Deerfield Wind turbines up and operating, but renewables lagging in cold temps



Deerfield Wind turbines
Up and operating
But renewables lagging in cold temps


READSBORO — The controversial Deerfield Wind project that took over 10 years and $7.5 million to complete is now generating power, but regional data shows that renewables are not producing as much energy in these cold winter months as some might have hoped.

The 15-turbine industrial wind plant located in the towns of Searsburg and Readsboro will produce enough renewable energy to power approximately 14,000 Vermont homes annually, according to officials at Avangrid Renewables, the project’s developer. Green Mountain Power has a 25-year contract to purchase the harvested renewable energy from the 30-megawatt facility.

Spokespersons at ISO New England chose not to comment on the efficiency of the Deerfield Wind project, but the nonprofit responsible for overseeing the region’s electric power grid provides daily live charts that show renewables aren’t producing much energy in the cold weather when demand is high.

..... ..... .... ..

According to Linowes, Green Mountain Power signed a contract with Avangrid at an “enormous price” of $88 per megawatt hour, or 8.8 cents per kilowatt hour — significantly higher than what Massachusetts and Connecticut are paying, and far above the market rate of 5.5 cents per kilowatt hour.

“If the energy is very low, if it goes negative, who’s going to pick up the price? Deerfield is always going to get its 8.8 cents per kilowatt hour they (Green Mountain Power) are committed to paying,” Linowes said. “It’s a terrible contract. … I don’t think Vermonters realize how much they are paying for this energy.”

► Source ◄

LI



Views: 55

Comment

You need to be a member of Citizens' Task Force on Wind Power - Maine to add comments!

Join Citizens' Task Force on Wind Power - Maine

 

Maine as Third World Country:

CMP Transmission Rate Skyrockets 19.6% Due to Wind Power

 

Click here to read how the Maine ratepayer has been sold down the river by the Angus King cabal.

Maine Center For Public Interest Reporting – Three Part Series: A CRITICAL LOOK AT MAINE’S WIND ACT

******** IF LINKS BELOW DON'T WORK, GOOGLE THEM*********

(excerpts) From Part 1 – On Maine’s Wind Law “Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine if the law’s goals were met." . – Maine Center for Public Interest Reporting, August 2010 https://www.pinetreewatchdog.org/wind-power-bandwagon-hits-bumps-in-the-road-3/From Part 2 – On Wind and Oil Yet using wind energy doesn’t lower dependence on imported foreign oil. That’s because the majority of imported oil in Maine is used for heating and transportation. And switching our dependence from foreign oil to Maine-produced electricity isn’t likely to happen very soon, says Bartlett. “Right now, people can’t switch to electric cars and heating – if they did, we’d be in trouble.” So was one of the fundamental premises of the task force false, or at least misleading?" https://www.pinetreewatchdog.org/wind-swept-task-force-set-the-rules/From Part 3 – On Wind-Required New Transmission Lines Finally, the building of enormous, high-voltage transmission lines that the regional electricity system operator says are required to move substantial amounts of wind power to markets south of Maine was never even discussed by the task force – an omission that Mills said will come to haunt the state.“If you try to put 2,500 or 3,000 megawatts in northern or eastern Maine – oh, my god, try to build the transmission!” said Mills. “It’s not just the towers, it’s the lines – that’s when I begin to think that the goal is a little farfetched.” https://www.pinetreewatchdog.org/flaws-in-bill-like-skating-with-dull-skates/

Not yet a member?

Sign up today and lend your voice and presence to the steadily rising tide that will soon sweep the scourge of useless and wretched turbines from our beloved Maine countryside. For many of us, our little pieces of paradise have been hard won. Did the carpetbaggers think they could simply steal them from us?

We have the facts on our side. We have the truth on our side. All we need now is YOU.

“First they ignore you, then they laugh at you, then they fight you, then you win.”

 -- Mahatma Gandhi

"It's not whether you get knocked down: it's whether you get up."
Vince Lombardi 

Task Force membership is free. Please sign up today!

Hannah Pingree on the Maine expedited wind law

Hannah Pingree - Director of Maine's Office of Innovation and the Future

"Once the committee passed the wind energy bill on to the full House and Senate, lawmakers there didn’t even debate it. They passed it unanimously and with no discussion. House Majority Leader Hannah Pingree, a Democrat from North Haven, says legislators probably didn’t know how many turbines would be constructed in Maine."

https://pinetreewatch.org/wind-power-bandwagon-hits-bumps-in-the-road-3/