I have been informed that the DEP is delaying its decision on whether to permit First Wind's proposed 62+ turbine "Bingham Wind" project until early 2014.

I was under the impression that the Maine Wind Energy Act required projects within the Expedited Area to be permitted within 6 months of the application being accepted as complete for processing. That deadline would be at the end of November 2013. 

Would this delay be cause to require First Wind to reapply? At least 7 local people wrote to the DEP requesting a formal Public Hearing and Intervenor status, but were denied due to not getting comments in within the 20-day deadline from when the application was accepted as complete for processing (even though there was no notice in local papers.)

I know there are a number of major problems with the proposal, and major pieces of information missing from the application. I think we have a chance to challenge this, though even many opponents of the project are claiming this is a "done deal." 

Anyone who believes this does not have to be a done deal, and is interested in circulating petitions (or helping with editing video or website design) and helping organize to support local communities fighting this proposal, please be in touch.

More information: 

http://eastwestwindway.wordpress.com/        (under construction)

http://www.maine.gov/dep/land/sitelaw/selected-developments/

Views: 306

Reply to This

Replies to This Discussion

Bear in mind that while the
MA utilities signed these
contracts, they have not been approved by the MA DPU. Delay past PTC incentive and permitting uncertainty should be brought to the attention of the Mass AG and DPU, along with the fact that generation is not going to contribute to the ISO-NE grid. Keep us posted.

I believe the only way DEP can go beyond the 185 day deadline for decision is with the developer's approval. It's possible that the developer initiated the delay and DEP simply agreed.

From the WEA. See the last sentence. We asked the same question on the Highland project. CITIZENS can't get a time extension when opposing a development, but DEVELOPERS and REGULATORY AGENCIES can extend the time period of the 'expedited' clock. 

 

Sec. B-5. 38 MRSA §344, sub-§2-A, ¶A, (1) The commissioner may not request the board to assume jurisdiction of an application for any permit or other approval required for an expedited wind energy development, as defined in Title 35-A, section 3451, subsection 4, pursuant to the site location of development laws pursuant to chapter 3, subchapter 1, article 6, the Natural Resources Protection Act or storm water management laws or a certification pursuant to Title 35-A, section 3456. Except as provided in subparagraph (2), the commissioner shall issue a decision on an application for an expedited wind energy development within 185 days of the date on which the department accepts the application as complete pursuant to this section or within 270 days of the department's acceptance of the application if the commissioner holds a hearing on the application pursuant to section 345-A, subsection 1-A. (2) The expedited review periods of 185 days and 270 days specified in subparagraph (1) do not apply to the associated facilities, as defined in Title 35-A, section 3451, subsection 1, of the development if the commissioner determines that an expedited review time is unreasonable due to the size, location, potential impacts, multiple agency jurisdiction or complexity of that portion of the development. If an expedited review period does not apply, a review period specified pursuant to section 344-B applies. The commissioner may stop the processing time with the consent of the applicant for a period of time agreeable to the commissioner and the applicant.

Reply to Discussion

RSS

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."