Wind Power Bandwagon Hits Bumps in the Road
WRITTEN BY NAOMI SCHALIT SENIOR REPORTER MAINE CENTER FOR PUBLIC INTEREST REPORTING
FRIDAY, AUGUST 06, 2010 AT 8:38 AM
AUGUSTA — The Wind Energy Act of 2008, which gave developers a fast track to putting up wind turbines in some of the state’s treasured high ground, was a special interest bill justified at the time in the name of jobs, energy independence and climate change.

“There is tremendous potential for Maine to become a leader in clean, renewable energy, including wind energy,” said Governor John Baldacci, who appointed the task force whose report led to the bill. “This kind of investment would create jobs and help to expand Maine’s economy.”

But now, two years after the law was championed by Baldacci, some members of the task force are questioning whether the goals they set for wind power can or even should be achieved.

Critics and even some one-time supporters say the proponents of the law were swept up in a tidal wave of enthusiasm for a technology that turns out to require significant sacrifice from the state, but has little to offer Maine in return.

That issue was faced head-on recently when the state Land Use Regulation Commission (LURC) was asked to rule on a TransCanada wind project in western Maine.

LURC Commissioner Ed Laverty summed up the problem with the bill: “Our job is to protect the resources in these high mountain areas … given the fragile nature, and the rich nature of the resources in these areas, we have to ask ourselves, to what extent can these benefits really outweigh the long-term costs?

Chris O’Neil, a former state legislator who now works as a public affairs consultant to groups opposing wind power development in Maine’s mountains, said that the Governor’s vision was fundamentally flawed.

“To fulfill the charge of making Maine a leader in wind power development and to simultaneously protect Maine’s quality of place is impossible,” O’Neil said.

This is part one of a three-part series on the 2008 law to fast-track wind turbine development.

Views: 62

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/