CMP released a route map today for the proposed Haynesville-to-Pittsfield transmission line during an informational meeting held this morning. For the first time, we can see the route CMP is proposing in considerably more detail.
The map also confirms that a significant portion of this project would be new transmission development rather than construction within an existing transmission corridor.
transmission corridor.
The areas highlighted below show (approximately) where there are no existing transmission lines. This will be new development.
The Haynesville-to-Pittsfield transmission line is approximately 108 miles long. Of that, approximately 40 miles is in areas where there is no existing transmission line.
That means roughly 37% of the route would create a new transmission corridor.
That is 40 miles of new clearing and construction, new transmission structures and access roads, and land that will have to be maintained over the life of the project. The towers are expected to be approximately 150 feet tall (that part of the design has not yet been released).
The route may also cross one or more rail trails, including rail trails in Lagrange and Corinna.
The rail trails are important to note because Maine law requires a high-impact electric transmission line crossing or utilizing certain state-designated public lands - including state-owned former railroad rights-of-way used as recreational trails - to receive approval by two-thirds of all members elected to each house of the Legislature. Maine law also created a process for the Bureau of Parks and Lands to establish criteria under which a transmission line crossing certain designated lands would not constitute a reduction or substantial alteration of those lands.
That rulemaking has not been completed.
I have sent several emails to the Bureau of Parks and Lands asking where the rulemaking stands. Their response was essentially that they will let me know when they have something to tell me.
I’m not holding my breath.
From LD 2087, passed in April, 2024:
Until that rulemaking is completed, the statutory requirements remain important for any portion of the proposed route that crosses the affected public lands. And now that CMP has released a route map, we can begin to see exactly where that issue may arise.
The map released today shows the location of the Haynesville substation only as a square. It does not provide a site plan or indicate how much land the new substation will occupy. We don’t yet have the current design details.
However, a Haynesville resident recently showed me a copy of a substation design from 2014 that indicates a footprint of approximately 15 acres. To be clear, this is not a design for the current project and I have not seen a current site plan for the Haynesville substation. (For comparison, CMP’s Coopers Mills Substation in Windsor occupies approximately 17 acres. Coopers Mills has the largest single-voltage source converter (STATCOM) of its kind in North America, so a 15-acre substation is substantial.)
I took a photograph of the 2014 Haynesville substation design. The quality isn’t great, but it gives some perspective on just how large the substation might be.
Is a facility of approximately this size required for a 1,200 MW, 345-kV transmission line?
I don’t know. I’m not an engineer.
But now that CMP has released the route, I think it is reasonable to start asking questions about not just where the line will go, but what will actually be built along it, how much land will be required, and how much will Maine ratepayers actually benefit, including those who will never receive their electricity from this project?
Thanks for reading Landowners' Voice! Subscribe for free to receive new posts and support my work.
https://landownersvoicemaine.substack.com/p/the-northern-maine-transmission-route
Maine just picked winning projects in a regional bid for new generation and transmission. Here’s what we know so far, and what comes next.
By Nathaniel Eisen
September 15, 2026
EXCERPTS
Several wind farms already exist in Northern Maine, including developments in Mars Hill, Oakfield and Columbia. Oakfield, with a capacity of 148 MW, is the largest and would be dwarfed by the proposed Clearway project.
But the transmission line on which the latter two installations send power to southern New England is at capacity. That has thwarted several additional proposed wind generation projects for over a decade.
Prior attempts to independently build new transmission lines to the region—including one by the Maine Electric Power Co., which is jointly owned by CMP and Maine’s other large utility, Versant—have also floundered. Observers described a chicken and egg problem of developers of proposed generation needing guaranteed transmission to secure financing, and vice versa................................................
Neither of the two largest power-consuming states in New England, Massachusetts and Connecticut, will contract for a share of the 800 MW, according to officials with each state’s energy offices.
That could set up a race among the New England states to sign contracts with further wind farms and other would-be generators in Northern Maine to use the remaining 400 MW of line capacity....................................
https://insideclimatenews.org/news/15092026/maine-wind-energy-transmission-winning-proposals/
*************************************
Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.
Dan McKay
The PUC secretive process is very frustrating to landowners and electricity customers.
15 hours ago