LUPC staff say CMP corridor project complies with rules

The Land Use Planning Commission is scheduled to meet Jan. 8 to render a decision on the controversial power corridor.

In a Dec. 30 memo, staff from the Land Use Planning Commission said the power line, called New England Clean Energy Connect, is an allowed use in development districts as planned, as long as CMP follows plans to limit impact on wetlands and recreational areas.

In the protected Kennebec River Gorge and Appalachian Trail, CMP showed there were no alternative building sites and has plans to buffer the power line to limit negative impact to the environment and other uses in those areas, staff concluded.

Commissioners are scheduled to discuss the proposal at a Jan. 8 meeting in Orono.

An endorsement from LUPC, which oversees land use regulations in Maine’s unorganized townships and other remote areas, is among the remaining approvals CMP needs to build a new $1 billion transmission corridor to deliver hydro power from Quebec to Massachusetts.

It is also waiting for a decision from the Maine Department of Environmental Protection and other regional and federal approvals.

Read the full article at:

https://www.pressherald.com/2019/12/31/lupc-staff-say-cmp-corridor-...

Another regulator signals approval of controversial CMP hydropower project

On Monday, staff of the state’s Land Use Planning Commission released a 34-page draft recommendation and a memo to commissioners and intervening parties that proposed approving CMP’s use of land for its controversial New England Clean Energy Connect project, which would pipe hydroelectricity from Canada to Massachusetts through Maine.

The draft recommendation said CMP’s project overall complies with the commission’s land-use standards, although it requires CMP to remove and in some cases add vegetation, assure emergency vehicles can get into the planned hydropower corridor and get applicable construction permits.

It is the second regulator, behind the Maine Public Utilities Commission, to consider a permit for the project. The public utilities commission granted its permit in April.

Read the full article at:

https://bangordailynews.com/2019/12/31/business/another-regulator-s...

************************************* 


Fair Use Notice: This website may reproduce or have links to copyrighted material the use of which has not been expressly authorized by the copyright owner. We make such material available, without profit, as part of our efforts to advance understanding of environmental, economic, scientific, and related issues. It is our understanding that this constitutes a "fair use" of any such copyrighted material as provided by law. If you wish to use copyrighted material from this site for purposes that go beyond "fair use," you must obtain permission from the copyright owner.

Views: 142

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

Comment by Penny Gray on January 1, 2020 at 3:58pm

And the ultimate irony of that would be that all the people so passionately opposing the Hydro-Quebec corridor would just as passionately embrace the buildout of hundreds of wind turbines, the destruction of Maine's mountains, wildlife, rural landscapes and tourism for the sake of southern New England.  All of the arguments, and more, about how the corridor would defile Maine could be made about industrial wind, and should have been, but never were.  This baffles me.

Comment by Dan McKay on January 1, 2020 at 2:28pm

I can tell you one thing, if this project with Hydro-Quebec doesn't happen, CMP or a successive owner  will still own the land that encompasses the corridor and can open it up for 1200 megawatts of wind turbines slicing out even more corridor from turbines to transmission, carving out miles of mountaintops and accelerating the costs to ratepayers of Maine.

Comment by Penny Gray on December 31, 2019 at 5:22pm

Let's hope 2020 brings clear vision and science-based energy solutions that offer far greater protection to Maine's mountains, rural communities, woods, waters and wildlife.  

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."