One of the problems of installing wind turbines in remote locations such as Maine is having a highway for energy shipment. First Wind, Bangor Hydro and National Grid have an answer :

 

 

 

 

WALTHAM, Mass., Jul 11, 2011 (BUSINESS WIRE) -- National Grid and Emera Inc. subsidiary, Bangor Hydro Electric Company, have taken a major step in advancing the Northeast Energy Link (NEL) transmission project by filing today with the Federal Energy Regulatory Commission for approval of its funding approach for the proposed project. Today's filing seeks confirmation that the companies' sale of transmission capacity is consistent with FERC's Open Access policies. Under the proposed participant funding approach, renewable energy generators would pay to use NEL's transmission capacity.

The NEL, as currently proposed, is a new underground transmission line that would stretch approximately 220 miles from northern Maine to northeastern Massachusetts by 2016.

The new line will provide a critical connection to the vast renewable and carbon-neutral energy resources of northern and eastern Maine and eastern Canada.

"This proposed project is yet another example of National Grid's commitment to and leadership in expanding the region's portfolio of clean energy resources," said Tom King, president, National Grid USA. "Having access to the significant renewable and carbon-neutral energy resources in Maine and eastern Canada makes this a huge win for New England energy consumers, who will enjoy the benefits of cost-competitive, clean and reliable energy for years to come."

"The Northeast Energy Link will serve as a pathway for the region's energy independence. Projects like this one make it possible to develop the region's renewable energy resources and reduce its dependence on carbon-based fuels for electricity generation," said Gerry Chasse, President and Chief Operating Officer of Bangor Hydro Electric Company. "We are pleased to be working with a number of private companies and state governments to improve the region's energy independence by bringing clean, indigenous energy to market at a cost that will be competitive, predictable, and stable for the long term."

NEL, which is in the preliminary stages of development, is expected to have a capacity of 1,100 megawatts. It is being proposed as an underground, high voltage direct-current line. The companies will evaluate a number of potential routes, including one that would utilize existing corridors in eastern Maine, New Hampshire and Massachusetts. By utilizing such existing rights-of-way to the greatest extent possible, National Grid and Bangor Hydro are seeking to mitigate potential effects on the environment and the communities where the line would be located. It is important to emphasize that the project route has not yet been chosen.

Under the proposed project, renewable generators would pay to use NEL's transmission capacity. First Wind Holdings, LLC, based in Boston, Mass., plans to build wind farms in northern and eastern Maine and would purchase the majority of the proposed transmission line's capacity. Remaining capacity, if any, would be sold to other generators.

While the project is in the preliminary stages, significant research has been undertaken related to energy consumer benefits, siting, and the impact the new line would have on the New England power system. Delivered renewable supply over NEL was found to be cost-competitive with other means of meeting state Renewable Portfolio Standards. Further research, site planning and permitting preparation are planned for this year, along with the negotiation of a Transmission Service Agreement with First Wind.

Siting and permitting work for NEL are expected to continue over the next two to three years, followed by an estimated three-year construction period. As part of this work, National Grid and Bangor Hydro plan to reach out to communities where the proposed new line might be located to begin discussions about possible routes and other considerations. The companies anticipate the project will be completed at the end of 2016.

Additional information about NEL can be found at http://www.northeastenergylink.com.

National Grid is an international energy delivery company. In the U.S., National Grid delivers electricity to approximately 3.3 million customers in Massachusetts, New Hampshire, New York and Rhode Island, and manages the electricity network on Long Island under an agreement with the Long Island Power Authority (LIPA). It is the largest distributor of natural gas in the northeastern U.S., serving approximately 3.4 million customers in Massachusetts, New Hampshire, New York and Rhode Island. National Grid also owns over 4,000 megawatts of contracted electricity generation that provides power to over one million LIPA customers.

Bangor Hydro Electric Company is an electric utility wholly-owned by Emera Inc. Bangor Hydro serves 117,000 customers in an area encompassing 5,275 square miles in eastern and east coastal Maine. Bangor Hydro is a member of the New England Power Pool and is interconnected with other New England utilities to the south and with the New Brunswick Power Corp. to the north. Visit us atwww.bangorhydro.com .

Emera Inc. is a growing energy and services company with $6.5 billion in assets and 2010 revenues of $1.6 billion. The company invests in electricity generation, transmission and distribution, as well as gas transmission and utility energy services. Emera's strategy is focused on the transformation of the electricity industry to cleaner generation and the delivery of that clean energy to market. Emera operates throughout northeastern North America, in three Caribbean countries and in California. More than 80% of the company's earnings come from regulated investments. Emera common and preferred shares are listed on the Toronto Stock Exchange and trade respectively under the symbol EMA and EMA.PR.A. Additional information can be accessed at www.emera.com .

SOURCE: National Grid

 

Views: 149

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Kathy Sherman on December 12, 2014 at 8:53pm
And to think that less than one year ago, Massachusetts Dept. of Public Utilities bought and augmented First Wind's, Dept. of Energy Resources, the MA utilities and even the 'municipal aggregator' of electric supply for Cape Cod and Martha's Vineyard's argument that new transmission was not needed, the costs of it could not be ascribed to particular wind projects and it did not matter if there was a 'highway' for the generation being contracted for 20 years to be paid by MA consumers existed. 'Reliability', a core concept for electricity was apparently an elusive concept for these regulators. All of the above named parties slammed the MA Attorney General's experts and her pleas that the contracts not be approved until costs of transmission were addressed. First Wind had already submitted a plan to FERC asking for approval 'in concept' of something very similar, although likely with Emera rather than the current 'link'. There is no way that the plan for wind developers to purchase the transmission does not totally violate 'open access'. The only possible reasoning would be that there are no other generators who would want to use it because of where it is.

In the story about the transmission, I was curious about the math - 2 to 3 years for site planning and permitting, and 3 years construction, but completion by the end of 2016???

The link on yieldco still leaves me baffled about this pyramid scheme.
Comment by Martha thacker on December 10, 2014 at 2:50pm

Finally read the link re. sale of FW..guess it is not up to FW to build the transmission lines. So finishing up projects would be what? Projects like Bowers Mt.? Never understood megawatts and all that , but 1,100 does not seem like much to build transmission lines over.

http://www.batr.org/corporatocracy/121014.html


 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service