|
Comment
Willem,
Thanks for the numbers.
Dan,
In the table, you see the formula for hydro plants P = ndQgH
PUMPED STORAGE HYDRO IN NEW ENGLAND
https://www.windtaskforce.org/profiles/blogs/pumped-storage-hydro-i...
New England PSH Plants
NE has two major PSH plants. The Northfield plant is the major subject of this article.
Bear Swamp, rated storage/cycle 600 MW x 6 h = 3000 MWh
Northfield rated storage/cycle 1168 MW x 8 h = 9344 MWh
The actual values are less. See table 1B.
Production over about 8 hours is 12344 MWh, if both cycle capacities were fully available at the same time.
NOTE: Average NE consumption during a similar period on a high-demand day is 22000 MW, average x 7 h = 154,000 MWh
BEAR SWAMP HYDROELECTRIC POWER STATION
The plant is located in Deerfield River in Rowe and Florida, MA. It is used for:
- Time shifting, i.e., using night-time electricity (low wholesale price) to top off the upper reservoir and producing daytime electricity (high wholesale price).
- Ramping, i.e., provide filling-in electricity in case of an unscheduled outage of a plant on the NE grid, or to provide electricity during peak loads on the NE grid, usually late afternoon/early evening.
- The plant could be used for balancing variable wind and solar electricity, but that would require major modifications, because of the limited water quantity in the upper reservoir. Once that quantity is used up, the plant would have to stop balancing mode, and start pumping mode to top-off the reservoir. The same is true for the Northfield plant.
http://www.berkshireeagle.com/stories/bear-swamp-hydroelectric-gene...
https://www.energystorageexchange.org/projects/228
Table 1/Rated output |
600 MW |
Elevation drop |
700 ft |
Ramp up 0% to 100% |
3 minutes |
Duration |
6 h |
Production/cycle |
3000 MWh |
Pumping electricity |
1.38 x 3000 MWh |
Cycle electrical efficiency |
1/1.38 = 72.5%, below average |
Maximum annual production |
365 x 3000 = 1,095,000 MWh |
Actual average annual production |
450,000 MWh |
Plant capacity factor |
41% |
NORTHFIELD MOUNTAIN PUMPED STORAGE HYDRO PLANT
First-Light Power Resources, former owner of the Northfield Mountain Pumped Storage Plant, sold the plant to one of Canada’s largest pension investment managers, the Public Sector Pension Investment Board (PSP Investments), which is retaining properties from First-Light Power Resource, primarily located on the Connecticut River in Massachusetts and Connecticut, for $1.2 billion.
http://www.gazettenet.com/News/Local/FirstLight-Power-Resources-to-...
NOTE: The Canadian entity is collecting money from Vermonters to pay Canadian pensioners. The US debtor status was $8.3 trillion at end 2016, on which foreign entities collected at least $415 billion (5%) to pay pensioners, etc.
http://www.windtaskforce.org/profiles/blogs/cop21-flawed-trade-agre...
The Northfield plant, generating capacity 1168 MW after the recent replacement of the hydro turbine-generators, was built in 1976 as a companion to the former, base-loaded, Vermont Yankee nuclear power plant in Vernon, Vermont, which used to produce about 600 x 8766 x 0.9 = 4,733,640 MWh/y, of steady, near-CO2-free, electricity, at about 5 c/kWh. The VY production was almost as much as the 6,100,000 MWh/y supplied to Vermont utilities and was much more than generated by the Hoover Dam (4,200,000 MWh/y). See table 8.
PSH Plant Operation:
Arbitrage Mode: At present, the main use of the PSH plant is in arbitrage mode, i.e., generate electricity when daytime wholesale prices are high and use electricity to pump when nighttime wholesale prices are low. Even though the pumping electricity exceeds the generated electricity by about 20%, the difference in wholesale prices makes that mode a profitable operation. See table 1A.
Table 1A/Summary |
NE Wholesale |
||
MWh/y |
$/MWh |
$million/y |
|
Generating |
3404925 |
60 |
204.30 |
Pumping |
4271600 |
40 |
170.86 |
Efficiency |
0.797 |
||
Capacity factor |
0.333 |
|
|
Net Revenue from arbitrage |
33.43 |
The plant has an upper reservoir and a lower reservoir (Connecticut River) and 4 reversible, hydro turbine-generators, for a total rating of 1168 MW. The units can be electrically powered to pump water from the river into the upper reservoir. See table 1B for plant design parameters.
http://www.northfieldrelicensing.com/Pages/Northfield.aspx
http://www.northfieldrelicensing.com/Pages/features.aspx
Emergency Power Mode: The grid operator, ISO-NE, to quickly obtain temporary power in case of an unscheduled outage of a major plant, often calls the Northfield plant to provide filling-in electricity for several hours until other generators can be brought on line.
The plant can increase its output from 0% to rated output, MW, in less than 10 minutes, and maintain that output for up to 8 hours (longer at less than rated output) by using the maximum allowed water quantity from the upper reservoir.
ISO-NE pays a high fee per MW and per MWh for that emergency service, in accordance with contract provisions.
Table 1B/Name |
Northfield |
||
Location |
Massachusetts |
||
Upper reservoir |
Manmade |
||
Lower reservoir |
Connecticut River |
||
Commissioned |
1972 |
||
Nameplate rating, MW |
1200 |
Average |
|
Operating elevation range, ft |
1000.5 - 938 |
988.75 |
|
Elevation differential, ft |
62.5 |
||
Head range, ft |
753 - 824.5 |
788.75 |
|
Head differential, ft |
71.5 |
||
Reservoir capacity, gal |
5,600,000,000 |
||
m^3/gal |
0.003785 |
||
Reservoir capacity, m^3 |
21196000 |
||
Useable storage, acre-ft |
12318 |
||
m^2/acre |
4047 |
||
m/ft |
0.3048 |
||
Usable storage, m^3 |
15194568 |
||
Usable storage fraction |
0.717 |
Conv. Factors |
Q, Mass flow |
Turbine-Generators, reversible to pump |
4 |
m^3/ft^3 |
m^3/s |
Tunnel design flow, ft^3/s |
27000 |
0.02832 |
765 |
Flow, generating, ft^3/s |
20000 |
0.02832 |
566 |
Flow, pumping, ft^3/s |
15200 |
0.02832 |
430 |
T-G rating, new, MW |
1168 |
||
T-G rating, old, MW |
1080 |
||
Start-up, 0 to 1168 MW, min |
10 |
||
Electricity supply duration, h |
8 |
Electricity Generated Per Cycle: The plant generates about 9329 MWh per 8-hour cycle, based on the data in table 2. Some of the data were assumed, as they could not be found.
Table 2/Electricity supply/cycle |
Generation |
|
Head at reservoir surface, ft |
838.75 |
|
Head loss*, ft |
25.00 |
|
Head at turbine inlet, ft |
813.75 |
|
Head at turbine inlet, m |
H |
248.03 |
Gravity acceleration, m/s^2 |
g |
9.80664 |
Density, kg/m^3 |
d |
1000 |
Mass flow, m^3/s |
Q |
566 |
Efficiency, turbine |
n |
0.920 |
Water power to generator, joules/s |
P = ndQgH |
1267468155 |
s/h |
3600 |
|
Water power to generator, joules/h |
4.56289E+12 |
|
kWh/million J |
0.2777777 |
|
kWh/h = kW |
1267468 |
|
Water power to generator, MW |
1267 |
|
Efficiency, generator to grid |
n |
0.920 |
Electrical power to grid, MW |
1166 |
|
Duration, h |
8 |
|
Electricity to grid, MWh/8 h |
9329 |
Electricity Used For Pumping Per Cycle: The plant uses about 11703 MWh per 10.53-hour cycle, based on the data in table 3. Some of the data were assumed, as they could not be found.
Table 3/Electricity used/cycle |
Pumping |
|
Head at reservoir surface, ft |
838.75 |
|
Head adder*, ft |
25.00 |
|
Head at turbine inlet, ft |
863.75 |
|
Head at turbine inlet, m |
H |
263.27 |
Gravity acceleration, m/s^2 |
g |
9.80664 |
Density, kg/m^3 |
d |
1000 |
Mass flow, m^3/s |
Q |
430 |
Efficiency, turbine |
n |
0.920 |
Water power to turbine, joules/s |
P = ndQgH |
1022463251 |
s/h |
3600 |
|
joules/h |
3.68087E+12 |
|
kWh/million J |
0.2777777 |
|
kWh/h = kW |
1022463 |
|
Water power to turbine, MW |
1022 |
|
Efficiency, generator to grid |
n |
0.920 |
Electrical power from grid, MW |
1111 |
|
Duration, 566/430 x 8 h |
10.53 |
|
Electricity consumed, MWh/10.53 h |
11703 |
|
Electricity loss per cycle, MWh |
2374 |
|
Cycles/y |
365 |
|
Electricity loss/y^, MWh |
866675 |
* Head adder = upstream of turbine + downstream of turbine
^ Electricity loss is similar to historic. See table 5.
Estimated Annual Net Revenue: The plant has revenues of electricity sales of about $204.30 million/y, and costs of electricity purchases of about $170.86 million/y, for net revenues of about $33.43 million/y. Other revenue is from ISO-NE-requested emergency services. See table 4.
Table 4/Electricity Trading Net Revenue |
|||
h/y |
8766 |
||
s/h |
3600 |
||
Flow, generating, 8 h, m^3 |
16312320 |
||
Fraction of useable storage used |
1.074 |
107 |
% |
Plant capacity factor, CF |
0.333 |
||
Efficiency, Generation/Pumping |
0.797 |
||
Electricity production, MWh/8 h |
9329 |
8500 |
|
Cycles/y |
365 |
||
Electricity production, MWh/y |
3404925 |
||
Daytime average wholesale, c/kWh |
6.00 |
||
Revenue, $/y |
204295530 |
||
Revenue, $million/y |
204.30 |
||
Electricity, pumping, MWh/10.53 h |
11703 |
||
Cycles/d |
365 |
||
Electricity consumption, MWh/y |
4271600 |
||
Nighttime average wholesale, c/kWh |
4.00 |
||
Pumping cost, $/y |
170864003 |
||
Pumping cost, million$/y |
170.86 |
||
Net Revenue*, $million/y |
33.43 |
* Actual net revenue is less due to fewer cycles per year and partial cycles.
Historic Annual Net Generation: Below are the historic values for annual net generation, GWh/y. Those values date from before the replacement of the original turbine generators with new units of slightly greater capacity, MW. See table 5.
http://globalenergyobservatory.org/geoid/1239
Table 5 |
Net generation, GWh |
2000 |
-614.760 |
2001 |
-552.245 |
2002 |
-512.425 |
2003 |
-392.991 |
2004 |
-386.698 |
2005 |
-329.032 |
2006 |
-371.347 |
2007 |
-579.880 |
2008 |
|
2009 |
Willem,
I would rather see a billion dollars go into building a hydro pumped storage facility in Maine than a 300-megawatt wind facility. And I would much love to own it.
Fossil fuel prices are too susceptible to politics. Water is natural, plentiful and can produce 1200 megawatts at a turbine feed rate of 27,000 gallons per second.
Alicia and Dan,
CO2, at 1.75 W/m2 driving force, is a pigmy, compared to the 120-plus W/m2 driving force of clouds and water vapor.
If CO2 were doubled, which would use up all the fossil fuels, and would cause major forest growth, there would be only a very minor increase in temperature, because of absorption frequency limitations, according to Modern Physics.
I understand your rah rah for hydro, but reducing pigmy CO2 to save the planet is bull manure to Physicists
U.S. Sen Angus King
Maine as Third World Country:
CMP Transmission Rate Skyrockets 19.6% Due to Wind Power
Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.
Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT
******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********
(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/
Not yet a member?
Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?
We have the facts on our side. We have the truth on our side. All we need now is YOU.
“First they ignore you, then they laugh at you, then they fight you, then you win.”
-- Mahatma Gandhi
"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi
Task Force membership is free. Please sign up today!
Hannah Pingree - Director of Maine's Office of Innovation and the Future
"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."
https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/
© 2025 Created by Webmaster.
Powered by
You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!
Join Citizens' Task Force on Wind Power - Maine