HOW CONNECTICUT NIMBYS SATISFY THEIR GREEN CONSCIENCE ? by blasting Me, Vt and NH mountains!!!

 
FROM OUR  FRIENDS  AT  WINDACTION.ORG WE  HAVE  LEARNED THAT: RECENT CHANGES TO  CONNECTICUT RPS  NOW REQUIRE THAT 4 % DEMAND BE  MET WITH LONG TERM POWER  PURCHASE  AGREEMENTS ( PPA) FOR CLASS 1 RENEWABLES (WIND  AND SOLAR )   
1) The CT RFP is a very public process since the State is the entity that's selecting and negotiating the contracts. This is in contrast to a near identical RFP issued in MA that is being negotiated by the utilities behind closed doors.
 
2) The link below lists all of the projects that sent notices of intent to bid to Connecticut. This full list likely represents the TOTALITY of all renewable energy projects that have a hint of being built in New England.
 
 
3) Projects that are not already operational or shovel ready have substantial obstacles before them including negative public responses and transmission constraints.
 
4). According to the CT RFP, Connecticut is seeking to procure up to 4% of the State's load, which is approximately 174 MW of installed capacity, or 525 MW of wind-equivalent installed capacity. CT must be assuming an 80% capacity factor for reliable Class I resources and about 26% capacity factor for wind
 
 
 
* Due Date for Proposal Submissions - August 5, 2013 * Selection of Applicants - August 20, 2013 * EDCs Negotiate and Execute Contacts through - September 3, 2013 * Submit Contracts for PURA Approval - September 9, 2013 * PURA Approval - October 9, 2013

(from windaction.org)

 
WHAT DOES   THIS  MEAN  FOR MAINE ?: IF YOU CLICK ON  THE LINK PROVIDED  IN  THE ABOVE MATERIAL , YOU WILL SEE  THAT PATRIOT RENEWABLE , FIRST WIND AND RECORD HILL ARE  ACTIVELY REQUESTING PPA s TO Connecticut , THEY ARE  AWARE THAT THEY NEED TO HAVE THOSE  AGREEMENTS BEFORE THE END  OF 2013 SO  AS  TO  BE  ELIGIBLE FOR PTC.
FIRST WIND ESPECIALLY IN THEIR  APPLICATION INSISTS TO DEEEP  Ct TO GRANT THEM THOSE PPAs BECAUSE  Of  THE LOOMING THREAT TO THE PTC, PLEASE  READ  THEIR  FOLLOWING  COMMENT IN  THEIR  APPLICATION :

 

"First Wind believes that the opportunity to qualify wind energy projects utilizing available federal tax credits

could close this year, and may not re-open in the near or medium term, if ever. We therefore urge DEEP to

consider procuring all 396.5 MW of First Wind’s proposed PPAs, in order to capture the full benefits of the

Production/Investment Tax Credits (“PTC/ITC”) for Connecticut energy consumers.

Capturing the full benefits of the PTC/ITC requires that a project developer be positioned to take on the

development risk and capital requirements necessary to quality by year’s end. We believe the selection of

proposals by Sponsors unable to meet those risks or requirements would deprive Connecticut consumers of an

opportunity to secure cheap renewable power. First Wind is prepared to qualify each project submitted for

review. In fact, First Wind is prepared to provide additional financial security during the remaining project

development period to demonstrate both our financial capacity and commitment to qualify our projects for the

PTC/ITC." ( END  OF TEXT )

SO  AS  YOU SEE  THE  FIGHT AGAINST THE EXTENSION OF THE PTC  WILL INTENSIFY SOON AND WE WILL  MAKE APPEALS TO THE CTFWP MEMBERS SOON . 

 

IN  THE MEANTIME YOU CAN EXPRESS YOUR OUTRAGE TO

   THE PUBLIC ADVOCATE  : tim.schneider@maine.gov

    THE ENERGY  DIRECTOR : patrick.c.woodcock@maine.gov

    THE DEP COMMISSIONER  patricia.aho@maine.gov

 

 

PLEASE TELL THEM  . THAT  SACRIFICING THE REMOTE MOUNTAINS OF MAINE TO SATISFY THE GREEN POLICIES OF CONNECTICUT IS AN INSULT TO MAINERS

                              , THAT SOME  OF  THE PROJECTs PROPOSED BY PATRIOT RENEWABLES AND FIRST WIND  HAVE NOT EVEN BEEN  PRESENTED TO MAINE RESIDENTS

                               .. THAT THE FALLACIOUS  ARGUMENTS THAT MAINE  WIND PROJECTS WILL POWER LOCAL HOMES IS EXPOSED IN THIS DESPICABLE SCHEME.

Monique Aniel       

    

 
    
 
 
 
.
 
 
-----

Views: 207

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Martha thacker on August 9, 2013 at 7:24pm

When Blumenthal was gov. of Conn., he would not allow transmission lines to run through Conn. for "a few wind farms in upper state ME." He took ISO New England to court for charging too much to rate payers..over a million for power not delivered. The case went all the way to the Supreme Court and of course they sided with ISO. I called the office and one of the lawyers said the power was supposedly from NY..which has a wind farm, Cohocton , built by First Wind , which also has no way to transmit. The locals found out that the grid was at capacity and made that fact public on their website..cohoctonwindwatch.

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service