 2018, or 190000/1791043 x 323 = 34 g/kWh, WM basis, PE basis, in 2018
See URL for GHG estimates for 2017 and 2018
https://dec.vermont.gov/sites/dec/files/aqc/climate-change/document...
APPENDIX 3
GMP and VT-DPS Reduce CO2
No CO2 is reduced by GMP signing paper PPAs with electricity generators, in-state or out-of-state.
It is unscientific for VT-DPS to calculate CO2 of the electricity sector, and CO2/kWh, based on paper PPAs, and for EAN to base CO2 reduction of ASHPs and EVs on VT-DPS numbers.
https://www.eanvt.org/wp-content/uploads/2020/03/EAN-report-2020-fi...
VT-DPS calculates CO2 of the electricity sector at 32 g/kWh for 2018, based on PPAs
ISO-NE calculates CO2 at 299 g/kWh for 2018, based on CO2 of fuel combustion. See URL page 18
https://dec.vermont.gov/sites/dec/files/aqc/climate-change/document...
https://www.iso-ne.com/static-assets/documents/2019/04/2017_emissio...
Table B/Grid CO2/Year |
1990 |
2000 |
2015 |
2016 |
2017, est. |
2018, est. |
VT-DPS, PE basis |
|
|
|
|
|
|
Electricity fed to VT grid, GWh |
6,000 |
6,000 |
6,000 |
6,000 |
6,000 |
6,000 |
Vermont electrical sector CO2, million Mt |
1.09 |
0.43 |
1 |
0.81 |
0.49 |
0.19 |
Total CO2, all sectors |
8.65 |
9.70 |
10.19 |
9.76 |
9.41 |
9.02 |
CO2, g CO2/kWh, Fed to grid basis |
72 |
167 |
135 |
82 |
32 |
|
CO2, g CO2/kWh, WM basis |
78 |
180 |
146 |
88 |
34 |
|
ISO-NE, PE basis |
||||||
NE generation fed to grid, GWh |
110,199 |
107,916 |
105,570 |
102,562 |
103,740 |
|
NE grid CO2, lb//MWh, Fed to grid basis |
726 |
747 |
710 |
682 |
658 |
|
NE grid CO2, g/kWh, Fed to grid basis |
330 |
339 |
322 |
310 |
299 |
|
NE grid CO2, g/kWh, WM basis |
357 |
366 |
348 |
335 |
323 |
APPENDIX 4
Vermont Electricity Prices
Table C last column, shows the c/kWh for electricity from wind. solar, hydro, etc., paid to owners of Standard Offer and Net-metered systems; those prices would be much higher without cost shifting and subsidies, paid by ratepayers and taxpayers. See URL
http://www.windtaskforce.org/profiles/blogs/cost-shifting-is-the-na...
Table C/VT In-state generation, fed to grid basis |
2000 |
2000 – 2018 |
2018 |
2018 |
Existing |
New added |
Total |
SO/NM |
|
Energy Source |
MWh |
MWh |
MWh |
c/kWh |
Hydro, VT-DPS Utility Facts 2013 |
491,878 |
21,305 |
513,183 |
13.0 |
Solar, behind and before the meter; per ISO-NE |
502,949 |
502,949 |
21.8 |
|
Ryegate, wood, per US-EIA |
166,902 |
166,902 |
10.0 |
|
McNeil, wood, per US-EIA |
244,755 |
244,755 |
10.0 |
|
Middlebury College, wood, per US-EIA |
2,298 |
2,298 |
? |
|
Farm methane; Standard Offer |
22,674 |
22,674 |
14.5 to 20.0 |
|
Landfill methane |
52,931 |
52,931 |
9.0 |
|
Wind |
161,198 |
161,198 |
11.6 to 25.8 |
|
Total |
903,535 |
763,355 |
1,666,890 |
|
VT total fed to grid, MWh |
6,000,000 |
6,000,000 |
6,000,000 |
|
VT in-state, % |
15.1 |
12.7 |
27.8 |
|
Vermont Yankee, nuclear, closed in 2015 |
4,733,640 |
4,733,640 |
||
Out-of-state purchases, incl. HQ, MWh |
4,333,110 |
|||
HQ, MWh; per Power Purchase Agreement |
1,300,000 |
5.549 |
||
ISO-NE annual average price since 2009 |
5.000 |
APPENDIX 5
GMP Cost of Electricity in 2016
Table D shows the prices GMP pays for electricity.
Standard Offer and Net-metering prices are off-the-charts expensive.
EAN members want more SO and Net-metered,
http://www.windtaskforce.org/profiles/blogs/green-mountain-power-co...
In 2016, the PUC began competitive bidding of SO solar systems.
Some recent SO solar bids were as low as 11 c/kWh.
More SO systems would slowly reduce SO solar below 21.793 c/kWh in future years. See Appendix.
http://www.windtaskforce.org/profiles/blogs/cost-shifting-is-the-na...
Table D/GMP costs |
1 |
2 |
3 |
4 |
5 |
GMP purchases, 2016 |
MWh |
% of purchases |
Cost, $ |
c/kWh |
% of Cost |
HQUS (Hydro-Quebec) |
919312 |
22.13 |
51013678 |
5.549 |
20.34 |
Standard Offer |
78920 |
1.90 |
17199202 |
21.793 |
6.86 |
Net-metered |
71970 |
1.73 |
15699137 |
21.813 |
6.26 |
Ryegate (wood) |
126707 |
3.05 |
12710175 |
10.031 |
5.07 |
ISO wholesale |
575553 |
13.85 |
18645214 |
3.240 |
7.43 |
Misc. sources |
1772462 |
42.66 |
115267406 |
6.503 |
45.96 |
Other sources |
2382075 |
57.34 |
135516232 |
5.689 |
54.04 |
Total GMP purchases |
4154537 |
100.00 |
250783638 |
6.036 |
100.00 |
ISO midday wholesale |
6.000 |
APPENDIX 6
Gas Guzzler Fees to Reduce CO2
Vermont should have an energy efficiency standard for light duty vehicles.
Annual fees would be paid at time of annual registration.
Inefficient vehicles would rapidly disappear.
CO2 would be rapidly reduced.
The collected funds could be used for filling potholes.
The wasteful Comprehensive Transportation Initiative, TCI, would not be needed.
http://www.windtaskforce.org/profiles/blogs/electric-vehicles-and-m...
Table E/EPA combined, mpg |
Fee, $/y |
40 |
0 |
39 |
10 |
38 |
20 |
37 |
30 |
36 |
40 |
35 |
50 |
34 |
60 |
Etc. |
APPENDIX 7
GMP Purchased Electricity Mix
GMP electricity mix based on PPAs, i.e., paper contracts.
GMP increased purchases of large hydro and nuclear, which have very low CO2/kWh.
GMP decreased purchases on the wholesale market, which had 299 g CO2/kWh in 2018, fed to grid basis, PE basis.
GMP’s paper PPAs for hydro and nuclear did not physically reduce any CO2 anywhere.
GMP is required to have such PPAs to satisfy state-RES mandates.
GMP did not need to spend any money to make any changes in its operations to reduce CO2
Table F/GMP Electricity Mix |
2017 |
2018 |
2019 |
% |
% |
% |
|
Large hydro |
23.7 |
49.4 |
|
Existing VT hydro |
6.3 |
6.3 |
|
Total hydro |
30.0 |
55.7 |
60.6 |
Wholesale market purchases |
30.4 |
28.2 |
9.8 |
Nuclear |
14.7 |
14.7 |
27.9 |
Oil and natural gas |
0.5 |
0.4 |
|
Methane |
0.7 |
||
Hydro |
5.5 |
||
Solar |
5.2 |
0.9 |
1.7 |
Wind |
8.0 |
||
Wood |
5.0 |
||
Total RE |
24.4 |
0.9 |
1.7 |
APPENDIX 8
More Wind, Solar and Storage Harmful for Vermont
GMP would need to replace the nuclear electricity, as it cannot rely on Seabrook Nuclear to be generating far into the future.
If the replacement were in-state RE (primarily wind, solar and storage), there would be major adverse environmental impacts on pristine ridge lines and open spaces in Vermont, plus the cost would be prohibitively expensive, which would adversely affect the Vermont economy. See URLs.
http://www.windtaskforce.org/profiles/blogs/cost-shifting-is-the-na...
http://www.windtaskforce.org/profiles/blogs/the-more-wind-and-solar...
http://www.windtaskforce.org/profiles/blogs/excessive-subsidies-for...
APPENDIX 9
Electricity Moves as Electro-Magnetic Waves at Nearly the Speed of Light
Electricity Mix Based on Power Purchase Agreements
There are non-technical people talking about the “Vermont electricity mix” or the “New Hampshire electricity mix”. That mix exists only on paper, because it is based on power purchase agreements, PPAs, between utilities and owners of electricity generators.
If a utility claims it is 100% renewable, it has PPAs with owners of renewable generators, i.e. wind, solar, biomass, hydro, etc. That mix has nothing to do with physical reality.
If a utility did not have PPAs and drew electricity from the grid, it would be stealing, just as a person would be by bypassing the utility electric meter.
Entities, such as VT-DPS, should not use PPAs to calculate the CO2 of the VT electricity sector and CO2/kWh
Electricity Mix Based on Physics
Once electricity is fed into the NE electric grid by any generator, it travels:
- On un-insulated wires, as electromagnetic waves at somewhat less than the speed of light, i.e., from northern Maine to southern Florida, about 1800 miles in 0.01 of a second
- On insulated wires, the speed decreases to as low as 2/3 the speed of light, depending on the application.
If those speeds were not that high, the NE electric grid would not work, and modern electronics would not work.
The electrons vibrate at 60 cycles/second, 60 Hz, and travel at less than 0.1 inch/second; the reason it takes so long to charge a battery.
It is unfortunate most high school teachers told students the electrons were traveling.
Teachers likely never told them about EM waves
http://www.djtelectricaltraining.co.uk/downloads/50Hz-Frequency.pdf
http://www.windtaskforce.org/profiles/blogs/popular-misconceptions-...
Entities, such as VT-DPS, should use the ISO-NE estimated CO2/kWh, at wall meters, to calculate CO2 of the VT electricity sector and CO2/kWh
Living Off the Grid
- If you live off the grid, have your own PV system, batteries, and generator for shortages and emergencies, then you use your own electricity mix.
- If you draw electricity from a wall socket, you draw the NE mix
APPENDIX 10
Highly Sealed, Highly Insulated House
In 2008, Transformations Inc., Townsend, MA, was chosen among six builders to participate in the state’s investor-owned utilities Zero Energy Challenge, a competition to encourage builders to plan and develop a home with a HERS Index below 35 before December 2009.
Carter Scott, President of Transformations, Inc. brought together a team of design and energy experts to not only meet the challenge, but to figure out how to get all the way to zero, while still building an affordable, new house. The team designed a three-bedroom 1,232-sq ft house, called the “Needham," which has a “- 4” HERS rating, i.e., the home is producing more energy than it is using. Sales price: $195,200 in 2009
https://www.buildingscience.com/sites/default/files/2011-03-08%20NE...
Major Design Features:
Roof (R75): 5 inches of high-density polyurethane foam, HDF, and 13 inches of high-density cellulose all along the slope of the second-floor roof rafters; 2 x 12s and a 2 x 4s held off by 3 inches for a thermal break separation
Walls (R49): 2 x 4 outside wall; added a second 2 x 4 wall for a total depth of 12 inches; filled 3 inches with HDF and 9 inches with cellulose
Basement Ceiling: 3 inches of HDF and a layer of R-30 fiberglass batts
Windows: Paradigm triple-pane model with Low-E and krypton gas
Heating/Cooling: Two Mitsubishi Mr. Slim mini-split, ductless, ASHPs
Ventilation: Lifebreath 155 ECM Energy Recovery Ventilator
Leakage: About 175 cfm at 50 pascal, per blower door test (or 284 cfm for a 2000 sq ft house. See table 8)
Solar: Evergreen Solar’s 30 Spruce Line 190-watt PV panels to create a 6.4-kW system;
Hot Water: SunDrum Solar’s DHW heating system
Heat Loss: About 10,500 Btu/h, at 70F indoor, 6F outdoor (or 2000/1232 x 75 delta T/64 delta T x 10500 = 19,975 Btu/h for a 2000 sq ft house, at 65F indoor and -10F outdoor, in Vermont)
APPENDIX 11
CO2 of Gasoline and E10
E10 fuel (90% gasoline/10% ethanol) has a source energy, which is reduced due to exploration, extraction, processing and transport, to become the primary energy fed to E10 vehicles. See URL.
http://www.patagoniaalliance.org/wp-content/uploads/2014/08/How-muc...
Burning E10 (90% gasoline/10% Ethanol) = 0.9 x 19.569 + 0.1 x 12.720 = 18.884 lb/gal
Upstream = 0.9 x 4.892 + 0.1 x 13.556 = 5.759 lb/gal
Total = 24.643 lb/gal, if CO2 of ethanol fraction in gasoline (aka, gasohol, or E10) is counted.
Total = 24.643 - 1.272 = 23.371 lb/gal, if not counted.
Table G/Fuel CO2 |
Combustion |
Upstream |
Total |
lb CO2/gal |
lb CO2/gal |
lb CO2/gal |
|
Burning pure gasoline |
19.569 |
||
Upstream = 25% of combustion, per EPA |
4.892 |
||
Total |
|
24.461 |
|
Burning pure ethanol |
12.720 |
||
Cropping, processing, blending |
13.556 |
||
Total |
26.276 |
||
Burning E10 (90/10) |
18.884 |
||
Upstream |
5.759 |
||
Total, if ethanol CO2 is counted |
24.643 |
||
Total, if ethanol CO2 is not counted |
17.612 |
5.759 |
23.371 |
. |
|||
Burning pure diesel |
22.456 |
||
Upstream = 27% of combustion, per EPA |
6.063 |
||
Total |
28.519 |
||
Burning pure biodiesel, B100, soy oil |
20.130 |
||
Upstream = 43% of combustion |
8.656 |
||
Total, if biodiesel CO2 is counted |
28.786 |
||
Total, if biodiesel CO2 is not counted |
8.656 |
||
Burning B20 (80/20) |
21.991 |
||
Upstream |
6.582 |
||
Total, if biodiesel CO2 is counted |
28.572 |
||
Total, if biodiesel CO2 is not counted |
17.965 |
6.582 |
24.546 |
APPENDIX 12
The Prius Prime, plug-in hybrid, 8.8 kWh battery, partial AWD, travels about 25 miles on the battery, after which it functions as any other Prius.
Owners, with short commutes, need not buy any gasoline for months.
They only need to plug-in every day.
Per EPA, (33.7 kWh/gal-eq)/(133 mpg-eq) = 0.259 kWh/mile, WM basis; includes charging losses
Adjusted to 0.259 x 1.055, loss factor = 0.267 mile/kWh, WM basis; includes 1) charging loss, 2) self-use losses due to heating, cooling, electronics, etc., and 3) losses due to NE road/climate conditions, 4) losses due to idle time, such as parked at an airport. (Items 2, 3 and 4 are not measured by EPA)
On average, electricity use would be 25 x 0.267 = 6.675 kWh to travel 25 miles each day, WM basis.
Battery rated capacity is 8.8 kWh, DC, i.e., about 65% is utilized, because the battery control system renders the top and bottom 15% as off limits to extend battery life. The middle portion has the most efficient charging and discharging.
Summer weather increases the 25-mile range and winter weather reduces it.
https://web.mit.edu/evt/summary_battery_specifications.pdf
https://batteryuniversity.com/learn/article/bu_1003a_battery_aging_...
Daily Commuting Cost
Commuting cost of Prime would be 6.675 x $0.19/kWh = $1.27/day.
Commuting cost of a 30-mpg gasoline vehicle would be 25/30 x $2.50/gal = $2.08/day
Lifetime CO2
Lifetime CO2 of Prime would be about 26.49 Mt/105600 miles
Lifetime CO2 of 30-mpg vehicle would be about 43.02 Mt/105600 miles
https://en.wikipedia.org/wiki/Toyota_Prius_Plug-in_Hybrid
https://calevip.org/electric-vehicle-charging-101
2020 Prius |
Standard |
Eco L |
Prime, AWD |
Plug-in |
no |
no |
yes |
Battery packs |
2 |
2 |
5 |
Pack arrangement |
parallel |
parallel |
series |
Cells/pack |
28 |
28 |
19 |
Cells |
56 |
56 |
95 |
Cell energy, Ah |
3.6 |
3.6 |
25 |
Battery energy, Ah = cells x 3.6 |
201.6 |
201.6 |
2375 |
Cell voltage, V |
3.7 |
3.7 |
3.7 |
Battery voltage, V = 28 x 3.7 |
103.6 |
103.6 |
|
Battery voltage, V = 95 x 3.7 |
351.5 |
||
Battery capacity, kWh = V x Ah/1000 |
0.746 |
0.746 |
8.788 |
City |
54 |
58 |
52 |
Highway |
50 |
53 |
48 |
Combined |
52 |
56 |
50 |
U.S. Sen Angus King
Maine as Third World Country:
CMP Transmission Rate Skyrockets 19.6% Due to Wind Power
Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.
Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT
******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********
(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/
Not yet a member?
Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?
We have the facts on our side. We have the truth on our side. All we need now is YOU.
“First they ignore you, then they laugh at you, then they fight you, then you win.”
-- Mahatma Gandhi
"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi
Task Force membership is free. Please sign up today!
Hannah Pingree - Director of Maine's Office of Innovation and the Future
"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."
https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/
© 2024 Created by Webmaster. Powered by
You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!
Join Citizens' Task Force on Wind Power - Maine