First Wind has submitted the attached condition compliance application for conditions 5 (financial capacity) and 6 (decommissioning) of Department Order #L-25973-24-A-N/L-25973-TG-B-N.  The application was been accepted as complete for processing on January 6, 2015. 

 

Please let me know if you have any questions.

 

Regards,

 

Dan Courtemanch

Environmental Specialist

Maine Department of Environmental Protection

Bingham Wind Project Application

Email: BinghamWindProject.DEP@maine.gov

 

Views: 164

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by alice mckay barnett on January 12, 2015 at 8:37pm

was been?

Comment by alice mckay barnett on January 12, 2015 at 8:33pm

BASED on the above findings of fact, and subject to the conditions listed below, the Department makes the following conclusions pursuant to 38 M.R.S.A. Sections 480-A et seq. and Section 401 of the Federal Water Pollution Control Act: 
A. The proposed activity will not unreasonably interfere with existing scenic, aesthetic, recreational, or navigational uses. 
B. The proposed activity will not cause unreasonable erosion of soil or sediment. 
C. The proposed activity will not unreasonably inhibit the natural transfer of soil from the terrestrial to the marine or freshwater environment. 
D. The proposed activity will not unreasonably harm any significant wildlife habitat, freshwater wetland plant habitat, threatened or endangered plant habitat, aquatic habitat, travel corridor, freshwater, estuarine, or marine fisheries or other aquatic life. 
E. The proposed activity will not unreasonably interfere with the natural flow of any surface or subsurface waters. 
F. The proposed activity will not violate any state water quality law including those governing the classifications of the State's waters. 
G. The proposed activity will not unreasonably cause or increase the flooding of the alteration area or adjacent properties. 
H. The proposed activity is not on or adjacent to a sand dune. 
I. The proposed activity is not on an outstanding river segment as noted in 38 M.R.S.A. Section

Comment by alice mckay barnett on January 10, 2015 at 9:06am

Ask DEP, they are the one and only answering service.  Even Maine Supreme Judicial judges are not sure if they can rule against DEP ruling.   DEP lies in the applications.   Who can make them stop it?

Comment by Penny Gray on January 8, 2015 at 5:31pm

I read it, skimmed through, what struck me were two things:; this was a requirement for First Wind to restore the construction site if they don't complete the project and I couldn't find any reference to requiring that the funds for the restoration of the site (which was nearly five million dollars not including turbines) having to be set aside in advance.  So, if the developer (LLC) declares bankruptcy and walks away, what then? 

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/

© 2024   Created by Webmaster.   Powered by

Badges  |  Report an Issue  |  Terms of Service